Syllabus Topics
4.1 Two room load bearing single-storey building with verandah
The procedure, once, for every building
- Read the drawings and list the items of work under sub-heads (§3.6).
- Find the wall length by the centre line or long wall – short wall method (Chapter 2). This one length drives most of the estimate.
- Take out the quantities item by item into the measurement sheet, working from the bottom of the foundation upward.
- Apply the deduction rules of §1.4 for openings.
- Analyse the rates (Chapter 6) and abstract the cost (§3.7).
Work bottom-upward and the items come out in a natural order that is hard to forget: excavation → PCC bed → footings → DPC → plinth filling → superstructure masonry → lintels and slab → floor → plaster → doors and windows → finishing.
Items for a two-room building with verandah
| S.N. | Item | Length used | Unit |
|---|---|---|---|
| 1 | Earthwork in excavation in foundation | centre line, breadth of trench | m³ |
| 2 | PCC 1:3:6 bed in foundation | same, breadth of bed | m³ |
| 3 | Masonry in foundation and plinth, footing by footing | same, breadth of each footing | m³ |
| 4 | DPC at plinth level | centre line × wall thickness | m² |
| 5 | Earth filling in plinth | inside dimensions × depth | m³ |
| 6 | Brickwork in superstructure | centre line × thickness × height, less openings | m³ |
| 7 | RCC in lintels, sunshade, slab | from the drawing | m³ |
| 8 | Reinforcement | bar schedule | kg |
| 9 | Doors and windows — frames and shutters | schedule | m³ and m² |
| 10 | Floor finish, plastering inside and outside, painting | areas, less openings by the §1.4 rule | m² |
The three quantities that are always asked
Verandah. A verandah is measured with the building but its walls are usually thinner and it is often open on one or more sides, so its length must be taken separately from the main block. Its plinth area is included in full if it is covered; a projected balcony or open terrace is normally taken at 50%.
Doing it fast — the method that saves the most time
A detail estimate is long but it is not hard. Almost all the time is lost re-deriving lengths that never needed re-deriving. Work in this order and the whole question becomes one table.
1. Get the two centre-line lengths first, and never touch them again.
Half a wall at each end, plus every internal room and every internal wall in between. Write these two numbers in a box at the top of your answer book.
2. Use the ±b rule instead of re-measuring. For an item of breadth b, the long wall is 8.10 + b and the short wall is 4.30 − b. Write the b column down the page first, then fill the two length columns mechanically — no thinking, no drawing:
| Item | b | long wall = 8.10 + b | short wall = 4.30 − b |
|---|---|---|---|
| Earthwork in trench | 0.90 | 9.00 | 3.40 |
| PCC bed | 0.90 | 9.00 | 3.40 |
| 1st footing | 0.70 | 8.80 | 3.60 |
| 2nd footing | 0.50 | 8.60 | 3.80 |
| 3rd footing and plinth | 0.30 | 8.40 | 4.00 |
| Superstructure brickwork | 0.30 | 8.40 | 4.00 |
Six items, and you did one subtraction and one addition each. Every length in the sheet below comes out of this table.
3. Check each row with the centre-line method before you multiply. This is the one check worth its time in an examination, because it catches a wrong length before it is multiplied through three columns. The total centre-line length of this building is fixed:
The two methods must agree exactly, for every value of b. If they do not, you have either miscounted the short walls or used the wrong sign in the ±b rule — and you have found out in ten seconds instead of losing the whole item.
4. Take the deductions in one block at the end, not opening by opening as you go. The volume deducted from brickwork for any opening is simply L × wall thickness × H, and the same L and H serve the plastering deduction (twice, for two faces). One row per opening type, multiplied by the number of them.
