5.1 Pipe culverts, slab culverts and box culverts
A culvert is a cross-drainage structure of span up to about 6 m carrying the road over a small stream. Three kinds are examined:
| Type | Description | Used when |
|---|---|---|
| Pipe culvert | One or more Hume (RCC) pipes bedded in concrete between headwalls | Small discharge; the cheapest option |
| Slab culvert | An RCC slab spanning between two abutments, on a concrete or masonry foundation | Span 1–6 m, firm foundation |
| Box culvert | A monolithic RCC box — base slab, two walls and top slab acting together | Poor foundation, or where the base must resist uplift and scour |
Items for a slab culvert
| S.N. | Item | Unit |
|---|---|---|
| 1 | Earthwork in excavation in foundation, including dewatering | m³ |
| 2 | PCC 1:3:6 levelling course under the footings | m³ |
| 3 | Stone masonry or RCC in abutments and wing walls | m³ |
| 4 | RCC in the deck slab | m³ |
| 5 | Reinforcement in slab and abutment | kg |
| 6 | Formwork to the slab soffit and sides | m² |
| 7 | Wearing coat over the slab | m² or m³ |
| 8 | Parapet / railing | m |
| 9 | Backfilling behind the abutments, with a granular filter | m³ |
| 10 | Apron, floor protection and pitching upstream and downstream | m² |
| 11 | Weep holes | number |
Worked estimate — an RCC slab culvert
Abutments 500 mm thick brick masonry in 1:4, 1.57 m high overall (0.45 footing + 0.90 clear + 0.22 slab), with wing walls 1.40 m long.
Foundation trench 0.80 m wide, 0.75 m deep, on a 300 mm PCC 1:3:6 bed.
Deck slab 220 mm RCC 1:2:4, bearing 500 mm on each abutment.
Reinforcement 16 mm main bars at 100 mm c/c, 10 mm distribution bars at 220 mm c/c, clear cover 25 mm.
Parapets 500 mm and 400 mm wide with a string course; 80 mm PCC wearing coat.
Item 1 — Earthwork in excavation
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Abutment walls | 2 | 5.30 | 0.80 | 0.75 | 6.360 | 5.30 = 5.00 + 2 × 0.15 |
| Wing walls | 4 | 1.40 | 0.80 | 0.75 | 3.360 | 0.75 = 0.45 + 0.30 |
| Total — Earthwork in excavation in foundation | 9.720 | m³ | ||||
Item 2 — PCC 1:3:6 in foundation
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Under the abutment walls | 2 | 5.30 | 0.80 | 0.30 | 2.544 | |
| Under the wing walls | 4 | 1.40 | 0.80 | 0.30 | 1.344 | |
| Total — PCC 1:3:6 in foundation | 3.888 | m³ | ||||
Item 3 — Brickwork in abutments, wing walls and parapets
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Abutment walls up to slab top | 2 | 5.00 | 0.50 | 1.57 | 7.850 | 1.57 = 0.45 + 0.90 + 0.22 slab |
| Wing walls | 4 | 1.40 | 0.50 | 1.57 | 4.396 | |
| Parapet wall, 50 cm | 2 | 5.30 | 0.50 | 0.30 | 1.590 | 0.30 = 0.08 + 0.22 |
| Parapet wall, 40 cm | 2 | 5.30 | 0.40 | 0.40 | 1.696 | |
| String course | 2 | 5.30 | 0.12 | 0.08 | 0.10176 | |
| Slab bearing inside the abutments | 2 | 5.00 | 0.30 | 0.22 | −0.660 | |
| Total — First class brickwork in 1:4 cement mortar | 14.97376 | m³ | ||||
The slab bearing must be deducted from the abutment masonry — that volume is occupied by the RCC slab and is measured as concrete, not as masonry. Omitting the deduction counts the same volume twice.
