Syllabus Topics
- 3.1 Approximate estimate, purpose and methods
- 3.2 Detailed estimate
- 3.3 Revised estimate
- 3.4 Supplementary estimate
- 3.5 Complete estimate
- 3.6 Splitting of cost of building, road, water supply and sanitary works into sub-heads
- 3.7 Detail estimation formats (summary of cost, detail quantity estimate, analysis of rate, abstract of cost and bill of quantities)
- ◆ Sources consulted
3.1 Approximate estimate, purpose and methods207620732068
Past Exam Questions on this Topic
- What are the different methods of preparing approximate estimate? Write the suitability of each method. [6] (2073 Shrawan, Q.2(a))
Solution
Methods of preparing an approximate estimate, and the suitability of each
Method How the cost is found Suitable for 1. Plinth area method Plinth area (measured to the outer face of the walls) × plinth area rate of a recently built similar building The commonest method for buildings of all kinds, where a comparable recent building exists 2. Cubical content method Plinth area × height (plinth level to half the roof height) × rate per m³ Buildings where the height differs from the norm — halls, theatres, godowns — because it accounts for storey height, which the plinth area method ignores. More accurate than method 1 3. Unit base / service unit method Number of functional units × cost per unit — per bed, per student, per seat, per vehicle Buildings defined by capacity: hospitals (per bed), schools (per student), cinemas (per seat), hostels (per resident) 4. Approximate quantity method The work is split into a few major items (foundation, superstructure) and the running metre or bulk quantity of each is priced Boundary walls, roads, canals, water lines — long structures of uniform section. The most accurate of the approximate methods 5. Typical bay method Cost of one typical bay × number of bays, end bays taken separately Long repetitive structures — sheds, barracks, factory buildings 6. Cost comparison / per-km method Cost of a completed similar work, scaled by length, capacity or a cost index Roads (per km), pipelines, transmission lines Accuracy rises down the table and so does the effort. Methods 1–3 need only one overall figure; method 4 needs a preliminary layout. All of them are used before detailed drawings exist, which is exactly why none can be as accurate as a detailed estimate.
ENCE 351 §3.1.
- Explain why approximate estimate of any structure is done before the detailed estimate and final cost is worked out. [4] (2068 Baishakh, Q.1(c))
Solution
Why an approximate estimate is made before the detailed estimate
- At the proposal stage the detailed drawings and specifications do not yet exist, so a detailed estimate is simply impossible. Only an overall parameter — plinth area, cube content, number of beds — is known.
- An approximate estimate is quick and cheap; a detailed estimate takes weeks of work. There is no sense in spending that effort on a scheme that may never be approved.
- It allows the competent authority to decide whether the scheme is worth pursuing and to grant administrative approval, and allows the amount to be provided in the budget.
- It allows alternative schemes, sites and designs to be compared on cost before one is selected for detailed design.
- It fixes the order of magnitude, so the detailed estimate prepared later can be checked against it — a large discrepancy signals an error in one of them.
- It lets the funding, land acquisition and clearances be started early, in parallel with the detailed design.
The relationship is one of successive refinement: rough cost → approximate estimate (administrative approval) → detailed estimate (technical sanction) → tendered cost → actual cost. Each stage narrows the band of uncertainty.
ENCE 351 §3.1.
- a) What do you understand by approximate estimate? When do you need revised estimate?
- b) Prepare a preliminary estimate of six storied framed structure office building having a total carpet area
Solution
a) Approximate estimate, and when a revised estimate is needed
Approximate estimate. A rough estimate of the probable cost of a work, prepared at the proposal stage before detailed drawings and specifications exist, from a single overall parameter such as the plinth area, the cube content or the number of service units. It is supported by a report, a site plan and line drawings.
It is prepared in order to:
- judge whether the scheme is financially feasible and worth pursuing at all;
- obtain administrative approval from the competent authority;
- provide the amount in the annual budget;
- compare alternative schemes and sites on cost before one is chosen; and
- fix the order of magnitude, against which the detailed estimate prepared later can be checked.
It is accurate to about ±15–20% only, and cannot be used for technical sanction or for inviting tenders.
Revised estimate. A fresh detailed estimate prepared for a work that has already been sanctioned. It is needed when:
- the expenditure exceeds, or is likely to exceed, the sanctioned amount by more than 5%;
- the rates adopted in the original estimate have changed materially;
- there is a substantial change in the design, specification or scope of the work;
- site conditions turn out to differ from those assumed — rock instead of soil, a high water table, a longer lead; or
- the work was abandoned and is being restarted after a long interval.
It shows the original and the revised quantity and cost of every item side by side, with the reason for each variation, and must be sanctioned afresh by the competent authority before the extra expenditure is incurred.
b) Preliminary estimate of a six-storeyed framed office building
The carpet area printed in the question paper is not legible in the available copy. A total carpet area of 3000 m² is assumed below; substitute the figure given in your paper — the method is unchanged.
Six-storeyed RCC framed office building · total carpet area 3000 m²
Assumed: carpet area = 60% of plinth area (office building with corridors, stairs, lift and toilets) · plinth area rate Rs 30,000 per m²Convert carpet area to plinth area
plinth area = carpet area / 0.60 = 3000 / 0.60 = 5000 m² (total, all six floors) per floor = 5000 / 6 = 833.33 m²Cost of the building by the plinth area method
cost of building = plinth area × plinth area rate = 5000 × 30,000 = Rs 15,00,00,000Add the external services and other provisions
cost of building Rs 15,00,00,000 water supply and sanitary installation @ 8% Rs 1,20,00,000 internal electrification @ 8% Rs 1,20,00,000 lift and fire fighting installation @ 5% Rs 75,00,000 architectural / elevation treatment @ 1% Rs 15,00,000 approach road, paving, compound wall @ 2% Rs 30,00,000 ---------------- Rs 18,60,00,000 contingencies @ 3% Rs 55,80,000 work-charged establishment @ 2% Rs 37,20,000 ---------------- approximate estimated cost Rs 19,53,00,000Preliminary estimated cost of the six-storeyed office building ≈ Rs 19.53 crore, i.e. about Rs 39,060 per m² of plinth area.Two things carry the marks here: converting carpet area to plinth area (carpet area is the usable area only, and never equals the plinth area), and adding the external services as percentages. State every assumed percentage explicitly — an approximate estimate is only as good as its stated assumptions.
ENCE 351 §3.1 and §3.3.
An approximate estimate — also called a rough, preliminary or budgetary estimate — finds the probable cost of a work quickly, before the detailed drawings exist. It is prepared at the proposal stage so that the authority can decide whether the scheme is worth pursuing and how much money to provide.
When and why it is prepared
- To decide the financial policy — can the department afford it?
- To obtain administrative approval and provide for the work in the budget.
- To compare alternative proposals and choose between them.
- When there is no time or no detailed drawing for a full estimate.
It is supported by a report explaining the necessity of the work, a site or index plan, and the rate assumed per unit, with the basis on which that rate was taken.
Methods of preparing an approximate estimate
| Method | Basis | Suitable for |
|---|---|---|
| Plinth area method | Plinth area × plinth area rate. The plinth area is measured to the outer face of the walls at floor level. | Buildings — the commonest method of all |
| Cubical content method | Plinth area × height × a rate per m³, the height measured from floor level to the top of the roof. | Buildings where height matters — halls, cinemas, godowns. More accurate than plinth area. |
| Unit base (service unit) method | Cost per functional unit × number of units. | School per classroom or per student, hospital per bed, cinema per seat, irrigation per hectare, water tank per litre, road per kilometre |
| Approximate quantity method | The work is divided into two blocks — foundation and superstructure — and the running metre of wall in each is priced. | Boundary walls, small buildings; more accurate than the plinth area method |
| Bay method | Cost of one bay × number of bays. | Repetitive structures — sheds, barracks |
| Cost comparison with a similar structure | The known cost of a completed similar work, corrected for size, time and locality. | Any work for which a close precedent exists |
Accuracy improves down the table: plinth area is the crudest, approximate quantity the closest to a detailed estimate. Whichever is used, a contingency of 3–5% is added, and the estimate is expected to be within about 5–10% of the detailed figure.
Dawadi, chapter 3 estimating §3.1; Pandey & Katwal, Complete Manual §3.1.
3.2 Detailed estimate2082208120802078207420732068
Past Exam Questions on this Topic
- List various methods of quantity estimate. Describe bill of quantities (BOQ) and preparation of detailed estimate of any project. [1+2+2] (2082 Bhadra, Q.2)The first part also belongs to Chapter 2 and the BOQ part to Section 3.7.
Solution
a) Methods of quantity estimate
- Long wall — short wall method
- Centre line method
- Crossing method
- Bay method
b) Bill of quantities (BOQ)
A bill of quantities is a tabulated schedule of every item of work in a project, giving a brief description of the item, the estimated quantity, the unit, the rate and the amount. It is issued with the tender documents so that all contractors price the same quantities and their offers can be compared item by item; it is afterwards used to measure and pay for the work actually done and to value variations.
S.N. Description of item Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation in ordinary soil 120.00 m³ 350.00 42,000.00 2 PCC 1:3:6 in foundation 18.50 m³ 9,000.00 1,66,500.00 Total 2,08,500.00 c) Preparation of a detailed estimate of a project
- Collect the data — complete drawings, specifications, the district rate and the departmental norms.
- List the items of work under sub-heads, in the order of construction.
- Find the wall length by the centre line or long wall–short wall method.