5. Fixed order of items. Never hunt for what comes next — it is always this, from the ground upwards:
6. Sanity checks that take five seconds each.
| Quantity | Expected |
|---|---|
| Steel in RCC | 80 to 120 kg per m³ of concrete |
| Bricks | 500 per m³ of brickwork |
| Mortar | 20 to 25% of the volume of masonry |
| Internal plaster area | roughly twice the wall area, because both faces are done |
| Earthwork | always the largest volume on the sheet |
The mistakes that cost marks in this question
| Trap | The rule |
|---|---|
| Counting two short walls | The partition is a short wall too. Here there are three. This is the commonest single mistake in the paper. |
| Using one length for every item | The length changes with b. A 0.90 m trench and a 0.30 m wall do not share a length. |
| Deducting the slab bearing | The bearing of an RCC slab on a wall is never deducted from the brickwork. |
| Deducting small bearings | Bearings up to 500 cm² (0.05 m²) in section are not deducted — a section is an area. |
| Beam depth in a framed building | Measure the beam below the slab: 500 − 125 = 375 mm, or the flange is counted twice. |
| Forgetting the +1 on bars | Number of bars or stirrups = (span / spacing) + 1. |
| Plaster deduction bands | Up to 0.5 m² nothing; 0.5 to 3 m² one face; over 3 m² both faces, adding jambs and soffit. |
| Lintel length | Clear span + 2 bearings, bearing = thickness of the lintel with a minimum of 12 cm — not the clear span. |
Worked estimate — a two-roomed load bearing building
Foundation. Trench 90 cm wide and 1.00 m deep · PCC bed 90 cm wide, 20 cm thick · footings 70 cm (50 cm high), 50 cm (30 cm high) and 30 cm (40 cm high) · plinth 45 cm above ground with a 5 cm DPC.
Superstructure. 30 cm walls 3.00 m high · 10 cm RCC 1:2:4 roof slab with a 50 cm projection all round · 15 cm RCC lintels with 150 mm bearing · 20 cm parapet 90 cm high.
Openings. Door D = 1.2 × 2.1 m (2 no.) · window W1 = 2.0 × 1.5 m (2 no.) · window W2 = 1.5 × 1.5 m (4 no.). Frames 100 × 75 mm.
Step. 3.50 m long at the entrance.
Step 1 — the centre-line lengths. Everything below follows from these two numbers, so they are worked out once and once only:
There are three short walls, not two — the two external end walls and the partition between the rooms. Forgetting the partition is the commonest single mistake in this question.
Length of a lintel. l = clear span + 2 × bearing. Where the bearing is not given, take it as equal to the thickness of the lintel, with a minimum of 12 cm. Here the lintel is 150 mm thick, so the bearing is 150 mm and a 1.20 m door gets a lintel 1.20 + 2(0.15) = 1.50 m long — which is the figure used throughout the sheet below.
Step 2 — the measurement sheet.
Item 1 — Earthwork in excavation in foundation
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Long walls | 2 | 9.00 | 0.90 | 1.00 | 16.200 | L = 8.10 + 0.90 (c/c plus one breadth) |
| Short walls | 3 | 3.40 | 0.90 | 1.00 | 9.180 | L = 4.30 − 0.90; three walls — two external and one partition |
| Entrance step | 1 | 3.70 | 0.50 | 0.10 | 0.185 | 3.70 = 3.50 + 2 × 0.10 |
| Total — Earthwork in excavation in foundation | 25.565 | m³ | ||||
Item 2 — PCC 1:3:6 bed in foundation
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Long walls | 2 | 9.00 | 0.90 | 0.20 | 3.240 | |
| Short walls | 3 | 3.40 | 0.90 | 0.20 | 1.836 | |
| Entrance step | 1 | 3.70 | 0.70 | 0.10 | 0.259 | |
| Total — PCC 1:3:6 bed in foundation | 5.335 | m³ | ||||
Item 3 — First class brickwork in foundation and plinth
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| First footing — 70 cm wide, 50 cm high | ||||||
| Long walls | 2 | 8.80 | 0.70 | 0.50 | 6.160 | L = 8.10 + 0.70 |
| Short walls | 3 | 3.60 | 0.70 | 0.50 | 3.780 | L = 4.30 − 0.70 |
| Second footing — 50 cm wide, 30 cm high | ||||||
| Long walls | 2 | 8.60 | 0.50 | 0.30 | 2.580 | L = 8.10 + 0.50 |
| Short walls | 3 | 3.80 | 0.50 | 0.30 | 1.710 | L = 4.30 − 0.50 |
| Third footing up to plinth — 30 cm wide, 40 cm high | ||||||
| Long walls | 2 | 8.40 | 0.30 | 0.40 | 2.016 | L = 8.10 + 0.30 |
| Short walls | 3 | 4.00 | 0.30 | 0.40 | 1.440 | 0.40 = 0.45 plinth height − 0.05 DPC |
| Entrance step | ||||||
| First footing | 1 | 3.50 | 0.60 | 0.15 | 0.315 | |
| Second footing | 1 | 3.50 | 0.30 | 0.15 | 0.1575 | |
| Total — Brickwork in foundation and plinth | 18.1585 | m³ | ||||
Notice how the length changes for every footing because the breadth changes: the long wall grows and the short wall shrinks by exactly the same amount, so the total length stays 2(8.10) + 3(4.30) throughout. That identity is the arithmetical check on the whole sheet.
