Syllabus Topics
1.1 Definition, importance and purpose of estimation208220812080207820762075207420732070206720662065
Past Exam Questions on this Topic
- What is an estimating? Why should prepare before construction work? Describe the data required for the preparation of an estimate. [1+1+4] (2082 Bhadra, Q.1)The third part of this question also belongs to Section 1.3.
Solution
Estimating. An estimate is the process of calculating, in advance, the probable quantity of each item of work and its probable cost, from the drawings and specifications and the rates prevailing at the time. It is prepared before the work is taken up.
Why it must be prepared before construction. Because a client must know what the work will cost before he commits to it. Without an estimate there is no basis to arrange finance, obtain sanction, provide the amount in the budget, order materials, engage labour, fix the completion time, or invite tenders. It is the single document on which the whole administrative and contractual process rests.
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.1 and §1.3.
- Compare estimated cost and actual cost. Write down the unit of measurement and unit of payment for following item of works.
- i) R.C. sunshade with specified width and height
- ii) Thickness specified shutter of doors and windows
- iii) Iron Grills
- iv) Asbestos cement sheet in roofs
The second part of this question also belongs to Section 1.2.Solution
(a) Estimated cost compared with actual cost
Estimated cost Actual cost When known Before the work starts After the work is completed Basis Drawings, specifications and current rates Actual measurements and vouchers of money spent Nature A forecast — approximate A fact — exact Prepared by The estimator / engineer The accounts branch from paid bills Purpose Sanction, budget, tender Final payment, audit, completion report Can it change? Yes — revised estimate No — it is final An estimate can never equal the actual cost because rates fluctuate, site conditions differ from those assumed, the design changes during execution and the tender is accepted above or below the estimated rates. A contingency of 3–5% is provided to absorb the difference.
(b) Units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 R.C. sunshade with specified width and height running metre (m) per m width and thickness are fixed by the specification, so only the length varies 2 Thickness specified shutter of doors and windows square metre (m²) per m² thickness is already specified, so only the area varies 3 Iron grills kilogram (kg) per kg fabricated steel is bought and paid for by weight 4 Asbestos cement sheet in roofs square metre (m²) per m² a thin covering of fixed thickness spread over a surface The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.1 and §1.2; IS 1200.
- a) What is purpose of preparing detail estimate before construction work?
- b) Estimated cost is never equal to the actual cost of a project. Give your opinion.
Solution
a) Purpose of preparing a detailed estimate before construction
A detailed estimate gives the quantity and cost of every item of work separately. It is prepared beforehand in order to:
- know the accurate probable cost and decide the financial feasibility of the work;
- obtain technical sanction and provide the amount in the budget;
- work out the materials, labour and plant required, and programme their supply;
- prepare the bill of quantities and invite tenders on it;
- fix the completion period; and
- check the contractor's running and final bills against measured work.
b) "Estimated cost is never equal to the actual cost" — opinion
The statement is correct, and it is a property of estimating itself, not a defect of the estimator.
Why the estimated cost is never exactly the actual cost
An estimate is a forecast made before the work starts, from assumed data. The actual cost is known only after the work is finished. The two differ because:
- Rates change. The estimate uses the rates prevailing on the day it is prepared; prices of materials, labour and fuel fluctuate during construction.
- Time gap. Sanction, tendering and execution take months or years, during which escalation occurs.
- Site conditions differ from those assumed — unexpected soil, rock, water table, or a longer lead than allowed for.
- Changes in design and extra or substituted items ordered during execution.
- Tender premium. The contract is awarded above or below the estimated rates.
- Errors and omissions in taking out quantities, and approximations in the rate analysis.
- Unforeseen causes — weather, strikes, accidents, scarcity of materials.
This is exactly why a contingency of 3–5% is added to every estimate, and why a revised estimate must be prepared when the cost exceeds the sanctioned amount by more than 5%. A good estimate should come within about ±5–10% of the actual cost.
In my opinion the estimate should therefore be judged not by whether it equals the actual cost — which is impossible — but by whether it falls within a reasonable margin of it. An estimate based on correct drawings, current district rates and standard norms, and honestly provided with contingencies, is a good estimate even though the final bill differs from it.
ENCE 351 §1.1.