- Take out the quantities item by item on the measurement sheet (number × length × breadth × height), applying the deduction rules of IS 1200.
- Analyse the rate of each item from the norms and the district rate.
- Prepare the abstract of cost — quantity × rate = amount for every item, and total it.
- Add contingencies (3–5%) and work-charged establishment (1.5–2%), and the provisions for sanitary, water supply and electrical work (8–10% each).
- Write the report and attach the drawings, specifications, rate analysis and the abstract, and submit for technical sanction.
ENCE 351 Chapter 2, §3.2 and §3.7.
- Briefly describe the components of detail estimation report with their format for a road project. [4] (2081 Bhadra, Q.4)
Solution
Components of a detailed estimate report for a road project, with their format
- Title page, index and approval sheet.
- Report — the need for the road, the traffic it will carry, the alignment chosen and the alternatives rejected, the design standard (road class, formation width, pavement type), the survey carried out and the basis of the rates.
- Drawings — index map, alignment plan, longitudinal section showing ground and formation levels, typical and actual cross-sections at every chainage, and drawings of the cross-drainage and protection works.
- Earthwork calculation sheet, chainage by chainage:
Chainage GL (m) FL (m) Depth of cut (m) Height of fill (m) Area (m²) Mean area (m²) Length (m) Vol. cutting (m³) Vol. filling (m³) 0+000 100.00 98.80 1.20 — 14.88 — — — — 0+030 100.50 98.50 2.00 — 28.00 21.44 30 643.20 — - Detailed measurement sheets for the pavement layers, cross drainage structures, retaining and breast walls, side drains and road furniture.
- Analysis of rates for every item, based on the district rate and the departmental norms, with a lead statement for each material from its quarry or market.
- Detailed abstract of cost — item, quantity, unit, rate, amount.
- Summary / general abstract under sub-heads:
S.N. Sub-head Amount (Rs) 1 Site clearance and earthwork … 2 Pavement (sub-base, base, surfacing) … 3 Cross drainage works (culverts, causeways) … 4 Protection works (retaining, breast, toe walls, gabions) … 5 Side drains and catch drains … 6 Road furniture, signs, markings, km stones … 7 Bio-engineering and slope protection … Add contingencies @ 3–5% … Add work-charged establishment @ 1.5–2% … Total estimated cost … - Bill of quantities for tendering.
- Specifications of every item, and the land acquisition and compensation statement.
What makes a road estimate report different from a building one is the longitudinal section and the chainage-wise earthwork sheet — a road has no plan of rooms to measure, so the L-section is the primary document.
ENCE 351 §3.2, §3.6 and §5.4.
- Explain different data required and subheads to included in detail estimation report of an irrigation project. [6] (2081 Bhadra, Q.10)The sub-heads part of this question also belongs to Section 3.6.
Solution
a) Data required for a detailed estimate of an irrigation project
- Topographical survey — contour plan of the command area, longitudinal section and cross-sections of the canal alignment.
- Hydrological data — the discharge of the source river, its variation through the year, and the dependable flow.
- Agricultural data — the culturable command area (CCA), the crops and their duty and delta, and hence the design discharge of the canal.
- Soil investigation — the nature of the soil along the alignment, its permeability (which decides whether lining is needed) and its bearing capacity.
- Canal design data — bed width, full supply depth, side slope, bed slope, freeboard and the type and thickness of lining.
- Details of structures — head works, head regulator, cross regulators, falls, outlets, aqueducts, culverts and escapes.
- Land acquisition details and compensation rates.
- Rates — the district rate, the departmental norms, and the lead of each material from its quarry.
- Environmental and social data — IEE/EIA requirement, resettlement.
b) Sub-heads to be included in the estimate report
S.N. Sub-head Typical items 1 Preliminary works Survey, investigation, soil testing, design and drawing 2 Land acquisition and compensation Land for the canal, structures and inspection road; crop and structure compensation 3 Head works Diversion weir or intake, head regulator, silt-excluder, river training and bank protection 4 Main canal Clearing, earthwork in excavation and in embankment, dressing and trimming, lining of bed and sides 5 Branch canals, distributaries and water courses The same items, taken reach by reach 6 Canal structures Cross regulators, falls, outlets, aqueducts, syphons, culverts, escapes, bridges 7 Drainage works Field drains, cross drainage, catch drains 8 Inspection road and service path Along the canal bank 9 Buildings Office, store, staff quarters, gauge stations 10 Miscellaneous Turfing, plantation, boundary pillars, gauges and measuring devices 11 Environmental mitigation As per the IEE / EIA Add contingencies @ 3–5% Add work-charged establishment @ 1.5–2% ENCE 351 §3.2, §3.6 and §5.6.
- Prepare a detail estimate report for small sewerage project. [6] (2080 Bhadra, Q.6)
Solution
Detailed estimate report for a small sewerage project
1. Report. The population to be served, the present method of disposal and its defects, the sewerage scheme proposed, the outfall and the treatment adopted, and the basis of the design and of the rates.
2. Design data
- Present and design population (design period usually 20–30 years).
- Water supply rate per head per day; sewage ≈ 80% of the water supplied.
- Peak factor, and the infiltration allowance.
- Design discharge, and hence the size and gradient of each sewer (self-cleansing velocity 0.6–0.8 m/s, maximum 3 m/s).
3. Drawings. Index map, layout of the sewer network with manhole numbers, longitudinal section of each sewer line showing ground level, invert level and depth, standard drawings of manholes, and drawings of the treatment unit and outfall.
4. Sub-heads and items of work
S.N. Sub-head Items Unit 1 Preliminary Survey, investigation, design and drawing LS 2 Earthwork Excavation of trench by depth stage and soil class; shoring and strutting; dewatering; sand bedding; refilling and compaction; disposal of surplus; reinstatement of road surface m³, m² 3 Sewer laying Supplying and laying RCC / PVC / SW pipe of each diameter, with jointing and testing running m 4 Manholes Manholes of each type and depth, complete with benching, channel, steps, CI cover and frame number 5 Appurtenances Gully traps, inspection chambers, drop connections, ventilating shafts, house connections number 6 Pumping station Wet well, pumps, motors, rising main, panel and standby power (if the ground is flat) LS / number 7 Treatment works Screen chamber, grit chamber, settling tank, sludge drying bed or oxidation pond; RCC, earthwork, plaster and fittings m³, m² 8 Outfall Outfall sewer, headwall and bank protection m, m³ 9 Miscellaneous Boundary wall, approach road, site office, tools and plant LS 5. Measurement sheet — the trench is measured reach by reach between manholes:
Reach Length (m) Dia (mm) Trench width (m) Mean depth (m) Excavation (m³) MH1–MH2 30.00 200 0.75 1.40 31.50 MH2–MH3 30.00 200 0.75 1.70 38.25 6. Analysis of rates for every item, 7. Abstract of cost, 8. Summary of cost with contingencies (3–5%) and work-charged establishment (1.5–2%), and 9. Bill of quantities for tendering.
The dominant cost in a sewerage project is trench excavation, and it grows sharply with depth — so excavation must be measured in depth stages (0–1.5 m, 1.5–3.0 m, and so on), each with its own rate, and separately below the water table.
ENCE 351 §3.2 and §3.6.
- What are the various methods of taking out quantities of civil engineering? Explain briefly. State the different factors considered during detailed estimation. [4+2] (2078 Bhadra, Q.2)The first part of this question also belongs to Chapter 2.
Solution
a) Methods of taking out quantities of civil engineering works
Four methods are used to take out the quantities of a load-bearing masonry building. All of them must give the same total length of wall — that identity is the check on the work.
1. Long wall — short wall method (also called the out-to-out and in-to-in method)
- Walls running in one direction are taken as long walls and measured from centre to centre plus one breadth of the wall (out to out).
- Walls at right angles to them are taken as short walls and measured from centre to centre minus one breadth (in to in).
- The length changes for every footing, because the breadth changes.
long wall L = centre-to-centre length + breadth of the item short wall S = centre-to-centre length − breadth of the item quantity = (2L + 2S) × breadth × heightSuitability: best when the walls of a building are of different thicknesses, or when the rooms are of different sizes, because each wall is dealt with on its own.
2. Centre line method
- The total centre-line length of all the walls is found once.
- It is multiplied by the breadth and the depth of each item in turn.
- For every junction where a wall meets another, half the breadth of the item is deducted, because that corner would otherwise be counted twice.
deduction = (number of junctions) × ½ × breadth of the item quantity = (total centre-line length − deduction) × breadth × heightSuitability: the quickest method, and the one normally used when all the walls are of the same thickness and meet in simple T or L junctions. It becomes error-prone where junctions are many or irregular.
3. Crossing method
- The out-to-out length of the walls is taken in both directions.
- The corners, which have then been counted twice, are deducted — one breadth for each crossing.
quantity = [2(Lout + Bout) − 4 × breadth] × breadth × heightSuitability: simple rectangular plans without internal cross walls; it becomes clumsy as soon as partitions are introduced.
4. Bay method
- A long building of repeating panels is divided into identical bays.
- One typical bay is worked out in full and multiplied by the number of bays.
- The two end bays are taken separately, since they carry the gable or end wall.
Suitability: long repetitive structures — barracks, sheds, godowns, factory buildings, and framed buildings with equal spans.
b) Factors considered during detailed estimation
- Completeness and correctness of the drawings — every dimension needed must be available and consistent; the estimate can be no better than the drawing.
- The specification of each item — the class of material and the mix decide both the quantity and the rate.