Item 4 — 50 mm damp proof course
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Long walls | 2 | 8.40 | 0.30 | — | 5.040 | |
| Short walls | 3 | 4.00 | 0.30 | — | 3.600 | |
| Door openings | 2 | 1.20 | 0.30 | — | −0.720 | no DPC under a door |
| Total — 50 mm damp proof course | 7.920 | m² | ||||
Item 5 — First class brickwork in superstructure
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Main walls — 30 cm thick, 3.00 m high | ||||||
| Long walls | 2 | 8.40 | 0.30 | 3.00 | 15.120 | |
| Short walls | 3 | 4.00 | 0.30 | 3.00 | 10.800 | |
| Parapet wall — 20 cm thick, 90 cm high | ||||||
| Long side | 2 | 9.40 | 0.20 | 0.90 | 3.384 | |
| Short side | 2 | 5.20 | 0.20 | 0.90 | 1.872 | |
| Gross brickwork in superstructure | 31.176 | |||||
| Deductions for openings and lintels | ||||||
| Door openings D, 1.2 × 2.1 | 2 | 1.20 | 0.30 | 2.10 | −1.512 | |
| Window W1, 2.0 × 1.5 | 2 | 2.00 | 0.30 | 1.50 | −1.800 | |
| Window W2, 1.5 × 1.5 | 4 | 1.50 | 0.30 | 1.50 | −2.700 | |
| Lintel over doors | 2 | 1.50 | 0.30 | 0.15 | −0.135 | 150 mm bearing each end |
| Lintel over W1 | 2 | 2.30 | 0.30 | 0.15 | −0.207 | |
| Lintel over W2 | 4 | 1.80 | 0.30 | 0.15 | −0.324 | |
| Total — Brickwork in superstructure, 1:4 cement sand mortar | 24.498 | m³ | ||||
Item 6 — RCC 1:2:4 in slab and lintels
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Roof slab, 100 mm | 1 | 9.40 | 5.60 | 0.10 | 5.264 | 9.40 = 8.10 + 0.30 + 2 × 0.50 projection |
| Lintel over doors | 2 | 1.50 | 0.30 | 0.15 | 0.135 | |
| Lintel over W1 | 2 | 2.30 | 0.30 | 0.15 | 0.207 | |
| Lintel over W2 | 4 | 1.80 | 0.30 | 0.15 | 0.324 | |
| Total — RCC 1:2:4, excluding reinforcement | 5.930 | m³ | ||||
Item 7 — Steel reinforcement
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Slab, at 1% of the volume of concrete | 0.01 × 5.264 × 7850 | 413.224 | density of steel = 7850 kg/m³ | |||
| Lintels, at 1.5% of the volume of concrete | 0.015 × 0.666 × 7850 | 78.4215 | ||||
| Total — Steel reinforcement | 491.6455 | kg | ||||
Where no bar bending schedule is given, reinforcement is taken as a percentage of the volume of concrete — about 1% for a slab, 1.5% for a lintel or beam, 2% for a column and 5% for a footing — converted to weight at the density of steel, 7850 kg/m³. A full bar bending schedule is worked out in §4.2.