- What is estimating and costing? Explain the principle of units. [2+3] (2080 Baishakh, Q.1)
Solution
Estimating and costing
Estimating is calculating in advance the probable quantity of each item of work and the probable cost of the whole work, from the drawings, specifications and prevailing rates.
Costing is determining the actual cost of the work after it has been executed, from measurements actually taken and money actually spent. Estimating looks forward, costing looks back; together they let the engineer forecast the cost, control it during execution, and account for it at the end.
Principle of units. Each item of work is measured in the unit that best expresses the labour and material in it — the unit follows the shape of the item.
Nature of the item Unit Examples All three dimensions vary — volumetric m³ earthwork, concrete, masonry Thin and spread over a surface — thickness fixed by specification m² plastering, pointing, DPC, painting, flooring, formwork Long and thin — only the length varies running m cornice, string course, skirting, hand rail, kerb, pipes Piece or job work — counted number doors, windows, sanitary fittings, trees Sold by weight kg / MT reinforcement, M.S. grills, structural steel Liquid litre paint, bitumen, kerosene The principle is simply this: measure in the dimensions that actually vary. If the specification already fixes a dimension, that dimension drops out of the unit. A 12 mm plaster is paid per m² because its thickness is fixed; concrete is paid per m³ because all three dimensions vary.
ENCE 351 §1.1.
- Explain that estimated cost is never the actual cost. What are the data required for estimating? [3+2] (2078 Bhadra, Q.1)The second part of this question also belongs to Section 1.3.
Solution
a) The estimated cost is never the actual cost
Why the estimated cost is never exactly the actual cost
An estimate is a forecast made before the work starts, from assumed data. The actual cost is known only after the work is finished. The two differ because:
- Rates change. The estimate uses the rates prevailing on the day it is prepared; prices of materials, labour and fuel fluctuate during construction.
- Time gap. Sanction, tendering and execution take months or years, during which escalation occurs.
- Site conditions differ from those assumed — unexpected soil, rock, water table, or a longer lead than allowed for.
- Changes in design and extra or substituted items ordered during execution.
- Tender premium. The contract is awarded above or below the estimated rates.
- Errors and omissions in taking out quantities, and approximations in the rate analysis.
- Unforeseen causes — weather, strikes, accidents, scarcity of materials.
This is exactly why a contingency of 3–5% is added to every estimate, and why a revised estimate must be prepared when the cost exceeds the sanctioned amount by more than 5%. A good estimate should come within about ±5–10% of the actual cost.
b) Data required for estimating
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.1 and §1.3.
- a) List out principle of units of measurement. Explain the data required for preparing detailed estimate.
- b) Mention the various purposes of estimating and costing.
Part a of this question also belongs to Sections 1.2 and 1.3.Solution
a) Principle of units of measurement
Principle of units. Each item of work is measured in the unit that best expresses the labour and material in it — the unit follows the shape of the item.
Nature of the item Unit Examples All three dimensions vary — volumetric m³ earthwork, concrete, masonry Thin and spread over a surface — thickness fixed by specification m² plastering, pointing, DPC, painting, flooring, formwork Long and thin — only the length varies running m cornice, string course, skirting, hand rail, kerb, pipes Piece or job work — counted number doors, windows, sanitary fittings, trees Sold by weight kg / MT reinforcement, M.S. grills, structural steel Liquid litre paint, bitumen, kerosene Data required for preparing a detailed estimate
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
b) Purposes of estimating and costing
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
ENCE 351 §1.1–§1.3.
- What is an estimating? What are the purposes of estimating? Mention various data which are required for preparing detailed estimate. [1+3+2] (2076 Ashwin, Q.1)The third part of this question also belongs to Section 1.3.
Solution
Estimating. Calculating in advance the probable quantity of each item of work and the probable cost of the whole work, from the drawings, the specifications and the rates prevailing at the time.
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.1 and §1.3.
- State, why estimated cost is necessary in construction work. Describe various data required to prepare an estimate. [3+3] (2075 Chaitra, Q.1)The second part of this question also belongs to Section 1.3.
Solution
a) Why the estimated cost is necessary in construction work
Construction consumes large sums over a long period, and the money must be arranged and sanctioned before a single brick is laid. The estimated cost is necessary because it is the only figure available at that stage. Specifically it is needed to:
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
b) Data required to prepare an estimate
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.1 and §1.3.