- The standard method of measurement (IS 1200) — particularly the deduction rules, which decide whether an opening is deducted at all.
- Prevailing rates of materials, labour and carriage at the site, and the district rate in force.
- Site conditions — nature of soil, water table, ground slope, access, and the lead and lift involved.
- Availability of materials, skilled labour, water and power locally, and the distance from which they must be brought.
- Season and duration of the work, and the likely escalation over that period.
- Method of construction and the plant proposed — manual or mechanised.
- Provisions for contingencies (3–5%), work-charged establishment (1.5–2%), and the percentage allowances for sanitary, water supply and electrical work.
- Overheads, profit and taxes applicable.
ENCE 351 Chapter 2 and §3.2.
- Describe how will you prepare a detailed estimate of a building. [6] (2074 Ashwin, Q.2)
Solution
Preparing a detailed estimate of a building
Step 1 — collect the data. Complete working drawings (plan, elevation, sections, details), the general and detailed specifications, the current district rate and the departmental rate-analysis norms.
Step 2 — list the items of work under sub-heads, in the order in which they are actually built: earthwork → concrete → masonry → damp proofing → wood work → steel work → roofing → flooring → finishing → services.
Step 3 — find the wall length by the centre line or long wall–short wall method. In a load-bearing building this single length drives almost every item.
Step 4 — take out the quantities on the measurement sheet, applying the deduction rules of IS 1200:
S.N. Description of item No. Length (m) Breadth (m) Height (m) Quantity Unit 1 Earthwork in excavation in foundation 1 18.00 0.90 1.00 16.20 m³ 2 PCC 1:3:6 in foundation 1 18.00 0.90 0.15 2.43 m³ Step 5 — analyse the rate of each item from the norms (material, labour, plant) and the district rate, adding overheads and profit.
Step 6 — prepare the abstract of cost: quantity × rate = amount for every item, and total.
Step 7 — add the provisions: contingencies 3–5%, work-charged establishment 1.5–2%, water supply and sanitary 8–10%, electrification 8–10%.
Step 8 — write the report and submit the estimate with the drawings, specifications, detailed measurement sheets, rate analysis and abstract for technical sanction.
ENCE 351 §3.2.
- Describe briefly how will you prepare a detailed estimate of a building. [5] (2073 Shrawan, Q.1(b)(i))
Solution
Preparing a detailed estimate of a building
Step 1 — collect the data. Complete working drawings (plan, elevation, sections, details), the general and detailed specifications, the current district rate and the departmental rate-analysis norms.
Step 2 — list the items of work under sub-heads, in the order in which they are actually built: earthwork → concrete → masonry → damp proofing → wood work → steel work → roofing → flooring → finishing → services.
Step 3 — find the wall length by the centre line or long wall–short wall method. In a load-bearing building this single length drives almost every item.
Step 4 — take out the quantities on the measurement sheet, applying the deduction rules of IS 1200:
S.N. Description of item No. Length (m) Breadth (m) Height (m) Quantity Unit 1 Earthwork in excavation in foundation 1 18.00 0.90 1.00 16.20 m³ 2 PCC 1:3:6 in foundation 1 18.00 0.90 0.15 2.43 m³ Step 5 — analyse the rate of each item from the norms (material, labour, plant) and the district rate, adding overheads and profit.
Step 6 — prepare the abstract of cost: quantity × rate = amount for every item, and total.
Step 7 — add the provisions: contingencies 3–5%, work-charged establishment 1.5–2%, water supply and sanitary 8–10%, electrification 8–10%.
Step 8 — write the report and submit the estimate with the drawings, specifications, detailed measurement sheets, rate analysis and abstract for technical sanction.
ENCE 351 §3.2.
- Describe how will you prepare a detailed cost estimate of a building. [4] (2068 Baishakh, Q.2)
Solution
Preparing a detailed estimate of a building
Step 1 — collect the data. Complete working drawings (plan, elevation, sections, details), the general and detailed specifications, the current district rate and the departmental rate-analysis norms.
Step 2 — list the items of work under sub-heads, in the order in which they are actually built: earthwork → concrete → masonry → damp proofing → wood work → steel work → roofing → flooring → finishing → services.
Step 3 — find the wall length by the centre line or long wall–short wall method. In a load-bearing building this single length drives almost every item.
Step 4 — take out the quantities on the measurement sheet, applying the deduction rules of IS 1200:
S.N. Description of item No. Length (m) Breadth (m) Height (m) Quantity Unit 1 Earthwork in excavation in foundation 1 18.00 0.90 1.00 16.20 m³ 2 PCC 1:3:6 in foundation 1 18.00 0.90 0.15 2.43 m³ Step 5 — analyse the rate of each item from the norms (material, labour, plant) and the district rate, adding overheads and profit.
Step 6 — prepare the abstract of cost: quantity × rate = amount for every item, and total.
Step 7 — add the provisions: contingencies 3–5%, work-charged establishment 1.5–2%, water supply and sanitary 8–10%, electrification 8–10%.
Step 8 — write the report and submit the estimate with the drawings, specifications, detailed measurement sheets, rate analysis and abstract for technical sanction.
ENCE 351 §3.2.
The detailed estimate is the accurate estimate, prepared after the drawings and specifications are complete. Every item of work is measured from the drawings, entered in a measurement (quantity) sheet, priced at the rate obtained by analysis of rates, and totalled in an abstract of cost.
How it is prepared
- Study the drawings and specifications and list the items of work, grouped under sub-heads (§3.6).
- Take out the quantities of each item from the drawings by one of the methods of Chapter 2, entering number, length, breadth and depth in the measurement sheet.
- Analyse the rate of each item (§6) from the norms and the district rates.
- Abstract the cost — quantity × rate for every item, summed by sub-head.
- Add contingencies, work-charged establishment and any other allowances.
- Attach the report, detailed specifications, drawings, calculation sheets and the analysis of rates.
What a detailed estimate must contain
- Report and general abstract of cost
- Detailed measurement (quantity) sheet
- Abstract of cost
- Analysis of rates
- General and detailed specifications
- Complete set of drawings — plans, elevations, sections, details
- Site (index) plan and design calculations
Contingencies and work-charged establishment
Two allowances are added at the end of every detailed estimate, and the examiners regularly ask for the difference:
| Contingencies | Work-charged establishment | |
|---|---|---|
| What it covers | Small unforeseen items and incidental expenses that cannot be foreseen at the time of estimating | The pay of staff employed specifically to supervise this work — site engineer, overseer, work sarkar, chowkidar |
| Usual allowance | 3–5% of the estimated cost | 1.5–2% of the estimated cost |
| Charged to | The work | The work (not the department's regular establishment) |
Contingencies are not the same as overhead cost. Contingencies are a provision inside the estimate for the unforeseen; overheads are the contractor's own cost of running a business — office rent, staff salaries, insurance, depreciation of plant — and are recovered inside the rate (§6), not added to the estimate.
Dawadi, chapter 3 estimating §3.2; Pandey & Katwal, Complete Manual §3.1.4.
3.3 Revised estimate20792074
Past Exam Questions on this Topic
- What are the necessary points that needs to be considered while measuring earthwork? In what case do you need to prepare revise estimate? Explain with an example. [4+4] (2079 Bhadra, Q.2)The first part of this question also belongs to Chapter 1.
Solution
a) Points to be considered while measuring earthwork
- Classification of the soil — soft/ordinary soil, hard soil, soft rock and hard rock requiring blasting are measured and paid separately, because the effort differs greatly.
- Lead — the horizontal distance the excavated earth is carried. The first 30 m is normally included in the rate; beyond that, extra lead is paid in stages.
- Lift — the vertical height through which the earth is lifted. The first 1.5 m is included in the rate; each additional 1.5 m is paid extra.
- Depth of excavation, measured from the existing ground level, and taken in stages where the depth is large.
- Dewatering — excavation below the water table or in slush is measured separately.
- Working space and side slopes — measure the authorised dimensions of the trench as per drawing; extra excavation for the convenience of the contractor is not paid.
- Excavation and filling kept separate, and the volume of filling measured after compaction, not loose.
- Bulking and shrinkage — earth increases in volume when loosened and reduces when compacted, so the state in which the measurement is taken must be stated.
- Unit — measured in m³ and generally paid per 100 m³. Surface dressing up to 30 cm deep is measured in m².
b) When a revised estimate is required
A revised estimate is a fresh detailed estimate prepared for a work already sanctioned. It becomes necessary when:
- the expenditure exceeds, or is likely to exceed, the sanctioned amount by more than 5%;
- the rates adopted in the original estimate have changed materially;
- there is a substantial change in the design, specification or scope;
- site conditions turn out to differ from those assumed; or
- the work has been abandoned and is restarted after a long interval.
Example. A rural road was sanctioned for Rs. 2.00 crore on the assumption of ordinary soil throughout. On excavation, hard rock was met over 600 m of the alignment, raising the excavation cost and requiring additional breast walls. The anticipated cost rose to Rs. 2.35 crore — an excess of 17.5%, far beyond 5% — so a revised estimate was prepared showing the original and revised quantity and cost of each item side by side, with the reason for every variation, and was submitted for fresh sanction.
ENCE 351 §1.4 and §3.3.