Item 4 — RCC 1:2:4 in the deck slab
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Deck slab, 220 mm | 1 | 5.00 | 2.10 | 0.22 | 2.310 | 5.00 = 4.00 clear + 2 × 0.50 · 2.10 = 1.50 + 2 × 0.30 |
| Total — RCC 1:2:4 in the deck slab | 2.310 | m³ | ||||
Item 5 — Bar bending schedule
Bar bending schedule — deck slab (one-way, B < L/2)
| Bar | ø (mm) | No. | Cutting length (m) | Total length (m) | kg/m | Weight (kg) | Remarks |
|---|---|---|---|---|---|---|---|
| Main straight, 16 mm | 16 | 26 | 2.34 | 60.84 | 1.580 | 96.14 | n = 5.00/0.10 + 1 = 51, of which 26 straight · L = 2.10 − 2 × 0.025 cover + 2 × 9d |
| Main bent-up, 16 mm | 16 | 25 | 2.49 | 62.25 | 1.580 | 98.37 | the other 25 bars · adds 2 × 0.42 D with D = 0.22 − 2 × 0.015 − 0.016 = 0.174 m |
| Distribution bottom, 10 mm | 10 | 11 | 5.13 | 56.43 | 0.617 | 34.83 | n = 2.10/0.22 + 1 = 11 · L = 5.00 − 2 × 0.025 + 2 × 9d |
| Top holder bars, 10 mm | 10 | 4 | 5.13 | 20.52 | 0.617 | 12.67 | 2 on each side |
| Total weight of steel | 242.01 | kg | |||||
Weight per metre is taken as w = d²/162. Some textbooks use d²/160, which gives figures about 1.2% higher — 1.600 instead of 1.580 kg/m for a 16 mm bar. Either is acceptable provided you state which you have used.
Item 6 — Formwork
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Slab soffit | 1 | 5.00 | 1.50 | — | 7.500 | |
| Slab edges | 2 | — | 2.10 | 0.22 | 0.924 | |
| Total — Formwork to the deck slab | 8.424 | m² | ||||
Item 7 — Wearing coat
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Over the deck | 1 | 4.00 | 2.50 | 0.08 | 0.800 | 2.50 = 1.50 + 2 × 0.50 |
| Total — PCC 1:2:4 wearing coat, 80 mm | 0.800 | m³ | ||||
For a box culvert take the four elements as one unit: base slab, two vertical walls, top slab, plus the haunches. Its great advantage in the estimate is that no separate foundation is needed — the base slab is the foundation.
Geometry after Dawadi, RCC slab culvert; every quantity recomputed here from the dimensions.
5.2 T-beam bridge (superstructure, abutment and pier)
A T-beam bridge has a deck slab cast monolithically with longitudinal girders, so that each girder and the slab above it act as a T. It is the standard medium-span (10–25 m) RCC road bridge.
Superstructure
| Element | How measured |
|---|---|
| Deck slab | overall length × width × thickness, measured over the girders |
| Longitudinal girders | number × length × web width × depth below the slab (the slab is already counted) |
| Cross girders / diaphragms | number × clear length between girders × width × depth |
| Kerb and footpath | length × width × thickness |
| Wearing coat | carriageway area × thickness |
| Railing / parapet | running metre, both sides |
| Bearings and expansion joints | counted |
| Reinforcement | kg, from the bar schedule of each element |
| Formwork | m² — soffit and sides of slab, girders and cross girders |
The single commonest error is double counting the flange. The deck slab is measured across the full width including the part over the girders, so each girder must be measured only for its web below the slab — not its full T-depth.
Worked estimate — superstructure of a T-beam bridge
Four longitudinal girders at 2.40 m centres, 300 mm web, 1.30 m total depth · deck slab 220 mm.
Five lines of cross girders, 250 mm × 1.10 m deep · kerbs 600 × 300 mm · wearing coat 75 mm.
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Deck slab, 220 mm | 1 | 12.60 | 8.40 | 0.22 | 23.2848 | measured right across, over the girders |
| Longitudinal girders — web below the slab | 4 | 12.60 | 0.30 | 1.08 | 16.3296 | web 300 mm × (1.30 − 0.22) deep |
| Cross girders / diaphragms | 15 | 2.10 | 0.25 | 0.88 | 6.930 | 5 lines × 3 bays · clear 2.40 − 0.30 |
| Kerb and footpath | 2 | 12.60 | 0.60 | 0.30 | 4.536 | |
| Wearing coat, 75 mm | 1 | 12.60 | 7.20 | 0.075 | 6.804 | carriageway width only |
| Total — RCC in the superstructure of a T-beam bridge | 57.8844 | m³ | ||||
Abutment and pier
Both are measured as a stack of prisms, bottom upward, each with its own dimensions:
- Foundation / footing — length × breadth × thickness.
- Stem or shaft — where the face is battered, use the mean thickness of top and bottom.
- Cap and bed block under the bearings.
- Dirt wall and wing / return walls for the abutment, measured separately.
- Backfilling behind the abutment, with filter media and weep holes.