Item 8 — Formwork to the slab and lintels
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Slab soffit | 1 | 9.40 | 5.60 | — | 52.640 | |
| Slab vertical edges | 1 | 30.00 | — | 0.10 | 3.000 | perimeter 2 (9.40 + 5.60) = 30.00 m |
| Lintel sides, doors | 4 | 1.50 | — | 0.15 | 0.900 | |
| Lintel soffit, doors | 2 | 1.20 | 0.20 | — | 0.480 | 0.20 = 0.30 − 0.10 taken by the frame |
| Lintel sides, W1 | 4 | 2.30 | — | 0.15 | 1.380 | |
| Lintel soffit, W1 | 2 | 2.00 | 0.20 | — | 0.800 | |
| Lintel sides, W2 | 8 | 1.80 | — | 0.15 | 2.160 | |
| Lintel soffit, W2 | 4 | 1.50 | 0.20 | — | 1.200 | |
| Slab area resting on the long walls | 2 | 8.40 | 0.30 | — | −5.040 | |
| Slab area resting on the short walls | 3 | 4.00 | 0.30 | — | −3.600 | |
| Total — Formwork (centering and shuttering) | 53.920 | m² | ||||
Item 9 — Sal wood in door and window frames
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Doors | 2 | 5.40 | 0.10 | 0.075 | 0.081 | 5.40 = 1.20 + 2 × 2.10 |
| Window W1 | 2 | 8.50 | 0.10 | 0.075 | 0.1275 | 8.50 = 2 × 2.0 + 3 × 1.5 |
| Window W2 | 4 | 9.00 | 0.10 | 0.075 | 0.270 | 9.00 = 2 × 1.5 + 3 × 1.5 |
| Total — Sal wood in door and window frames | 0.4785 | m³ | ||||
Item 10 — 12 mm cement plaster 1:6
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Internal faces | ||||||
| Room 4.5 × 4.0 — four walls | 1 | 17.00 | — | 3.00 | 51.000 | perimeter 2 (4.5 + 4.0) = 17.00 m |
| Room 3.0 × 4.0 — four walls | 1 | 14.00 | — | 3.00 | 42.000 | |
| Ceilings of both rooms | 1 | 4.50 | 4.00 | — | 18.000 | |
| Ceiling of the second room | 1 | 3.00 | 4.00 | — | 12.000 | |
| External faces | ||||||
| Long walls | 2 | 8.70 | — | 3.45 | 60.030 | 3.45 = 0.45 plinth + 3.00 storey height |
| Short walls | 2 | 4.60 | — | 3.45 | 31.740 | |
| Deductions for openings, both faces | ||||||
| Doors | 4 | 1.20 | — | 2.10 | −10.080 | |
| Window W1 | 4 | 2.00 | — | 1.50 | −12.000 | |
| Window W2 | 8 | 1.50 | — | 1.50 | −18.000 | |
| Total — 12 mm cement plaster 1:6 | 174.690 | m² | ||||
Openings over 3 m² are deducted on both faces, which is why each opening appears with twice its number in the deduction rows. A window of 1.5 × 1.5 = 2.25 m² would strictly be deducted on one face only (§1.4); it is deducted on both here because both faces of these walls are plastered and the reveals are then measured separately — state whichever convention you adopt.
Step 3 — abstract of cost. The quantities are carried forward and priced. The rates below are illustrative; in the examination take them from the district rate or from your own rate analysis, and say so.
Abstract of cost
| S.N. | Description of item | Quantity | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in ordinary soil | 25.565 | m³ | 400.00 | 10,226.00 |
| 2 | PCC 1:3:6 in foundation | 5.335 | m³ | 9,000.00 | 48,015.00 |
| 3 | First class brickwork in foundation and plinth | 18.159 | m³ | 11,000.00 | 199,743.50 |
| 4 | 50 mm damp proof course | 7.920 | m² | 700.00 | 5,544.00 |
| 5 | First class brickwork in superstructure, 1:4 | 24.498 | m³ | 12,500.00 | 306,225.00 |
| 6 | RCC 1:2:4 in slab and lintels | 5.930 | m³ | 15,000.00 | 88,950.00 |
| 7 | Steel reinforcement | 491.646 | kg | 120.00 | 58,997.46 |
| 8 | Formwork to slab and lintels | 53.920 | m² | 650.00 | 35,048.00 |
| 9 | Sal wood in door and window frames | 0.479 | m³ | 160,000.00 | 76,560.00 |
| 10 | 12 mm cement plaster 1:6 | 174.690 | m² | 350.00 | 61,141.50 |
| Total cost of works | 890,450.46 | ||||
| Add: contingencies @ 3% | 26,713.51 | ||||
| Add: work-charged establishment @ 2% | 17,809.01 | ||||
| Estimated cost | 934,972.98 | ||||
Estimated cost of the building ≈ Rs 934,973, to which must still be added the flooring, painting, door and window shutters, and the provisions for water supply and sanitary work (8–10%) and electrification (8–10%).
Deductions for openings in brickwork. Deduct the full volume of each door and window opening (area of opening × thickness of wall) and the volume of the lintel over it, since the lintel is measured separately as RCC. Do not deduct for lintel bearings up to 0.1 m³, or for openings up to 0.1 m² (§1.4).