- Enlist the purposes of preparing an estimate of quantities of work and its cost. [4] (2075 Ashwin, Q.1)
Solution
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
ENCE 351 §1.1.
- a) Mention the various purposes of Estimating.
- b) Write the units of measurement and payment for the following items of work:
- (i) Surface excavation
- (ii) Brick work in well steining
- (iii) Lightening conductor
- (iv) Cornice
Part b of this question also belongs to Section 1.2.Solution
a) Purposes of estimating
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
b) Units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 Surface excavation / surface dressing square metre (m²) per m² the depth is small and fixed (up to 30 cm), so only the area varies 2 Brick work in well steining cubic metre (m³) per m³ solid masonry — all three dimensions vary 3 Lightning conductor running metre (m) per m a long thin item; only the length varies 4 Cornice running metre (m) per m the section is fixed by the drawing; only the length varies The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.1 and §1.2; IS 1200.
- Describe the term estimate. State the necessity of estimated cost in construction work. Mention the various requirements for preparing detailed estimate. [2+2+2] (2073 Shrawan, Q.1(a))The third part of this question also belongs to Section 1.3.
Solution
a) The term "estimate"
An estimate is a written statement, prepared before the work is executed, of the probable quantity of each item of work and its probable cost, worked out from the drawings and specifications at the rates prevailing on the date of preparation.
b) Necessity of the estimated cost
It is needed to judge the financial feasibility of the work, to obtain administrative approval and technical sanction, to provide the amount in the budget, to arrange the materials, labour and plant, to fix the completion period, to invite tenders, and to check the contractor's bills.
c) Requirements for preparing a detailed estimate
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.1 and §1.3.
- a) What are the purposes of Estimating and Costing? Explain the data required for Estimating.
- b) Explain in short the various methods of taking quantities in building works.
The data part of a also belongs to Section 1.3; part b belongs to Chapter 2.Solution
a) Purposes of estimating and costing
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
Data required for estimating
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
b) Methods of taking out quantities in building works
Four methods are in use; all four must give the same total length of wall for the same building, and that identity is the check on the work.
- Long wall — short wall method. Walls running in one direction are taken as long walls measured centre to centre plus one breadth, and those at right angles as short walls measured centre to centre minus one breadth. Suitable when the walls of a room have different thicknesses.
- Centre line method. The total centre-line length of all the walls is found once and multiplied by the breadth and depth of each item, deducting half the breadth for each junction. Quickest, and best when all walls have the same thickness.
- Crossing method. The out-to-out length of the walls is taken and the overlapping corners are deducted. Suitable for simple rectangular plans.
- Bay method. The building is divided into identical bays; one bay is worked out in full and multiplied by the number of bays, the end bays being taken separately. Suitable for long repetitive structures such as barracks and sheds.
ENCE 351 §1.1, §1.3 and Chapter 2.
- What is an estimate? What is meant by quantity survey? Distinguish between estimated cost and actual cost. [3] (2067 Ashadh, Q.1(a))
Solution
Estimate. A statement prepared in advance of the probable quantity of each item of work and its probable cost, based on the drawings, specifications and current rates.
Quantity survey. The complete and itemised schedule of the quantities of every item of work in a project — the measurement side of the estimate, without the rates. When the rates are entered against those quantities it becomes the bill of quantities and hence the estimate. The person who does this work is the quantity surveyor.
Estimated cost distinguished from actual cost
Estimated cost Actual cost When known Before the work starts After the work is completed Basis Drawings, specifications and current rates Actual measurements and vouchers of money spent Nature A forecast — approximate A fact — exact Prepared by The estimator / engineer The accounts branch from paid bills Purpose Sanction, budget, tender Final payment, audit, completion report Can it change? Yes — revised estimate No — it is final ENCE 351 §1.1.
- a) What are the purposes of estimating? ‘An estimate is never the actual cost of the work’, justify your answer.
- b) What are the different types of estimates? How do they differ from each other?