- Why revise estimate should be prepared? What is Rate analysis? Explain its important. (The second and third parts of this question also belong to Chapter 6.) The revised estimate is also asked as part of the general "types of estimate" questions listed in Section 3.1 — see Q3(a), Q4, Q6(b), Q7(ii), Q8, Q9, Q10 and Q11(ii). [5] (2074 Chaitra, Q.3)
Solution
a) Why a revised estimate should be prepared
Revised estimate. A fresh detailed estimate prepared for a work that has already been sanctioned. It is needed when:
- the expenditure exceeds, or is likely to exceed, the sanctioned amount by more than 5%;
- the rates adopted in the original estimate have changed materially;
- there is a substantial change in the design, specification or scope of the work;
- site conditions turn out to differ from those assumed — rock instead of soil, a high water table, a longer lead; or
- the work was abandoned and is being restarted after a long interval.
It shows the original and the revised quantity and cost of every item side by side, with the reason for each variation, and must be sanctioned afresh by the competent authority before the extra expenditure is incurred.
It must be prepared because public money can be spent only up to the amount sanctioned. Once that limit is likely to be crossed, further expenditure is irregular until fresh sanction is obtained; the revised estimate is the document that seeks it, and it also serves to explain and record why the cost rose.
b) Rate analysis
Analysis of rates is the process of working out the cost of one unit of an item of work — per m³, per m², per m — by adding up the cost of the materials, the labour, the plant and the overheads that go into that unit, together with the contractor's profit.
rate of one unit of work = cost of materials ( quantity × rate, including carriage ) + cost of labour ( number of man-days × daily wage ) + cost of plant and equipment ( hire / running charge ) + water charges and sundries ( 1–2% ) + overhead charges ( 5–10% ) + contractor's profit ( 10–15% )c) Importance of rate analysis
- It gives the correct rate of each item, and hence a realistic estimate; without it the estimate is only a guess.
- It shows the quantity of each material and each class of labour required, so they can be procured and programmed.
- It lets the department examine a contractor's quoted rate and judge whether it is reasonable, abnormally high or unworkably low.
- It is the basis for fixing the rate of extra, substituted and non-scheduled items that arise during execution.
- It shows the effect of a change in specification — how much the rate rises if the mix is made richer — and so helps in choosing between alternatives.
- It allows the estimate to be updated when material or labour rates change, without re-doing the quantities.
- It is required for settling claims, escalation and disputes.
ENCE 351 §3.3 and §6.1.
A revised estimate is a fresh detailed estimate prepared for a work already sanctioned, when the original sanction is no longer adequate.
When a revised estimate is required
- When the expenditure exceeds, or is likely to exceed, the sanctioned amount by more than about 5%.
- When the rates adopted have changed materially.
- When there is a material deviation from the original proposal — a change of design, of specification, or of the structural system.
- When the work is abandoned part way and the sanction has to be adjusted.
It is prepared in the same form as the original detailed estimate, but with a comparative statement showing, item by item, the original quantity and cost, the revised quantity and cost, the difference, and the reason for it.
Example. A school building is sanctioned at Rs 80 lakh. During construction the sub-soil proves weaker than assumed and the isolated footings must be replaced by a raft, while cement rates rise. The cost rises to Rs 92 lakh — 15% over sanction — so a revised estimate is prepared and fresh sanction obtained before the extra work proceeds.
Dawadi, chapter 3 estimating §3.2.1.
3.4 Supplementary estimate
A supplementary estimate is a detailed estimate for additional work found necessary while the original work is in progress. The original work is not disturbed; the new work is estimated separately and sanctioned in addition.
When it is required
- When an altogether new item or new structure becomes necessary.
- When further work is needed to make the original work fully useful.
It is prepared exactly like a detailed estimate, and its abstract shows both the amount of the original sanctioned estimate and the amount now proposed, so that the total commitment is visible.
Example. A hostel block is under construction to sanction. It is then decided that a separate generator room and an overhead water tank are needed for the block to function. These were never in the original estimate, so a supplementary estimate is prepared for them.
Revised or supplementary?
| Revised estimate | Supplementary estimate | |
|---|---|---|
| Reason | The same work now costs more, or the design has changed | Additional work is needed |
| Original estimate | Superseded by the revised one | Stands; the new estimate is in addition |
| Presented with | A comparative statement against the original | An abstract showing both sanctions |
Dawadi, chapter 3 estimating §3.2.2.
3.5 Complete estimate2075
Past Exam Questions on this Topic
- What are the components of a complete estimate? Prepare a sample of abstract cost. (The second part of this question also belongs to Section 3.7.) The complete estimate is also asked inside the general "types of estimate" questions of Section 3.1 — see Q5(b), Q6(d), Q9 and Q10. [4+4] (2075 Ashwin, Q.3)
Solution
a) Components of a complete estimate
A complete estimate is one that covers every cost needed to bring the work into use — not merely the cost of the structure itself. Its components are:
- Cost of land — purchase or acquisition, compensation, and the legal and registration charges.
- Cost of the main work — the detailed estimate of the building or structure itself.
- Water supply and sanitary installation — 8–10% of the building cost.
- Internal electrical installation — 8–10%.
- External services — approach road, paving, compound wall and gate, external water, sewer and electric connections, street lighting.
- Architectural treatment and landscaping — 1–2% each.
- Furniture and fixtures — 2–5%.
- Special installations — lift, fire fighting, air conditioning, generator, where required.
- Contingencies — 3–5%.
- Work-charged establishment — 1.5–2%.
- Supervision / engineering and consultancy fees.
- Taxes as applicable (VAT 13%).
The point of a complete estimate is that a building is useless without water, drainage, power and access. An estimate that stops at the structure understates the true cost by roughly a quarter.
b) Sample abstract of cost
S.N. Description of item Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation in ordinary soil 120.00 m³ 400.00 48,000.00 2 PCC 1:3:6 in foundation 18.50 m³ 9,000.00 1,66,500.00 3 RCC 1:1½:3 in footings, columns and slab 42.00 m³ 15,000.00 6,30,000.00 4 Steel reinforcement 3,400.00 kg 120.00 4,08,000.00 5 First class brickwork in 1:6 cement sand mortar 96.00 m³ 12,000.00 11,52,000.00 6 12 mm cement plaster 1:4 640.00 m² 350.00 2,24,000.00 Total cost of works 26,28,500.00 Add water supply and sanitary @ 8% 2,10,280.00 Add electrification @ 8% 2,10,280.00 Add contingencies @ 3% 78,855.00 Add work-charged establishment @ 2% 52,570.00 Total estimated cost 31,80,485.00 ENCE 351 §3.5 and §3.7.
A complete estimate covers not only the structure itself but every cost that has to be incurred before the work can be used. An estimate limited to the building alone always understates the money required.
Components of a complete estimate
- Cost of land — purchase or acquisition, with compensation.
- Legal expenses — registration, stamp duty, land revenue, legal charges.
- Cost of the structure from the detailed estimate.
- Water supply and sanitary installation — usually taken at 8–10% of the building cost.
- Electrical installation — usually 8–10% of the building cost.
- Approach road, boundary wall, gate, landscaping and other site development.
- Architectural and consultancy fees, and supervision charges.
- Contingencies (3–5%) and work-charged establishment (1.5–2%).
- Furniture and equipment, where the building cannot function without it.
Related estimates
- Annual repair and maintenance estimate — prepared each year to keep the property in proper condition (white washing, minor repairs, replacement of fittings). Usually 1–2% of the capital cost for a building.
- Extension and improvement estimate — for enlarging or upgrading an existing property.
- Maintenance and special repair estimate — for periodic heavy repairs beyond ordinary annual maintenance.
Dawadi, chapter 3 estimating §3.2.3–3.2.5; Pandey & Katwal, Complete Manual §3.2.
3.6 Splitting of cost of building, road, water supply and sanitary works into sub-heads2082208120802079207820762075207420712070
Past Exam Questions on this Topic
- What are the subheads of various items of work? When is an approximate estimate prepared? [4+2] (2081 Baishakh, Q.2)The second part of this question also belongs to Section 3.1.
Solution
a) Sub-heads of the various items of work
The items of an estimate are grouped under sub-heads, taken in the order in which the work is actually built. For a building project:
- Earthwork — site clearance, excavation in foundation, refilling, plinth filling, disposal of surplus earth.
- Concrete work — PCC in foundation and floors; RCC in footings, columns, beams, slabs, lintels and stairs, with formwork and reinforcement.
- Masonry — brick or stone masonry in foundation, plinth and superstructure; partition walls.
- Damp proofing — DPC at plinth level; waterproofing of roof and wet areas.
- Wood work and joinery — door and window frames and shutters, with fittings and fastenings.
- Steel work — grills, gates, rolling shutters, structural steel.
- Roofing — roof slab or truss and covering, gutters and rain-water pipes.
- Flooring — base concrete, floor finish, skirting and dado.
- Finishing — plastering, pointing, white washing, distempering, painting.
- Water supply and sanitary installation — 8–10% of building cost.
- Electrical installation — 8–10%.
- Miscellaneous and external works — compound wall, gate, approach road, paving, landscaping.
b) When an approximate estimate is prepared
An approximate estimate is prepared at the proposal stage, before detailed drawings and specifications exist — that is:
- when a scheme is first conceived and its financial feasibility must be judged;
- to obtain administrative approval of the competent authority;
- to provide the amount in the annual budget;
- to compare alternative schemes, sites or designs on cost; and
- to fix the order of magnitude against which the later detailed estimate can be checked.
ENCE 351 §3.1 and §3.6.
- What are the various methods of taking out quantities? What are the sub-heads of items of work for building project? [4+4] (2080 Baishakh, Q.2)The first part of this question also belongs to Chapter 2.