Geometry and item sequence after Er. N. P. Dawadi's worked example; every quantity recomputed here from the dimensions.
4.2 Four room frame structured building with reinforcement calculations
A framed building differs from a load-bearing one in what carries the load, and therefore in what is measured:
| Load bearing | RCC framed | |
|---|---|---|
| Foundation | Continuous strip under every wall | Isolated footings under each column, measured by number |
| Vertical load path | The wall itself | Columns; the wall is only an infill panel |
| Wall thickness | Thick — 230 to 350 mm | Thin — often 115 mm partition, 230 mm external |
| Length used | Centre line of the walls | Column centres; beams measured clear between columns |
| Dominant item | Masonry | RCC and reinforcement |
Order of taking out a framed building
- Excavation for each isolated footing — number × length × breadth × depth.
- PCC bed, footing pad, and the column pedestal below plinth.
- Columns from footing top to slab soffit, then plinth beams, then floor beams.
- Slab — area × thickness, deducting large voids only.
- Infill brickwork panel by panel, deducting openings.
- Reinforcement, from the bar bending schedule.
Reinforcement calculation
This is the part that carries the marks. Steel is measured as the length of each bar in place, converted to weight:
| Bar ø (mm) | 8 | 10 | 12 | 16 | 20 | 25 |
|---|---|---|---|---|---|---|
| kg per metre | 0.395 | 0.617 | 0.888 | 1.580 | 2.469 | 3.858 |
Cutting length is the clear length plus hooks and bends, less the cover:
Two rules save marks: always add 1 when counting stirrups or bars from a spacing, and remember that binding wire and rolling margin are not measured separately — they are inside the rate.
Worked estimate — a four-roomed framed building
Footings. Isolated pads 1.80 × 1.80 × 0.45 m on a 2.00 × 2.00 × 0.10 m PCC 1:3:6 bed, in a pit 2.20 × 2.20 × 1.50 m.
Columns 400 × 400 mm, 3.00 m clear, 8–16 mm bars with 8 mm ties at 150 mm c/c. Pedestals 1.05 m high below plinth.
Beams 250 × 500 mm overall, 5.00 m clear span — 12 beams. Slab 125 mm over 10.60 × 10.60 m.
Item 1 — Earthwork and bedding
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Isolated pits | 9 | 2.20 | 2.20 | 1.50 | 65.340 | one pit per column |
| Total — Earthwork in excavation for the footings | 65.340 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Under each pad | 9 | 2.00 | 2.00 | 0.10 | 3.600 | |
| Total — PCC 1:3:6 bed under the footings | 3.600 | m³ | ||||
Item 2 — RCC in the frame
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Footing pads | 9 | 1.80 | 1.80 | 0.45 | 13.122 | |
| Pedestals below plinth | 9 | 0.40 | 0.40 | 1.05 | 1.512 | |
| Columns above plinth | 9 | 0.40 | 0.40 | 3.00 | 4.320 | |
| Beams | 12 | 5.00 | 0.25 | 0.375 | 5.625 | depth below the slab = 0.500 − 0.125 |
| Slab, 125 mm | 1 | 10.60 | 10.60 | 0.125 | 14.045 | 10.60 = 10.00 + 2 × 0.30 overhang |
| Total — RCC 1:1½:3 in the frame | 38.624 | m³ | ||||
The beam depth is measured below the slab, 500 − 125 = 375 mm. Measuring the full 500 mm would count the flange twice, since the slab has already been measured right across the beams. This is the single commonest error in a framed-building estimate.