Part b of this question also belongs to Chapter 3.Solution
a) Purposes of estimating
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
"An estimate is never the actual cost of the work" — justification
Why the estimated cost is never exactly the actual cost
An estimate is a forecast made before the work starts, from assumed data. The actual cost is known only after the work is finished. The two differ because:
- Rates change. The estimate uses the rates prevailing on the day it is prepared; prices of materials, labour and fuel fluctuate during construction.
- Time gap. Sanction, tendering and execution take months or years, during which escalation occurs.
- Site conditions differ from those assumed — unexpected soil, rock, water table, or a longer lead than allowed for.
- Changes in design and extra or substituted items ordered during execution.
- Tender premium. The contract is awarded above or below the estimated rates.
- Errors and omissions in taking out quantities, and approximations in the rate analysis.
- Unforeseen causes — weather, strikes, accidents, scarcity of materials.
This is exactly why a contingency of 3–5% is added to every estimate, and why a revised estimate must be prepared when the cost exceeds the sanctioned amount by more than 5%. A good estimate should come within about ±5–10% of the actual cost.
b) Types of estimate and how they differ
Type When prepared How it differs Approximate / preliminary At the very beginning, before detailed drawings exist Cost found from a single overall parameter (plinth area, cube content, per bed, per km). Rough; used to obtain administrative approval. Detailed After complete drawings and specifications are ready Every item measured separately and priced by rate analysis. Accurate; the basis of technical sanction and of the tender. Revised When the sanctioned cost is exceeded by more than 5%, or the rates change materially A fresh detailed estimate with the old and new figures shown side by side and the reason for each variation. Supplementary When additional work not in the original scope becomes necessary A detailed estimate of the extra work only; sanctioned together with the original. Complete With the main estimate Includes every ancillary cost — land, external services, roads, furniture, fees — so that the true total cost of making the work usable is shown. Annual repair / maintenance Every year Covers only petty repairs and upkeep to keep the property in working order. ENCE 351 §1.1 and Chapter 3.
- a) What is an estimate, why it should be prepared before construction work? What are the requirements of estimating?
- b) Under what circumstances different types of estimate is prepared? Describe each of them with conditional examples.
Part b of this question also belongs to Chapter 3.Solution
a) What an estimate is, and why it must precede construction
An estimate is the advance calculation of the probable quantity of each item of work and its probable cost. It must be prepared first because the owner has to know what the work will cost before committing to it — finance must be arranged, sanction obtained, the amount provided in the budget, materials and labour organised, the completion time fixed and tenders invited. Every one of these depends on the estimate.
Requirements of estimating
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
b) Circumstances in which each type of estimate is prepared
- Approximate estimate — when a proposal is first mooted and only the broad size is known. Example: a 40-bed hospital costed at Rs. X per bed to obtain administrative approval.
- Detailed estimate — once the drawings and specifications are complete and technical sanction is sought. Example: a school building measured item by item and priced by rate analysis.
- Revised estimate — when the expenditure will exceed the sanctioned amount by more than 5%. Example: rock is met in the foundation and the excavation rate rises sharply.
- Supplementary estimate — when additional work outside the original scope becomes necessary. Example: a compound wall and gate added to a building already under construction.
- Complete estimate — when the full cost of bringing the work into use is wanted. Example: a residential quarter including land, water supply, sanitation, electrification, approach road and fees.
- Annual repair and maintenance estimate — every year for an existing building. Example: whitewashing, painting and petty repairs of an office.
- Extension / renewal estimate — when an existing work is enlarged or a worn-out part renewed. Example: re-roofing an old shed.
ENCE 351 §1.1 and Chapter 3.
Estimating, costing and quantity survey
Estimating is the process of calculating the quantities of the various items of work in a project and the expenditure likely to be incurred on them. An estimate is therefore the probable cost of the work, worked out theoretically from the drawings, the specifications and the current rates before construction begins.
Costing is the complementary exercise of working out what the work actually cost once it has been done. Quantity survey is the schedule of all the items of work in a project with their quantities taken from the drawings; priced, it becomes the estimate.