One pier
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Footing | 1 | 6.00 | 3.00 | 0.90 | 16.200 | |
| Circular shaft, 1.20 m dia., 5.00 m high | π/4 × 1.20² × 5.00 | 5.65487 | ||||
| Pier cap | 1 | 8.40 | 1.50 | 0.60 | 7.560 | |
| Bed blocks under the bearings | 4 | 0.60 | 0.60 | 0.20 | 0.288 | |
| Total — RCC in one pier | 29.70287 | m³ | ||||
One abutment
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Footing | 1 | 9.00 | 4.00 | 1.00 | 36.000 | |
| Stem — battered face, mean thickness | 1 | 8.40 | 1.05 | 5.00 | 44.100 | mean of 1.50 at the bottom and 0.60 at the top |
| Abutment cap | 1 | 8.40 | 1.50 | 0.60 | 7.560 | |
| Dirt wall | 1 | 8.40 | 0.30 | 1.30 | 3.276 | |
| Return / wing walls, mean thickness | 2 | 4.00 | 0.60 | 3.50 | 16.800 | |
| Total — RCC in one abutment | 107.736 | m³ | ||||
The abutment stem is battered from 1.50 m at the bottom to 0.60 m at the top, so its mean thickness is ½(1.50 + 0.60) = 1.05 m. Using either the top or the bottom thickness alone would be wrong by about 43%.
Dawadi, RCC T-beam, well, septic, caisson, pier; quantities computed here from the stated dimensions.
5.3 Well foundation
A well foundation is a deep foundation sunk through a river bed to a firm stratum below the scour level. It is used where an open foundation cannot be taken down — the standard foundation for bridge piers in Nepal's braided rivers.
Parts, and how each is measured
| Part | Function | Measurement |
|---|---|---|
| Cutting edge | The sharpened steel-shod bottom that helps the well sink | weight of steel in kg; concrete in m³ |
| Well curb | The wedge-shaped RCC ring above the cutting edge | m³ — volume of the tapering ring |
| Steining | The main cylindrical wall of the well | m³ — the annular volume × height |
| Bottom plug | Concrete seal at the base, cast under water | m³ |
| Sand filling | Fills the dredge hole above the bottom plug | m³ |
| Top plug | Concrete seal over the sand filling | m³ |
| Well cap | The RCC slab that transfers the pier load to the well | m³ |
Worked estimate — one well foundation
Well curb 2.00 m high · bottom plug 2.00 m · sand filling 13.00 m · top plug 1.00 m · well cap 7.00 m dia. × 1.50 m thick.
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Well curb — tapering ring, 2.00 m high, mean thickness 1.00 m | π × 5.00 mean dia. × 1.00 × 2.00 | 31.41593 | cutting edge shod with steel | |||
| Steining — 6.00 m outer, 4.00 m inner, 18.00 m high | π/4 ( 6.00² − 4.00² ) × 18.00 | 282.74334 | ||||
| Bottom plug, 2.00 m thick, cast under water | π/4 × 4.00² × 2.00 | 25.13274 | ||||
| Sand filling in the dredge hole, 13.00 m | π/4 × 4.00² × 13.00 | 163.36282 | ||||
| Top plug, 1.00 m thick | π/4 × 4.00² × 1.00 | 12.56637 | ||||
| Well cap, 7.00 m dia., 1.50 m thick | π/4 × 7.00² × 1.50 | 57.72677 | ||||
| Total volume of concrete and filling | 572.94796 | m³ | ||||
Brickwork in well steining is one of the classic "state the unit" questions — it is measured and paid in m³ (§1.2). Sinking of the well is paid separately, per metre of depth, because the effort increases sharply with depth; it is not included in the rate for the steining.
Dawadi, RCC T-beam, well, septic, caisson, pier.
5.4 Earthwork in road construction in plain and hilly areas
Road earthwork means bringing the ground to formation level, by cutting where the ground is high and filling (banking) where it is low. The cross-section is a trapezium.
The s·D² term is the two side triangles taken together: each has base sD and height D, so the two contribute 2 × ½ × sD × D = sD². Cutting and filling normally take different side slopes, which is why sc and sf are kept apart.
Three methods of finding the volume between two sections
Let two cross-sections a distance L apart have depths d₁ and d₂.
| Method | Formula | Character |
|---|---|---|
| 1. Mid-sectional area (average depth) | dm = (d₁ + d₂)/2 Amid = B·dm + s·dm² Q = Amid × L | Averages the depth first. Under-estimates, because A is quadratic in d. |
| 2. Mean sectional area | A₁ = B·d₁ + s·d₁² A₂ = B·d₂ + s·d₂² Q = ½(A₁ + A₂) × L | Averages the areas. Over-estimates, for the same reason. |
| 3. Prismoidal formula | Q = (L/6)(A₁ + 4Amid + A₂) | Combines the two in the ratio 1:4:1. The most accurate, and the one to use unless told otherwise. |
Worked estimate — earthwork along a road
Depths read from the longitudinal section are tabulated below.