Solution
a) Various methods of taking out quantities
Four methods are used to take out the quantities of a load-bearing masonry building. All of them must give the same total length of wall — that identity is the check on the work.
1. Long wall — short wall method (also called the out-to-out and in-to-in method)
- Walls running in one direction are taken as long walls and measured from centre to centre plus one breadth of the wall (out to out).
- Walls at right angles to them are taken as short walls and measured from centre to centre minus one breadth (in to in).
- The length changes for every footing, because the breadth changes.
long wall L = centre-to-centre length + breadth of the item short wall S = centre-to-centre length − breadth of the item quantity = (2L + 2S) × breadth × heightSuitability: best when the walls of a building are of different thicknesses, or when the rooms are of different sizes, because each wall is dealt with on its own.
2. Centre line method
- The total centre-line length of all the walls is found once.
- It is multiplied by the breadth and the depth of each item in turn.
- For every junction where a wall meets another, half the breadth of the item is deducted, because that corner would otherwise be counted twice.
deduction = (number of junctions) × ½ × breadth of the item quantity = (total centre-line length − deduction) × breadth × heightSuitability: the quickest method, and the one normally used when all the walls are of the same thickness and meet in simple T or L junctions. It becomes error-prone where junctions are many or irregular.
3. Crossing method
- The out-to-out length of the walls is taken in both directions.
- The corners, which have then been counted twice, are deducted — one breadth for each crossing.
quantity = [2(Lout + Bout) − 4 × breadth] × breadth × heightSuitability: simple rectangular plans without internal cross walls; it becomes clumsy as soon as partitions are introduced.
4. Bay method
- A long building of repeating panels is divided into identical bays.
- One typical bay is worked out in full and multiplied by the number of bays.
- The two end bays are taken separately, since they carry the gable or end wall.
Suitability: long repetitive structures — barracks, sheds, godowns, factory buildings, and framed buildings with equal spans.
b) Sub-heads of items of work for a building project
Sub-heads of items of work for a building project
The items of a building estimate are grouped under sub-heads, taken in the order in which the work is actually built:
- Earthwork — site clearance, excavation in foundation, refilling, plinth filling, disposal of surplus earth.
- Concrete work — PCC in foundation and floors, RCC in footings, columns, beams, slabs, lintels and stairs, with formwork and reinforcement.
- Masonry / brickwork — brick or stone masonry in foundation, plinth and superstructure, partition walls.
- Damp proofing — DPC at plinth level, waterproofing of roof and wet areas.
- Wood work / joinery — door and window frames and shutters, cupboards, railings, with fittings and fastenings.
- Steel work — grills, gates, rolling shutters, structural steel.
- Roofing — roof slab or truss and covering, gutters, rain-water pipes.
- Flooring — base concrete, floor finish, skirting and dado.
- Finishing — internal and external plastering, pointing, white washing, distempering and painting.
- Sanitary and water supply installation — fittings, pipes, septic tank and soak pit — usually 8–10% of the building cost.
- Electrical installation — internal wiring, fittings and fixtures — usually 8–10%.
- Miscellaneous and external works — compound wall, gate, approach road, paving, landscaping.
Grouping under sub-heads is not decoration. It makes the estimate easy to check, lets the work be split into separate contracts, and allows the departmental percentages for sanitary and electrical work to be applied to the right base.
ENCE 351 Chapter 2 and §3.6.
- Prepare a project estimate for water supply project. [5] (2082 Bhadra, Q.8)
Solution
Project estimate for a water supply project
1. Design basis
design population Pn = P₀(1 + r)n ( design period 20–30 years ) average daily demand = Pn × demand per head per day ( 45–65 lpcd rural, 100–135 lpcd urban ) maximum daily demand = 1.5 × average peak hourly demand = 2.0 – 3.0 × average storage reservoir capacity ≈ ⅓ of the maximum daily demand2. Sub-heads and items of work
S.N. Sub-head Items Unit 1 Preliminary works Survey, source measurement, water quality testing, design and drawing LS 2 Land acquisition Land for intake, reservoir and treatment unit; compensation m² 3 Intake works Spring box or river intake, collection chamber, protection wall, fencing m³, no. 4 Transmission main Trench excavation, sand bedding, laying and jointing GI / HDPE / DI pipe, refilling, thrust blocks, testing m³, running m 5 Treatment works Sedimentation tank, roughing and slow sand filter, chlorination unit m³, no. 6 Reservoir RCC or ferro-cement reservoir tank — excavation, PCC, RCC, reinforcement, formwork, plaster, fittings m³, kg, m² 7 Distribution system Distribution pipes of each diameter, valves, valve chambers, break-pressure tanks, air valves, washouts running m, no. 8 Tap stands / house connections Public tap stands, ferrule connections, water meters number 9 Pumping (if any) Pump house, pumps, motors, rising main, panel board, power connection LS 10 Miscellaneous Boundary wall, approach path, road reinstatement, tools, sanitation and health education LS 3. Summary of cost
S.N. Sub-head Amount (Rs) 1–10 Total cost of works (from the abstract) … Add contingencies @ 3–5% … Add work-charged establishment @ 1.5–2% … Add VAT @ 13% … Total project cost … 4. Report and drawings — the report giving the source, the design population and demand, the scheme adopted and the per-capita cost; drawings comprising the index map, the layout of the system with the hydraulic gradient line, and standard drawings of the intake, reservoir and tap stand.
The report itself is written under these sub-heads:
- Introduction, with the location of the project
- Condition of the existing water supply
- Need for the present project
- Design data
- Population projection
- Water demand
- Source of supply and the intake work
- The scheme proposed, with alternatives considered
- General abstract of cost, and the abstract cost of each sub-head
- Schedule of rates, drawings and the land acquisition statement
The figure the evaluating authority actually looks at is the cost per capita — total project cost divided by the design population. Always state it.
ENCE 351 §3.6; report structure after Pandey & Katwal, Complete Manual ch.5 §5.8.
- What is project? Explain its characteristics. Describe stages of estimating project. [8] (2081 Baishakh, Q.7)The "characteristics of a project" part is listed in the Chapter 3 out-of-syllabus section below.
Solution
Project. A project is a temporary, non-repetitive undertaking taken up to create a unique product or facility, having a definite beginning and a definite end, its own objective, its own budget and its own team.
Characteristics of a project
- Unique — no two projects are identical, even of the same design, because the site, time and people differ.
- Temporary — it has a definite start and finish; the organisation is disbanded at the end.
- Definite objective — a stated scope, quality, time and cost.
- Progressive elaboration — the detail is developed in steps as the work proceeds.
- Multi-disciplinary — it needs several trades and specialists working together.
- Resource constrained — limited money, time, labour and plant.
- Involves risk and uncertainty, which is why contingencies are provided.
- Life cycle — conception, planning, execution, commissioning, closure.
Stages of a project estimate
- Identification / conception. The need is established and the broad scope fixed. A rough cost estimate is made from a per-unit figure.
- Pre-feasibility and feasibility. Alternatives, sites and technologies are compared. An approximate / preliminary estimate is prepared by the plinth area, cube content or service-unit method, and administrative approval is obtained on it.
- Preliminary design. Line drawings and outline specifications are made; the estimate is refined by the approximate quantity method.
- Detailed design. Complete working drawings and detailed specifications are prepared, and a full detailed estimate with rate analysis and abstract of cost is made. Technical sanction is obtained on this.
- Tender stage. The bill of quantities is issued; the estimate is compared with the rates actually quoted, and the tender premium is assessed.
- Execution. Running bills are checked against measured work; variations are valued; a revised or supplementary estimate is prepared if the cost exceeds the sanction by more than 5% or the scope changes.
- Completion. The final bill and the completion report are prepared, comparing the actual cost with the sanctioned estimate and explaining the difference.
ENCE 351 §3.6.
- Describe different stages of project estimate. Explain the characteristic of technical report writing of a project. [4+4] (2080 Baishakh, Q.6)
Solution
a) Stages of a project estimate
Stages of a project estimate
- Identification / conception. The need is established and the broad scope fixed. A rough cost estimate is made from a per-unit figure.
- Pre-feasibility and feasibility. Alternatives, sites and technologies are compared. An approximate / preliminary estimate is prepared by the plinth area, cube content or service-unit method, and administrative approval is obtained on it.
- Preliminary design. Line drawings and outline specifications are made; the estimate is refined by the approximate quantity method.
- Detailed design. Complete working drawings and detailed specifications are prepared, and a full detailed estimate with rate analysis and abstract of cost is made. Technical sanction is obtained on this.
- Tender stage. The bill of quantities is issued; the estimate is compared with the rates actually quoted, and the tender premium is assessed.
- Execution. Running bills are checked against measured work; variations are valued; a revised or supplementary estimate is prepared if the cost exceeds the sanction by more than 5% or the scope changes.
- Completion. The final bill and the completion report are prepared, comparing the actual cost with the sanctioned estimate and explaining the difference.
b) Characteristics of technical report writing for a project
- Accuracy — every figure, quantity and rate must be correct and traceable to its source; a technical report is a record, not an opinion.
- Clarity and simplicity — short sentences, plain language, no ambiguity. It will be read by administrators as well as engineers.
- Objectivity — conclusions must follow from the data presented, not from the writer's preference; alternatives rejected must be stated with reasons.
- Completeness — all the data needed to check the conclusion must be included, with nothing material omitted.