Estimated cost and actual cost
| Estimated cost | Actual cost | |
|---|---|---|
| When known | Before the work starts | Only after the work is complete |
| How obtained | Calculated from drawings, specifications and current rates | Compiled by the accounts section from all expenditure actually incurred |
| Nature | Probable — an anticipated figure | Real — a recorded figure |
| Use | Fixing the budget, inviting tenders, awarding the contract | Final payment, audit, and checking the estimator's accuracy |
Why the estimated cost is never exactly the actual cost
This is a standing favourite of the examiners. The estimate is a forecast, and a forecast made months before the work is built cannot match the outturn exactly:
- Rates move. Material, labour and equipment rates change between the date of the estimate and the date of execution — through inflation, fuel prices, or a shortage of a particular material.
- Quantities change. Ground conditions revealed on excavation, design changes and extra items ordered during construction all alter the quantities.
- Site conditions differ from those assumed — sub-soil water, rock, poor access, longer leads for materials.
- Time overruns add establishment and overhead costs and expose the work to further price rises.
- Weather and other natural causes interrupt the programme.
- The estimator's own judgement — the estimate rests on assumed norms, assumed wastage and assumed productivity.
A well-prepared estimate should nevertheless come close. A variance within about ±5–10% is regarded as acceptable; a large variance points to a defective estimate, and that is why the revised estimate exists (§3.3).
Purposes of estimating and costing
- To know the probable cost before the work is taken in hand, so the proposal can be judged and sanctioned.
- To fix the budget and obtain administrative approval and technical sanction.
- To work out the quantities of materials required, so that controlled materials — cement, steel, bricks, timber — can be arranged in time.
- To work out the labour of each category required.
- To work out the tools, plant and equipment required.
- To estimate the time needed and draw up the work schedule.
- To invite tenders, prepare the bill of quantities and arrange the contract.
- To check and control expenditure during execution and to check the contractor's bills.
- To justify the investment from a benefit–cost point of view.
- To help fix standard rent, and for the valuation of the property (§7).
Administrative approval and technical sanction
Administrative approval is the formal acceptance of the proposal, in principle and as to cost, by the administrative authority that needs the work. Technical sanction is the approval of the detailed estimate and design by the competent engineering authority; it certifies that the estimate is structurally and financially sound. Work cannot begin until both are in place, and an expenditure sanction releases the money.
Dawadi, Estimating ch.1 §1.1–1.3; R. Karki, CE 659 slides 1–6; Pandey & Katwal, Complete Manual ch.1.
1.2 Units of measurement and payment2081207420712068
Past Exam Questions on this Topic
- Write down the unit of measurement and payment of given items of works:
- i) Iron grills
- ii) Skirting
- iii) Formworks
- iv) Door window shutters
Solution
S.N. Item of work Unit of measurement Unit of payment Why 1 Iron grills kilogram (kg) per kg fabricated steel is bought and paid for by weight 2 Skirting running metre (m) per m height and thickness are fixed by the specification; only the length varies 3 Formwork (centering and shuttering) square metre (m²) per m² measured on the surface actually in contact with the concrete 4 Door and window shutters square metre (m²) per m² thickness is specified, so only the area varies The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.2; IS 1200.
- Compare estimated cost and actual cost. Write down the unit of measurement and unit of payment for following item of works.
- i) R.C. sunshade with specified width and height
- ii) Thickness specified shutter of doors and windows
- iii) Iron Grills
- iv) Asbestos cement sheet in roofs
Solution
(a) Estimated cost compared with actual cost
Estimated cost Actual cost When known Before the work starts After the work is completed Basis Drawings, specifications and current rates Actual measurements and vouchers of money spent Nature A forecast — approximate A fact — exact Prepared by The estimator / engineer The accounts branch from paid bills Purpose Sanction, budget, tender Final payment, audit, completion report Can it change? Yes — revised estimate No — it is final An estimate can never equal the actual cost because rates fluctuate, site conditions differ from those assumed, the design changes during execution and the tender is accepted above or below the estimated rates. A contingency of 3–5% is provided to absorb the difference.
(b) Units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 R.C. sunshade with specified width and height running metre (m) per m width and thickness are fixed by the specification, so only the length varies 2 Thickness specified shutter of doors and windows square metre (m²) per m² thickness is already specified, so only the area varies 3 Iron grills kilogram (kg) per kg fabricated steel is bought and paid for by weight 4 Asbestos cement sheet in roofs square metre (m²) per m² a thin covering of fixed thickness spread over a surface The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.1 and §1.2; IS 1200.