Item 3 — Formwork
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Sides of the footing pads | 36 | 1.80 | — | 0.45 | 29.160 | |
| Sides of the pedestals | 36 | 0.40 | — | 1.05 | 15.120 | |
| Sides of the columns | 36 | 0.40 | — | 3.00 | 43.200 | |
| Beam sides | 24 | 5.00 | — | 0.375 | 45.000 | |
| Beam soffits | 12 | 5.00 | 0.25 | — | 15.000 | |
| Slab soffit | 1 | 10.60 | 10.60 | — | 112.360 | |
| Slab area occupied by the beams | 12 | 5.00 | 0.25 | — | −15.000 | |
| Total — Formwork | 244.840 | m² | ||||
Item 4 — Bar bending schedules
Bar bending schedule — one column C1, 400 × 400 mm, 3.00 m high
| Bar | ø (mm) | No. | Cutting length (m) | Total length (m) | kg/m | Weight (kg) | Remarks |
|---|---|---|---|---|---|---|---|
| Main bars, 16 mm | 16 | 8 | 3.60 | 28.80 | 1.580 | 45.51 | 3.00 clear height + 0.60 lap and bend |
| Lateral ties, 8 mm | 8 | 21 | 1.12 | 23.52 | 0.395 | 9.29 | n = 3000/150 + 1 = 21 · length = 2(0.32 + 0.32) − bends + 2 × 9d hooks |
| Total weight of steel | 54.80 | kg | |||||
Bar bending schedule — one beam B1, 250 × 500 mm, 5.00 m clear span
| Bar | ø (mm) | No. | Cutting length (m) | Total length (m) | kg/m | Weight (kg) | Remarks |
|---|---|---|---|---|---|---|---|
| Bottom straight, 20 mm | 20 | 2 | 5.65 | 11.30 | 2.469 | 27.90 | 5.00 clear + 2 × 0.23 bearing − 2 × 0.025 cover + 2 × 9d hooks |
| Bottom bent-up, 20 mm | 20 | 2 | 5.87 | 11.74 | 2.469 | 28.99 | adds 2 × 0.42 D, with D = 0.45 − 0.19 = 0.26 m |
| Top anchor, 12 mm | 12 | 2 | 5.46 | 10.92 | 0.889 | 9.71 | 5.00 + 2 × 0.23 bearing |
| Stirrups, 8 mm | 8 | 34 | 1.36 | 46.24 | 0.395 | 18.27 | n = 5000/150 + 1 = 34 · length = 2(0.20 + 0.45) − bends + 2 × 9d |
| Total weight of steel | 84.86 | kg | |||||
Steel in a framed building normally works out to 80–120 kg per m³ of concrete overall, or roughly 4–6 kg per m² of built-up area. The figure above is lower because the slab and footing reinforcement has not yet been added. A result far outside that band means an error in the cutting length or the bar count — check before writing it down.
Bar bending rules after IS 2502; frame arrangement after Dawadi, Beam, slab and pillar.
4.3 Septic tank with soak pit
A septic tank is a watertight settling chamber that treats sewage from a building where no public sewer exists; the effluent then percolates into the ground through a soak pit (soakaway).
Sizing
The tank is deliberately made long and narrow. The sewage has to travel the length of the tank while it settles, so a squat tank short-circuits and settles badly. That is also why a baffle wall is set about 0.80 m from the inlet — it stops the incoming flow from disturbing the scum.
Worked estimate — septic tank for 25 users, with soak pit
Step 1 — capacity and internal size
Step 2 — measurement sheet for the tank
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| For the tank, including working space | 1 | 4.10 | 1.90 | 2.05 | 15.9695 | 4.10 = 3.30 + 2 (0.23 wall + 0.17 working space) |
| Total — Earthwork in excavation | 15.9695 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Under the base slab | 1 | 3.76 | 1.56 | 0.10 | 0.58656 | |
| Total — PCC 1:3:6 levelling course | 0.58656 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Base slab, 150 mm | 1 | 3.76 | 1.56 | 0.15 | 0.87984 | 3.76 = 3.30 + 2 × 0.23 wall thickness |
| Top slab, 120 mm | 1 | 3.76 | 1.56 | 0.12 | 0.70387 | |
| Manhole opening 0.60 × 0.60 | 1 | 0.60 | 0.60 | 0.12 | −0.0432 | |
| Total — RCC 1:2:4 in the base and top slabs | 1.54051 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Long walls, 230 mm | 2 | 3.76 | 0.23 | 1.80 | 3.11328 | measured out to out |
| Short walls, 230 mm | 2 | 1.10 | 0.23 | 1.80 | 0.9108 | measured in to in |
| Baffle wall, 115 mm | 1 | 1.10 | 0.115 | 1.50 | 0.18975 | set 0.80 m from the inlet |
| Total — Brick masonry in 1:4 cement sand mortar | 4.21383 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Internal faces of the walls | 1 | 8.80 | — | 1.80 | 15.840 | internal perimeter 2 (3.30 + 1.10) = 8.80 m |
| Internal floor | 1 | 3.30 | 1.10 | — | 3.630 | |
| Both faces of the baffle wall | 2 | 1.10 | — | 1.50 | 3.300 | |
| Total — Waterproof cement plaster 1:2 inside, 20 mm thick | 22.770 | m² | ||||
The internal plaster of a septic tank is specified 20 mm thick in 1:2 cement sand mortar with a waterproofing compound — richer and thicker than ordinary 12 mm plaster, because the tank must stay watertight. No plaster is measured on the scum board.