Earthwork in FILLING (embankment) — B = 10 m, side slope 2:1
| Chainage (m) | Depth (m) | Area (m²) | Volume by (m³) | |||||
|---|---|---|---|---|---|---|---|---|
| d₁ | d₂ | A₁ | Amid | A₂ | mid-sect. | mean-sect. | prismoidal | |
| 0+000 – 0+030 | 1.00 | 1.60 | 12.000 | 16.380 | 21.120 | 491.40 | 496.80 | 493.20 |
| 0+030 – 0+060 | 1.60 | 1.20 | 21.120 | 17.920 | 14.880 | 537.60 | 540.00 | 538.40 |
| 0+060 – 0+090 | 1.20 | 0.80 | 14.880 | 12.000 | 9.280 | 360.00 | 362.40 | 360.80 |
| Total volume (m³) | 1389.00 | 1399.20 | 1392.40 | |||||
Earthwork in CUTTING — B = 10 m, side slope 2:1
| Chainage (m) | Depth (m) | Area (m²) | Volume by (m³) | |||||
|---|---|---|---|---|---|---|---|---|
| d₁ | d₂ | A₁ | Amid | A₂ | mid-sect. | mean-sect. | prismoidal | |
| 0+120 – 0+150 | 1.20 | 2.00 | 14.880 | 21.120 | 28.000 | 633.60 | 643.20 | 636.80 |
| 0+150 – 0+180 | 2.00 | 1.50 | 28.000 | 23.625 | 19.500 | 708.75 | 712.50 | 710.00 |
| 0+180 – 0+210 | 1.50 | 0.90 | 19.500 | 14.880 | 10.620 | 446.40 | 451.80 | 448.20 |
| Total volume (m³) | 1788.75 | 1807.50 | 1795.00 | |||||
Mid-sectional and mean-sectional bracket the true volume from below and above; the prismoidal formula is Simpson's rule applied to the cross-sectional area and always lies between them. If a question asks you to "compare the methods", that bracketing is the answer — and the worked table above demonstrates it.
Hilly ground — the two-level section
In hilly country the ground itself slopes across the road, so the two side slopes are no longer of the same length and the simple trapezium no longer applies. The section is then a two-level section, and its area is
Do not use A = (B·d + s·d²) × r²/(r² − s²). That expression omits the s·b² term and under-estimates the area — by about 2% in the worked example below, and by more as the formation widens. The full form above is the one that reproduces the tabulated areas exactly, and it is the form Chakraborti derives in §8-7 as s·b² + 2b·r²·H + r²·s·H², all divided by (r² − s²).
A road on a cross slope is called a two-level section, because the ground meets the two side slopes at two different levels. Where the transverse and longitudinal slopes are uniform between two cross-sections, that reach is a two-level section and the formula above applies to it directly.
Worked example — road on a cross slope
Ground cross slope tan θ = 0.1, i.e. 1 vertical in 10 horizontal · cross-sections 20 m apart
Earthwork on a cross slope — two-level section, mean sectional area method
| Chainage | Height of bank d (m) | Sectional area (m²) | Mean area (m²) | Distance (m) | Quantity (m³) |
|---|---|---|---|---|---|
| 5 | 1.20 | 12.005 | — | — | — |
| 6 | 2.05 | 23.958 | 17.982 | 20 | 359.64 |
| 7 | 1.90 | 21.630 | 22.794 | 20 | 455.89 |
| 8 | 1.30 | 13.255 | 17.443 | 20 | 348.85 |
| 9 | 1.20 | 12.005 | 12.630 | 20 | 252.60 |
| 10 | 2.70 | 35.130 | 23.568 | 20 | 471.35 |
| Total quantity | 1888.33 | ||||
Cutting and filling must still be worked out separately, because earth cut on the hill side is used to build up the valley side. The estimate then shows how much material must be borrowed or wasted — which is exactly what a mass haul diagram answers.
The zero point — where cutting changes to filling
Along a hill road the formation crosses the ground surface somewhere between two chainages. That crossing is the zero point (or balance point): the section there is neither cutting nor filling. It must be located, because the cutting volume is measured up to it and the filling volume from it.