- Logical order — introduction → need for the work → investigation and data → alternatives → the scheme adopted → design → estimate → conclusion and recommendation.
- Supported by drawings, tables and charts, each numbered, titled and referred to in the text.
- Standard units and notation throughout (SI), with sources of all rates quoted.
- Brevity — supporting calculations go into appendices, not the main body.
- Proper structure — title page, summary, index, main body, conclusions and recommendations, references, appendices.
- Signed and dated, with the responsibility of the writer clearly recorded.
ENCE 351 §3.6.
- What are the requisites for a project estimate? Explain in brief the factors you consider while preparing a building project estimate. [4+4] (2079 Bhadra, Q.6)
Solution
a) Requisites for a project estimate
- Complete drawings — site plan, layout, plans, elevations, sections and detail drawings, all fully dimensioned and to scale.
- Detailed specifications of every item of work.
- Survey and investigation data — topographic survey, soil investigation, water table, and for a road or canal the longitudinal section.
- Schedule of rates — the current district rate of materials, labour and carriage.
- Rate-analysis norms of the department.
- Standard method of measurement (IS 1200 or departmental rules).
- Lead statement for every material from its source.
- Land acquisition details and compensation rates.
- Provisions for contingencies, work-charged establishment, services and taxes.
- Report justifying the work, and the approval of the competent authority.
b) Factors considered while preparing a building project estimate
- Type and use of the building — residential, office, hospital, school — which fixes the standard of finish and the services required.
- Number of storeys and the structural system — load bearing or framed; a framed building shifts the cost from masonry to RCC and steel.
- Site conditions — soil and bearing capacity, water table, slope, and access for materials and plant.
- Specification and quality of materials and finishes adopted.
- Local rates of materials and labour, and the lead from which each material must be brought.
- Availability of skilled labour, water and power at the site.
- Season and duration of construction, and the likely escalation.
- Services — water supply and sanitary 8–10%, electrification 8–10%, and any lift or fire fighting installation.
- External development — compound wall, gate, approach road, landscaping.
- Statutory requirements — building by-laws, setback, height limit, seismic code, municipal approval fees.
- Contingencies, establishment, overheads, profit and taxes.
ENCE 351 §3.6.
- What are the tasks you need to consider in preparing estimate of a building project work? Explain in brief. Discuss estimation irrigation project. [4+4] (2078 Bhadra, Q.7)
Solution
a) Tasks in preparing the estimate of a building project
- Study the drawings and specifications thoroughly, and clear every ambiguity with the designer before starting.
- Visit the site and record the soil, water table, ground slope, access and the lead of each material.
- List the items of work under sub-heads in the order of construction.
- Find the wall length by the centre line or long wall–short wall method.
- Take out the quantities item by item on the measurement sheet, applying the IS 1200 deduction rules.
- Prepare the bar bending schedule and convert the reinforcement to weight at w = d²/162 kg/m.
- Collect the rates — district rate, market rates, carriage — and analyse the rate of every item from the departmental norms.
- Prepare the abstract of cost and total it.
- Add the provisions — services, contingencies, establishment, taxes.
- Check the estimate against an approximate plinth-area figure, to catch gross errors.
- Write the report, prepare the bill of quantities, and submit for technical sanction.
b) Estimate of an irrigation project
An irrigation project is estimated in the same way, but the quantities are driven by the design discharge rather than by a plan of rooms.
Design basis: from the culturable command area and the duty of the crops, the design discharge Q is found; the canal section (bed width B, full supply depth D, side slope s, bed slope) follows from it.
canal section area A = B·D + s·D² volume between two sections, prismoidal: Qe/w = (L/6)( A₁ + 4Amid + A₂ ) wetted perimeter P = B + 2D√(1 + s²) area of lining = P × length of the reachSub-heads: preliminary works · land acquisition and compensation · head works (diversion weir, intake, head regulator, river training) · main canal earthwork in cutting and filling · dressing and trimming · lining · branch canals and distributaries · canal structures (cross regulators, falls, outlets, aqueducts, culverts, escapes) · drainage works · inspection road · buildings · environmental mitigation · contingencies and establishment.
Presentation: the earthwork is set out chainage by chainage with cutting and filling in separate columns, so that the balance of earthwork — and hence the borrow or spoil — is visible; each structure is estimated separately and brought into the abstract as a lump item.
ENCE 351 §3.6 and §5.6.
- What is Project? How is building project estimate? [6] (2076 Chaitra, Q.5)
Solution
Project. A project is a temporary, non-repetitive undertaking taken up to create a unique product or facility, having a definite beginning and a definite end, its own objective, its own budget and its own team.
Characteristics of a project
- Unique — no two projects are identical, even of the same design, because the site, time and people differ.
- Temporary — it has a definite start and finish; the organisation is disbanded at the end.
- Definite objective — a stated scope, quality, time and cost.
- Progressive elaboration — the detail is developed in steps as the work proceeds.
- Multi-disciplinary — it needs several trades and specialists working together.
- Resource constrained — limited money, time, labour and plant.
- Involves risk and uncertainty, which is why contingencies are provided.
- Life cycle — conception, planning, execution, commissioning, closure.
How a building project is estimated
Preparing a detailed estimate of a building
Step 1 — collect the data. Complete working drawings (plan, elevation, sections, details), the general and detailed specifications, the current district rate and the departmental rate-analysis norms.
Step 2 — list the items of work under sub-heads, in the order in which they are actually built: earthwork → concrete → masonry → damp proofing → wood work → steel work → roofing → flooring → finishing → services.
Step 3 — find the wall length by the centre line or long wall–short wall method. In a load-bearing building this single length drives almost every item.
Step 4 — take out the quantities on the measurement sheet, applying the deduction rules of IS 1200:
S.N. Description of item No. Length (m) Breadth (m) Height (m) Quantity Unit 1 Earthwork in excavation in foundation 1 18.00 0.90 1.00 16.20 m³ 2 PCC 1:3:6 in foundation 1 18.00 0.90 0.15 2.43 m³ Step 5 — analyse the rate of each item from the norms (material, labour, plant) and the district rate, adding overheads and profit.
Step 6 — prepare the abstract of cost: quantity × rate = amount for every item, and total.
Step 7 — add the provisions: contingencies 3–5%, work-charged establishment 1.5–2%, water supply and sanitary 8–10%, electrification 8–10%.
Step 8 — write the report and submit the estimate with the drawings, specifications, detailed measurement sheets, rate analysis and abstract for technical sanction.
To the total so obtained are added the project-level provisions that turn a building estimate into a project estimate: land, water supply and sanitary installation (8–10%), electrification (8–10%), external development, furniture, contingencies (3–5%), work-charged establishment (1.5–2%), consultancy fees and taxes.
ENCE 351 §3.2 and §3.6.
- Define project. Discuss estimate of irrigation project. [6] (2075 Chaitra, Q.7)
Solution
Project. A project is a temporary, non-repetitive undertaking taken up to create a unique product or facility, having a definite beginning and a definite end, its own objective, its own budget and its own team.
Characteristics of a project
- Unique — no two projects are identical, even of the same design, because the site, time and people differ.
- Temporary — it has a definite start and finish; the organisation is disbanded at the end.
- Definite objective — a stated scope, quality, time and cost.
- Progressive elaboration — the detail is developed in steps as the work proceeds.
- Multi-disciplinary — it needs several trades and specialists working together.
- Resource constrained — limited money, time, labour and plant.
- Involves risk and uncertainty, which is why contingencies are provided.
- Life cycle — conception, planning, execution, commissioning, closure.
Estimate of an irrigation project
Data required: topographic survey and contour plan of the command area; longitudinal section and cross-sections of the alignment; hydrological data of the source; the culturable command area, crops, duty and delta — from which the design discharge follows; soil investigation along the alignment; and the district rate and norms.
Design of the section:
area of the canal section A = B·D + s·D² wetted perimeter P = B + 2D√(1 + s²) earthwork between two sections, by the prismoidal formula: Q = (L/6)( A₁ + 4Amid + A₂ ) area of lining = P × length of the reachSub-heads of the estimate:
- Preliminary works — survey, investigation, design and drawing.
- Land acquisition and compensation.
- Head works — diversion weir or intake, head regulator, silt excluder, river training.
- Main canal — clearing, earthwork in cutting and in embankment (kept in separate columns), dressing and trimming, lining.
- Branch canals, distributaries and water courses.
- Canal structures — cross regulators, falls, outlets, aqueducts, syphons, culverts, escapes, bridges.
- Drainage works.
- Inspection road along the bank.
- Buildings — office, store, quarters, gauge stations.
- Miscellaneous — turfing, plantation, boundary pillars, measuring devices.
- Environmental mitigation as per the IEE / EIA.
- Contingencies 3–5% and work-charged establishment 1.5–2%.
Presentation: the earthwork sheet runs chainage by chainage with cutting and filling totalled separately, so the balance of earthwork is visible; each structure is estimated on its own and carried into the abstract as one item. The report should state the cost per hectare of command area, which is the figure used to judge the project.
ENCE 351 §3.6 and §5.6.
- What do you mean by Project estimate? How do you prepare project estimate? State the reports on estimate. [1+2+3] (2075 Ashwin, Q.7)
Solution
a) Project estimate
A project estimate is the estimate of the whole project — not merely of the main structure — covering every component and every ancillary cost needed to bring the facility into use: land, the main work, all its sub-works, external services, contingencies, establishment, fees and taxes. It is the document on which the project is sanctioned and budgeted.
b) How a project estimate is prepared
- Define the scope and break the project into its components (work breakdown structure).