Step 3 — inspection chamber
An inspection chamber is built between the septic tank and the soak pit so that the effluent line can be opened, inspected and cleared. It is a small covered masonry box with a benched and channelled floor, and it is measured as a separate item:
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Earthwork in excavation | 1 | 1.20 | 1.20 | 1.05 | 1.512 | |
| PCC 1:3:6 bed | 1 | 1.06 | 1.06 | 0.10 | 0.11236 | |
| Brick masonry walls, 230 mm | 4 | 0.83 | 0.23 | 0.80 | 0.61088 | mean length round the chamber |
| RCC 1:2:4 cover slab, 100 mm | 1 | 1.06 | 1.06 | 0.10 | 0.11236 | |
| (read row by row — the items go separately to the abstract) | 2.3476 | m³ | ||||
Where the cover slab carries a manhole opening, remember the IS 1200 rule: an opening larger than 0.1 m² is deducted, a smaller one is not. A 0.45 × 0.45 m cover is 0.2025 m² and therefore is deducted.
Step 4 — soak pit
The soak pit lining is honeycomb brickwork precisely so that effluent can escape through it — and honeycomb brickwork is measured in m², not m³ (§1.2). That is a favourite one-mark question.
Items to be measured
| Item | How measured | Unit |
|---|---|---|
| Earthwork in excavation | outside dimensions of the tank plus working space, × depth | m³ |
| PCC bed below the base slab | outside plan area × thickness | m³ |
| RCC base slab, walls and top slab | from the section | m³ |
| Brick masonry walls | centre line × thickness × height | m³ |
| Baffle wall / partition | separately | m³ |
| Cement plaster with waterproofing, inside | internal wet area and base, 20 mm in 1:2 mortar | m² |
| Reinforcement | bar schedule | kg |
| Inspection chamber between tank and soak pit | excavation, PCC, masonry, cover slab — measured as a separate small structure | m³ and no. |
| Manhole cover and frame, vent pipe, inlet and outlet T-pipes | counted | number |
| Soak pit — excavation, honeycomb lining, boulder and gravel filling | volume and surface of the pit | m³ and m² |
Dawadi, RCC T-beam, well, septic, caisson, pier; sizing per the standard septic tank design practice.
4.4 Underground water tank
An underground water tank (reservoir) is estimated exactly like a septic tank but is designed to hold clean water, so the whole shell is watertight RCC and the internal finish matters.
Sizing
Remember 1 m³ = 1000 litres. A tank for 20 people at 135 l/head/day for one day needs 2700 litres = 2.7 m³, plus free board.
Worked estimate — RCC underground water tank
Adopted: internal size 5.00 × 3.00 m, depth 3.00 m · walls 200 mm RCC 1:2:4 · base slab 150 mm · top slab 150 mm · PCC 1:3:6 bed 100 mm · 500 mm iron manhole cover.