Two quantities at the zero point are found by averaging, because the section there is transitional:
Worked illustration. Cutting 0.70 m deep at chainage 30 m, filling 0.80 m high at chainage 60 m; cross slopes 1 in 12 and 1 in 10; formation 8 m in cutting and 10 m in banking:
Note that the cross slope is averaged harmonically, not arithmetically. The arithmetic mean of 12 and 10 would be 11.00; the harmonic mean is 10.909. A slope is a rate, and rates average harmonically — the same reason an average speed over equal distances is a harmonic mean.
Presentation
Road earthwork is set out chainage by chainage exactly as in the tables above — chainage, ground level, formation level, depth of cut or fill, area, mean area, length, and volume of cutting and of filling in separate columns — and the two columns are totalled separately so that the balance of earthwork is visible.
Formulas transcribed from Dawadi, estimating earth work §6.3; the worked table is computed here.
5.5 Estimation of pavement work and retaining works in roads
Pavement work
Once the formation is ready, the pavement is measured layer by layer. Each layer is an area × a compacted thickness:
| Layer | Measurement | Unit |
|---|---|---|
| Preparation of subgrade | formation width × length | m² |
| Granular sub-base | width × length × compacted thickness | m³ |
| Water bound macadam base | as above, each course separately | m³ |
| Prime coat / tack coat | area sprayed | m² |
| Premix carpet, bituminous concrete | area × thickness | m² or m³ |
| Seal coat | area | m² |
| Shoulder | separately from the carriageway | m³ |
Always use the compacted thickness for payment. The loose thickness is greater — 120 mm of loose ballast compacts to about 80 mm — and the difference is absorbed in the rate through the norms.
Worked estimate — one kilometre of metalled road
Average height of bank 0.80 m · side slope 2 : 1 (H:V) · depth of borrow pit 0.30 m
Soling 150 mm boulder · sub-base and base each 120 mm loose compacted to 80 mm · two-coat bituminous surface.
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Survey, centre-line fixing and site clearance | 1 | 1,000.00 | — | — | 1,000.00 | measured per km; right of way 15 m |
| Permanent land required | 1 | 1,000.00 | 30.00 | — | 30,000.00 | m² |
| Earthwork in embankment | 1000 × ( 10 × 0.80 + 2 × 0.80² ) = 1000 × 9.28 | 9,280.00 | m³ — A = B·D + s·D² | |||
| Temporary land for borrowing soil | 9280 / 0.30 borrow-pit depth | 30,933.3333 | m² | |||
| Turfing on the side slopes, both sides | 2 × 1000 × 0.80 × √(1 + 2²) = 2000 × 1.7889 | 3,577.7088 | m² | |||
| Preparation of subgrade, dressing to camber | 1 | 1,000.00 | 5.00 | — | 5,000.00 | m² |
| Soling coat — 75 mm boulder, 150 mm thick | 1 | 1,000.00 | 5.00 | 0.15 | 750.00 | m³ |
| Sub-base — 50 mm ballast, 120 mm loose to 80 mm | 1 | 1,000.00 | 5.00 | 0.12 | 600.00 | m³ |
| Base course — 40 mm ballast, 120 mm loose to 80 mm | 1 | 1,000.00 | 5.00 | 0.12 | 600.00 | m³ |
| Surface, 1st coat — 12 mm ballast @ 0.015 m³/m² | 1000 × 5 × 0.015 | 75.00 | m³ | |||
| Surface, 1st coat — bitumen @ 2 kg/m² | 1000 × 5 × 2 | 10,000.00 | kg | |||
| Surface, 2nd coat — 8 mm ballast @ 0.009 m³/m² | 1000 × 5 × 0.009 | 45.00 | m³ | |||
| Surface, 2nd coat — bitumen @ 1.2 kg/m² | 1000 × 5 × 1.2 | 6,000.00 | kg | |||
The √(1 + s²) factor appears again here. For a 2:1 slope it is √5 = 2.236, so each sloping face is 2.236 times the bank height, not equal to it. Using the height alone would under-measure the turfing by more than half.
Retaining and breast walls
Hill roads need a great deal of retaining work, and it is measured as a stack of prisms exactly like a bridge abutment:
- Retaining wall — holds up filled ground on the valley side.
- Breast wall — supports the cut face on the hill side.
- Toe wall — protects the toe of an embankment.
- Gabion wall — wire crates filled with boulders; measured in m³ of crate, with the wire mesh in m² or by weight.