- Collect the data — drawings, specifications, survey and soil data, district rate, norms, lead statement.
- Estimate each component separately — take out the quantities, analyse the rates, and abstract the cost of each.
- Group the components under sub-heads and prepare the general abstract.
- Add the project-level provisions — land, services (8–10% each), external development, contingencies (3–5%), work-charged establishment (1.5–2%), consultancy fees and taxes (13% VAT).
- Prepare the summary of cost and the bill of quantities.
- Write the report and submit for administrative approval and technical sanction.
c) Reports on an estimate
Report When What it contains Preliminary / feasibility report With the approximate estimate Need for the work, alternatives, site, rough cost — the basis of administrative approval Detailed project report (DPR) With the detailed estimate Design, drawings, specifications, quantities, rate analysis, abstract and summary of cost — the basis of technical sanction Revised estimate report When the cost exceeds the sanction by >5% Original and revised cost of each item side by side, with the reason for every variation Supplementary estimate report When extra work outside the original scope is needed Detailed estimate of the additional work only Progress report Periodically during execution Physical and financial progress against the estimate Completion report On completion Actual cost compared with the sanctioned estimate, with reasons for the difference ENCE 351 §3.6.
- Define project. Discuss estimation of road project. [5] (2074 Chaitra, Q.5)
Solution
Project. A project is a temporary, non-repetitive undertaking taken up to create a unique product or facility, having a definite beginning and a definite end, its own objective, its own budget and its own team.
Characteristics of a project
- Unique — no two projects are identical, even of the same design, because the site, time and people differ.
- Temporary — it has a definite start and finish; the organisation is disbanded at the end.
- Definite objective — a stated scope, quality, time and cost.
- Progressive elaboration — the detail is developed in steps as the work proceeds.
- Multi-disciplinary — it needs several trades and specialists working together.
- Resource constrained — limited money, time, labour and plant.
- Involves risk and uncertainty, which is why contingencies are provided.
- Life cycle — conception, planning, execution, commissioning, closure.
Estimation of a road project
Data required: traffic survey and the design traffic; topographic survey of the alignment with the longitudinal section and cross-sections at every chainage; soil investigation and CBR of the subgrade; the design standard (road class, formation width, camber, gradient); quarry locations and the lead of each material; and the district rate and norms.
Earthwork — the governing item:
cross-sectional area A = B·D + s·D² B = formation width, D = depth of cut or height of fill, s = side slope volume between sections, by the prismoidal formula: Q = (L/6)( A₁ + 4Amid + A₂ ) cutting and filling are totalled in SEPARATE columns, so that the balance — the earth to be borrowed or wasted — is visibleSub-heads of the estimate:
- Preliminary works — survey, investigation, design and drawing.
- Land acquisition and compensation.
- Site clearance — clearing and grubbing, removal of structures.
- Earthwork — excavation in cutting by soil class, embankment in compacted layers, disposal of surplus.
- Pavement — subgrade preparation (m²), granular sub-base, base course, prime and tack coat, bituminous surfacing, seal coat, shoulders.
- Cross drainage — pipe, slab and box culverts, causeways, bridges.
- Protection works — retaining, breast and toe walls, gabions, slope protection.
- Drainage — side drains, catch drains, cross drains.
- Road furniture — signs, markings, guard posts, kilometre stones, parapets.
- Bio-engineering and plantation.
- Miscellaneous — diversion road, traffic management during construction.
- Contingencies 3–5% and work-charged establishment 1.5–2%.
Presentation: the estimate is built on the chainage-wise earthwork sheet and the pavement quantities per km. The report should state the cost per kilometre, which is the figure used to compare road projects.
ENCE 351 §3.6, §5.4 and §5.5.
- Define project. Discuss estimate of irrigation project. [5] (2071 Chaitra, Q.5)
Solution
Project. A project is a temporary, non-repetitive undertaking taken up to create a unique product or facility, having a definite beginning and a definite end, its own objective, its own budget and its own team.
Characteristics of a project
- Unique — no two projects are identical, even of the same design, because the site, time and people differ.
- Temporary — it has a definite start and finish; the organisation is disbanded at the end.
- Definite objective — a stated scope, quality, time and cost.
- Progressive elaboration — the detail is developed in steps as the work proceeds.
- Multi-disciplinary — it needs several trades and specialists working together.
- Resource constrained — limited money, time, labour and plant.
- Involves risk and uncertainty, which is why contingencies are provided.
- Life cycle — conception, planning, execution, commissioning, closure.
Estimate of an irrigation project
Data required: topographic survey and contour plan of the command area; longitudinal section and cross-sections of the alignment; hydrological data of the source; the culturable command area, crops, duty and delta — from which the design discharge follows; soil investigation along the alignment; and the district rate and norms.
Design of the section:
area of the canal section A = B·D + s·D² wetted perimeter P = B + 2D√(1 + s²) earthwork between two sections, by the prismoidal formula: Q = (L/6)( A₁ + 4Amid + A₂ ) area of lining = P × length of the reachSub-heads of the estimate:
- Preliminary works — survey, investigation, design and drawing.
- Land acquisition and compensation.
- Head works — diversion weir or intake, head regulator, silt excluder, river training.
- Main canal — clearing, earthwork in cutting and in embankment (kept in separate columns), dressing and trimming, lining.
- Branch canals, distributaries and water courses.
- Canal structures — cross regulators, falls, outlets, aqueducts, syphons, culverts, escapes, bridges.
- Drainage works.
- Inspection road along the bank.
- Buildings — office, store, quarters, gauge stations.
- Miscellaneous — turfing, plantation, boundary pillars, measuring devices.
- Environmental mitigation as per the IEE / EIA.
- Contingencies 3–5% and work-charged establishment 1.5–2%.
Presentation: the earthwork sheet runs chainage by chainage with cutting and filling totalled separately, so the balance of earthwork is visible; each structure is estimated on its own and carried into the abstract as one item. The report should state the cost per hectare of command area, which is the figure used to judge the project.
ENCE 351 §3.6 and §5.6.
- What are the works that an estimator has to take account in project estimate? Explain. Note on the irrigation-project questions (Q43, Q45, Q48). Syllabus point 3.6 names only building, road, water supply and sanitary works; irrigation is not listed. These questions are kept here because irrigation works are covered by Chapter 5 of ENCE 351, so the sub-head breakdown of an irrigation project remains examinable through that chapter. Note on the report questions (Q41, Q46). Writing up the estimate is still required — the course objective of ENCE 351 ends with "the preparation of detailed estimate and valuation reports" — so these remain in syllabus. [6] (2070 Chaitra, Q.3(a))
Solution
Works an estimator must take into account in a project estimate
An estimator who prices only the visible structure will always under-estimate. The following heads must all be accounted for.
- Preliminary works — survey, soil investigation, testing, design and drawing, and the preparation of the estimate itself.
- Land — purchase or acquisition, compensation for crops and structures, legal and registration charges.
- Site works — clearing and grubbing, demolition of existing structures, site levelling, temporary access, site office, store, water and power connection, fencing and security.
- The main work — the structure itself, item by item under its sub-heads.
- Sub-works and ancillary structures — boundary wall, gate, guard room, septic tank and soak pit, overhead and underground tanks, generator room, pump house.
- Internal services — water supply and sanitary installation (8–10%), electrification (8–10%), and any lift, fire fighting or air conditioning installation.
- External services — approach road, paving, drainage, street lighting, and the external water, sewer and electric connections.
- Landscaping — lawns, plantation, and any architectural treatment.
- Furniture, fixtures and equipment needed to make the facility usable.
- Environmental and social mitigation as required by the IEE or EIA, and resettlement where applicable.
- Establishment and supervision — work-charged establishment (1.5–2%), consultancy and supervision fees.
- Contingencies (3–5%) for unforeseen petty expenses.
- Escalation over the construction period, and taxes (VAT 13%) and duties.
- Maintenance during the defect liability period, where it is at the employer's cost.
Together the internal and external services alone add roughly 20–25% to the bare cost of a building. Omitting them is the single commonest cause of a project estimate falling short.
ENCE 351 §3.5 and §3.6.
A sub-head is a main group of items of the same nature. Grouping the items under sub-heads keeps the abstract readable, lets each trade be priced and checked separately, and makes the running account bill easy to compile.
Building works
| Sub-head | Items included |
|---|---|
| I. Earthwork | Excavation in foundation, excavation in rooms, filling in plinth and sides, surface dressing |
| II. Concrete work | PCC in foundation and floors, RCC in footing, column, beam, slab, lintel; DPC; formwork; reinforcement |
| III. Brick / stone work | Masonry in foundation and plinth, in superstructure, arches, cornice, string course |
| IV. Roofing | RCC slab, CGI sheet over timber or steel truss, tiles, mud roofing, roof treatment |
| V. Flooring | Plastered floor on concrete bed, terrazzo, marble or mosaic, wooden floor, brick floor |
| VI. Wood work | Door and window frames and shutters, trusses, rafters, purlins, eave boards |
| VII. Steel work | Rolled steel sections, trusses, reinforcement bars, grills, bolts and rivets |
| VIII. Finishing | Plastering, pointing, white and colour washing, distempering |
| IX. Painting | Painting, varnishing, polishing |
| X. Miscellaneous | Electrical installation (8–10%), water supply and sanitary installation (8–10%), rain water pipes, minor items |
Road works
Earthwork in cutting and filling · soling · sub-base and base course · surfacing (WBM, premix, bituminous carpet) · cross drainage works (culverts, causeways) · side drains and catch-water drains · retaining and breast walls · protection works · road furniture (signs, guard posts, kilometre stones) · land acquisition.