Step 1 — check the capacity
Step 2 — the measurement sheet
Item 1 — Earthwork and bedding
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| For the tank | 1 | 5.40 | 3.40 | 3.25 | 59.670 | 5.40 = 5.00 + 2 × 0.20 · 3.40 = 3.00 + 2 × 0.20 · 3.25 = 3.00 + 0.15 slab + 0.10 PCC |
| Total — Earthwork in excavation | 59.670 | m³ | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Under the base slab | 1 | 5.40 | 3.40 | 0.10 | 1.836 | |
| Total — PCC 1:3:6 levelling course | 1.836 | m³ | ||||
Item 2 — RCC 1:2:4, excluding reinforcement
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Base slab, 150 mm | 1 | 5.40 | 3.40 | 0.15 | 2.754 | |
| Side walls — 200 mm thick, 3.00 m high | ||||||
| Long walls | 2 | 5.40 | 0.20 | 3.00 | 6.480 | measured out to out |
| Short walls | 2 | 3.00 | 0.20 | 3.00 | 3.600 | measured in to in |
| Top slab cover, 150 mm | 1 | 5.40 | 3.40 | 0.15 | 2.754 | |
| Deduction for the 500 mm circular manhole | − ( π × 0.50² / 4 ) × 0.15 | -0.02945 | ||||
| Total — RCC 1:2:4 in the tank | 15.55855 | m³ | ||||
Item 3 — Steel reinforcement
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| At 1% of the volume of RCC | 0.01 × 15.559 × 7850 | 1,221.3460 | density of steel = 7850 kg/m³ | |||
| Total — Steel reinforcement | 1,221.3460 | kg | ||||
Item 4 — Formwork and finishing
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Wall inner faces | 1 | 16.00 | — | 3.00 | 48.000 | internal perimeter 2 (5.00 + 3.00) = 16.00 m |
| Wall outer faces | 1 | 17.60 | — | 3.00 | 52.800 | external perimeter 2 (5.40 + 3.40) = 17.60 m |
| Soffit of the top slab | 1 | 5.00 | 3.00 | — | 15.000 | |
| Total — Formwork | 115.800 | m² | ||||
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Internal faces of the walls | 1 | 16.00 | — | 3.00 | 48.000 | |
| Internal floor | 1 | 5.00 | 3.00 | — | 15.000 | |
| Total — Waterproof cement plaster 1:3 | 63.000 | m² | ||||
Item 5 — Fittings
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| 500 mm dia. iron manhole cover | 1 | — | — | — | 1.00 | number |
| Iron steps built into the wall | 6 | — | — | — | 6.00 | number |
| 25 mm dia. GI inlet pipe | 1 | 10.00 | — | — | 10.00 | running metre |
| 20 mm dia. GI outlet pipe | 1 | 5.00 | — | — | 5.00 | running metre |
| 20 mm dia. overflow pipe | 1 | 2.00 | — | — | 2.00 | running metre |
| 20 mm dia. drain pipe | 1 | 5.00 | — | — | 5.00 | running metre |
Pipes, valves and fixtures of different sizes are counted or measured in running metre from the drawing, each size as a separate item — they are never lumped together.
Items to be measured
- Earthwork in excavation — outside dimensions plus working space, to the full depth; classed by soil, and separately below the water table.
- PCC levelling course under the base slab.
- RCC base slab, walls and top slab, with the manhole deducted.
- Reinforcement from the bar schedule, or as a percentage of the concrete.
- Formwork to both faces of the walls and to the soffit of the top slab.
- Waterproof cement plaster inside, and plaster outside.
- Manhole cover, rungs, vent, inlet, outlet, overflow and washout pipes.
- Backfilling in layers around the tank, and disposal of surplus earth.
Note the difference from a building: for a tank the internal dimensions are fixed by the capacity, so the centre-line perimeter is found by adding one wall thickness to each internal dimension — the mirror image of the crossing method in §2.3.
Geometry after Dawadi, 1 km highway, RCC water tank and building §6.12; every quantity recomputed here from the dimensions.
Sources consulted for this chapter
These are the references actually used in writing this chapter. Where a worked example is taken from one of them, the figure or the sheet is recomputed here from the stated dimensions rather than transcribed.
- Er. Narayan Prasad Dawadi, Estimating and Costing lecture notes (IOE, Pashchimanchal Campus) — the two-roomed load bearing building and the RCC underground water tank — geometry and item sequence of the worked sheets
- M. Chakraborti, Estimating, Costing and Specification in Civil Engineering — ch. III estimate of buildings, ch. IV RCC works, ch. VI water supply and sanitary works (septic tank and reservoir)
- B. N. Dutta, Estimating and Costing in Civil Engineering — ch. 1 — length of a lintel (clear span + 2 bearings, bearing = thickness of lintel, minimum 12 cm) and the mean-length rule for arch masonry
- IS 1200 — Method of Measurement of Building and Civil Engineering Works — mode of measurement and the deduction rules used in the sheets
- Pandey & Katwal, Complete Manual of Estimating and Costing (T.U., B.E. Civil) — the septic tank – inspection chamber – soak pit sequence, the 20 mm waterproofed 1:2 plaster inside a tank, and the rule that a manhole cover over 0.1 m² is deducted
- Notes by RK Sir (course handwritten notes) — reinforcement taken as a percentage of the volume of concrete