Worked example — 50 m of stone masonry retaining wall, 0.60 m wide at the top, 1.80 m at the bottom, 4.00 m high, on a 0.30 m PCC bed:
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Earthwork in excavation for the foundation | 1 | 50.00 | 2.20 | 0.80 | 88.000 | m³ |
| PCC 1:3:6 levelling course | 1 | 50.00 | 2.00 | 0.30 | 30.000 | m³ |
| Stone masonry — mean of 0.60 and 1.80 | 1 | 50.00 | 1.20 | 4.00 | 240.000 | ½(0.60 + 1.80) = 1.20 m |
| Granular filter behind the wall | 1 | 50.00 | 0.50 | 4.00 | 100.000 | m³ |
| Coping, 0.60 × 0.15 | 1 | 50.00 | 0.60 | 0.15 | 4.500 | m³ |
| (read row by row — the items go separately to the abstract) | 462.500 | m³ | ||||
Add, separately: weep holes (number, one per 1.5–2 m² of face), and any drainage channel behind or in front of the wall.
Road estimate after Dawadi, 1 km highway, RCC water tank and building §6.6; every quantity recomputed here.
5.6 Earthwork and lining works in irrigation canals
An irrigation canal is estimated the same way as a road — a trapezoidal section repeated along a chainage — but here the section is a channel rather than an embankment, and it usually has to be lined.
Earthwork in the canal
Cutting and filling are kept in separate columns, chainage by chainage, exactly as for a road. Where the canal runs partly in cutting and partly on a bank, the bank itself is a further filling item with its own section.
Lining
Lining reduces seepage and prevents scour. It is measured on the wetted perimeter — the surface actually covered:
Worked estimate — 500 m reach of a lined canal
Reach length 500 m · PCC lining 100 mm thick on bed and sides.
| Description of item | No. | L (m) | B (m) | H / D (m) | Quantity | Remarks |
|---|---|---|---|---|---|---|
| Clearing and grubbing of the alignment | 1 | 500.00 | 12.00 | — | 6,000.00 | m² — alignment plus working width |
| Earthwork in excavation | ( 3.00 × 1.50 + 1.50 × 1.50² ) × 500 = 7.875 × 500 | 3,937.50 | m³ | |||
| Dressing and trimming of the bed and side slopes | P × L = 8.408 × 500 | 4,204.1635 | m² — on the wetted perimeter | |||
| PCC lining, 100 mm thick, on bed and sides | 8.408 × 500 × 0.10 | 420.4163 | m³ | |||
| Service road on the bank | 1 | 500.00 | 3.00 | — | 1,500.00 | m² |
| Turfing of the outer slopes | 2 | 500.00 | 2.70 | — | 2,700.00 | m² — slope length 1.50 × 1.803 |
The √(1 + s²) is simply the slope length of one side per unit depth — for a 1.5:1 side slope it is √(1 + 2.25) = 1.803, so each sloping face is 1.803 D long, not D. Forgetting it under-measures the lining by about half the side area.
Items to be measured
- Clearing and grubbing of the alignment.
- Earthwork in excavation, by class of soil; and earthwork in filling for banks, in compacted layers.
- Dressing and trimming of the bed and side slopes — m².
- PCC or brick lining to bed and sides — m² or m³ on the wetted perimeter.
- Construction joints and expansion joints — running metre.
- Structures on the canal — head regulator, cross regulator, outlets, falls, aqueducts and culverts, each estimated separately.
- Service road on the bank, and turfing of the slopes.
Canal sections after Dawadi, estimating earth work; the hydraulic relations are the standard trapezoidal-channel geometry.
Sources consulted for this chapter
These are the references actually used in writing this chapter. Where a worked example is taken from one of them, the figure or the sheet is recomputed here from the stated dimensions rather than transcribed.
- Er. Narayan Prasad Dawadi, Estimating and Costing lecture notes (IOE, Pashchimanchal Campus) — the 1 km metalled road, the RCC slab culvert, the well foundation and the earthwork formulas
- Notes by RK Sir (course handwritten notes) — the two-level (cross slope) section formula and its worked chainage table — which corrected the formula previously printed here
- Pandey & Katwal, Complete Manual of Estimating and Costing (T.U., B.E. Civil) — the zero (balance) point, the harmonic mean cross slope and the mean formation width at that point
- M. Chakraborti, Estimating, Costing and Specification in Civil Engineering — ch. VIII — earthwork by mid-sectional, trapezoidal and prismoidal formulas, area of turfing, culverts and pavements; §8-7 independently confirms the two-level section formula