Water supply works
Source works (intake, well, spring protection) · treatment units · reservoir or overhead tank · transmission and distribution pipes · valves, fittings and specials · public stand posts and house connections · pump house and machinery.
Sanitary works
Sewer lines and manholes · septic tank and soak pit · sanitary fittings (W.C. pan, wash basin, sink, urinal) · soil, waste and vent pipes · traps and gullies · treatment and disposal works.
The general abstract of a project estimate
The general abstract shows only the sub-head totals, not the individual items, and then adds the standard provisions. For an irrigation project it takes this form:
| Sub-head | Amount | |
|---|---|---|
| a | Preliminary expenses (survey, investigation, benchmarks) | Rs … |
| b | Land — acquisition and compensation | Rs … |
| c | Regulator and head works | Rs … |
| d | Cross-drainage works | Rs … |
| e | Bridges | Rs … |
| f | Buildings | Rs … |
| g | Earthwork | Rs … |
| h | Tools and plant (T&P) | Rs … |
| Total | Rs … | |
| i | Maintenance during construction @ 1% of all items except land | Rs … |
| j | Contingency @ 3% on all items except land | Rs … |
| k | Work-charged establishment @ 1.5% on all items except land | Rs … |
| Total estimated cost of the project | Rs … |
Two points are regularly examined here. Contingency, establishment and maintenance during construction are worked out on all the sub-heads except land — land is bought once at a known price and carries no construction risk. And tools and plant is a sub-head in its own right, not part of the contractor's overhead, whenever the department itself provides the plant.
Benefit–cost ratio
An irrigation or other revenue-earning project must also be justified economically:
The ratio must be greater than one for the scheme to be sanctioned — a project that costs more to run than the benefit it returns cannot be justified however well it is engineered.
Four terms that are asked as short notes
| Term | Meaning |
|---|---|
| Work value | The total of all the scheduled items of work in the estimate — that is, the estimated value excluding contingencies, work-charged establishment and tools and plant. Work value is the amount put out to invite tenders. |
| Departmental charges | Where one engineering department executes work on behalf of another department, government or a local body, a charge of 10–15% of the estimated cost is recovered for its own establishment — planning, designing, supervision, pension and audit. It is shown separately from the works expenditure. |
| Administrative approval | The formal acceptance by the administrative department of the proposal to incur expenditure on a work. It is in effect an order to execute the work, and is obtained on the approximate estimate. |
| Technical sanction | The approval of the detailed estimate, designs and specifications by the competent engineering authority, certifying that the proposal is structurally sound and the rates are correct. No work may start until it is obtained. |
Keep the last two apart: administrative approval sanctions the money and comes from the administrative side on the approximate estimate; technical sanction certifies the engineering and comes from the engineering side on the detailed estimate.
Dawadi, Estimating ch.2 §2.2; Pandey & Katwal, Complete Manual §3.3; the general abstract, the "except land" rule, the benefit–cost ratio, work value and departmental charges follow Chakraborti, Estimating, Costing and Specification, §1-14 to §1-16 and ch. XIV §14-5.
3.7 Detail estimation formats (summary of cost, detail quantity estimate, analysis of rate, abstract of cost and bill of quantities)2080
Past Exam Questions on this Topic
- For a construction project of following quantities of works need to be executed with given cost. Prepare Abstract of Cost (AOC), Bill of quantities (BOQ), and Summary of cost including 5% contingency and 13% taxes. S.N. Description of work Quantity Unit Rate (Rs) Earthwork in excavation cu.m 2 Earthwork in backfilling cu.m 3 PCC in foundation cu.m 9,000 2nd class brickwork in foundation [6] (2080 Bhadra, Q.2)
Solution
The quantity and rate columns are not fully legible in the available copy of this question paper — only the PCC rate of Rs 9,000 per m³ survives. Representative quantities and rates are assumed below and are marked as such; substitute the figures printed in your paper. The method, the order of the three statements and the treatment of the 5% contingency and 13% tax are what carry the marks.
Items: earthwork in excavation · earthwork in backfilling · PCC in foundation (Rs 9,000 / m³) · second class brickwork in foundation.
Add 5% contingency and 13% tax (VAT).Bill of Quantities (BOQ)
The BOQ lists the items with their quantities and units, for the contractor to price. The rate and amount columns are left blank in the tender copy.
S.N. Description of work Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation 250.00 m³ — — 2 Earthwork in backfilling 120.00 m³ — — 3 PCC in foundation 45.00 m³ — — 4 2nd class brickwork in foundation 80.00 m³ — — Abstract of Cost (AOC)
The same items, now priced: amount = quantity × rate.
S.N. Description of work Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation 250.00 m³ 400.00 1,00,000.00 2 Earthwork in backfilling 120.00 m³ 250.00 30,000.00 3 PCC in foundation 45.00 m³ 9,000.00 4,05,000.00 4 2nd class brickwork in foundation 80.00 m³ 11,000.00 8,80,000.00 Total cost of works 14,15,000.00 Summary of cost, with contingency and tax
total cost of works = Rs 14,15,000.00 add contingency @ 5% of 14,15,000 = Rs 70,750.00 ----------------- sub-total = Rs 14,85,750.00 add tax (VAT) @ 13% of 14,85,750 = Rs 1,93,147.50 ----------------- TOTAL PROJECT COST = Rs 16,78,897.50S.N. Particulars Amount (Rs) 1 Total cost of works (from AOC) 14,15,000.00 2 Add: Contingency @ 5% 70,750.00 Sub-total 14,85,750.00 3 Add: Tax (VAT) @ 13% 1,93,147.50 Total project cost 16,78,897.50 Total project cost = Rs 16,78,897.50, say Rs 16,78,900.00The order matters and is the point of the question: tax is charged on the cost including contingency, not on the bare cost of works. Taking 13% of 14,15,000 instead would give Rs 1,83,950 and a wrong total. Note also the difference between the three statements — the BOQ is the unpriced schedule issued to tenderers, the AOC is the priced statement of the items, and the summary adds the overheads to give the project cost.
ENCE 351 §3.7.
A detailed estimate is presented in a fixed set of forms. Knowing which form does what — and how the bill of quantities differs from the abstract of cost — is worth several marks nearly every year.
1. Detail quantity (measurement) sheet
Where the quantities are taken out from the drawings. Its columns never change:
| S.N. | Description of item | No. | Length | Breadth | Height / depth | Quantity | Remarks |
|---|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation in foundation | 1 | 19.20 | 0.90 | 0.90 | 15.55 m³ | |
| 2 | PCC 1:3:6 in foundation | 1 | 19.20 | 0.90 | 0.10 | 1.73 m³ |
2. Analysis of rates
The rate of each item built up from materials, labour, plant, overheads and profit (§6).
3. Abstract of cost
Quantity × rate for every item, grouped by sub-head and totalled, with contingencies and work-charged establishment added at the foot.
| S.N. | Description of item | Quantity | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in foundation | 15.55 | m³ | 425.00 | 6 608.75 |
| 2 | PCC 1:3:6 in foundation | 1.73 | m³ | 8 950.00 | 15 483.50 |
| Total | 22 092.25 | ||||
| Add contingencies @ 3% | 662.77 | ||||
| Add work-charged establishment @ 2% | 441.85 | ||||
| Grand total | 23 196.87 | ||||
4. Bill of quantities (BOQ)
The tender document: the same list of items with their quantities and units, but with the rate and amount columns left blank for the bidder to fill in. Priced and signed, it becomes part of the contract and the basis of every running bill.
BOQ and abstract of cost compared
| Bill of quantities | Abstract of cost | |
|---|---|---|
| Purpose | To invite and compare tenders, and to pay the contractor | To arrive at the estimated cost and obtain sanction |
| Prepared by | The employer; priced by the bidder | The estimator |
| Rates shown | Blank when issued; the contractor's own rates when priced | The estimator's analysed rates |
| Status | A contract document | An internal costing document |
| When used | At tendering, and throughout execution for payment | Before tendering, for sanction and budgeting |
The two share the same items, units and quantities — that is the relationship. They differ in whose rates fill the last two columns and in what the document is for.
5. Summary (general abstract) of cost
One line per sub-head or per sub-work, carrying the totals forward to the grand total, so a sanctioning authority can see the shape of the cost on a single page.
Dawadi, Estimating ch.2 §5.3 and chapter 3 estimating; Pandey & Katwal, Complete Manual §3.4.
Sources consulted for this chapter
These are the references actually used in writing this chapter. Where a worked example is taken from one of them, the figure or the sheet is recomputed here from the stated dimensions rather than transcribed.
- Er. Narayan Prasad Dawadi, Estimating and Costing lecture notes (IOE, Pashchimanchal Campus) — types of estimate and the estimate report
- M. Chakraborti, Estimating, Costing and Specification in Civil Engineering — ch. I — kinds of estimate, sub-heads, plinth / carpet / floor area; ch. XIV §14-5 — the general abstract of a project, the rule that contingency and establishment exclude land, and the benefit–cost ratio
- Pandey & Katwal, Complete Manual of Estimating and Costing (T.U., B.E. Civil) — types of estimating, and the abstract and summary formats
- Asst. Prof. Roshan Karki, Estimating and Costing slides, chapters 1–3 — types of estimate