- a) Mention the various purposes of Estimating.
- b) Write the units of measurement and payment for the following items of work:
- (i) Surface excavation
- (ii) Brick work in well steining
- (iii) Lightening conductor
- (iv) Cornice
Solution
a) Purposes of estimating
Purposes of estimating and costing
- To know the probable cost of the work before it is built, so the owner can decide whether the work is within his means and worth doing.
- To obtain administrative approval and technical sanction, and to provide for the amount in the budget.
- To work out the quantities of materials required, so they can be ordered and arranged in good time.
- To work out the labour of each category required, and to programme it.
- To work out the plant and equipment required.
- To fix the completion period from the quantum of work.
- To invite tenders and prepare the bill of quantities on which contractors quote their rates.
- To check and pass the contractor's running and final bills from actual measurements.
- To fix the rent, valuation or compensation of a property.
- To justify the investment from a cost–benefit point of view.
b) Units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 Surface excavation / surface dressing square metre (m²) per m² the depth is small and fixed (up to 30 cm), so only the area varies 2 Brick work in well steining cubic metre (m³) per m³ solid masonry — all three dimensions vary 3 Lightning conductor running metre (m) per m a long thin item; only the length varies 4 Cornice running metre (m) per m the section is fixed by the drawing; only the length varies The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.1 and §1.2; IS 1200.
- Write five units of measurement of each length, area and volume. [5] (2074 Chaitra, Q.1)
Solution
Five items measured in each of the three principal units:
Measured by length (running m) Measured by area (m²) Measured by volume (m³) 1. Cornice and string course 1. Plastering 1. Earthwork in excavation and filling 2. Skirting and dado 2. Pointing 2. Plain and reinforced cement concrete 3. Hand rail and kerb 3. Damp proof course 3. Brick masonry 4. Rain water pipe, G.I. pipe 4. White washing, painting, distempering 4. Stone masonry 5. R.C. sunshade of specified width 5. Flooring, formwork, roof covering 5. Timber in beams and posts The rule behind the table: an item is measured in the dimensions that vary. If the specification fixes the thickness, the item drops to an area; if it fixes two dimensions, it drops to a length.
ENCE 351 §1.2.
- List most common units of measurement and payment for civil works and sanitary works (at least five from each). [5] (2071 Chaitra, Q.3)
Solution
a) Civil works — common units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 Earthwork in excavation / filling m³ per 100 m³ all three dimensions vary; a bulk item, so paid per 100 units 2 Plain and reinforced cement concrete m³ per m³ solid work — all three dimensions vary 3 Brick and stone masonry m³ per m³ solid work 4 Plastering, pointing, painting m² per m² thickness fixed by specification 5 Steel reinforcement in RCC kg per kg or per MT sold by weight b) Sanitary works — common units of measurement and payment
S.N. Item of work Unit of measurement Unit of payment Why 1 G.I. / C.I. / PVC pipe laid and fixed running metre (m) per m the diameter is specified; only the length varies 2 Water closet, wash basin, sink, urinal number (no.) per number counted articles 3 Bib cock, stop cock, gully trap, floor trap number (no.) per number counted articles 4 Manhole and inspection chamber number (no.) per number counted, classified by size and depth 5 Septic tank and soak pit number, or m³ of capacity per number counted as a complete unit of specified capacity The unit of measurement is the unit in which the quantity is taken out; the unit of payment is the unit against which the rate is quoted. They are usually the same, but for bulk items payment is often per 100 or per 10 units (earthwork per 100 m³) to keep the rate a convenient number.
ENCE 351 §1.2; IS 1200.
- a) How are the following items of work measured? What are their units of measurement and payment?
- (i) Pointing work
- (ii) Steel reinforcement
- b) Explain what do you understand by:
- (i) Bill of quantities
- (ii) Contingency
- c) Explain why approximate estimate of any structure is done before the detailed estimate and final cost is worked out.
Part a also belongs to Section 1.4; parts b and c belong to Chapter 3.Solution
a) How the items are measured, and their units
(i) Pointing work. Pointing is raking out the joints of masonry to about 15–20 mm and refilling them with a richer mortar, finished to a pattern (flush, ruled, weathered, tuck). It is measured as the area of the finished wall face, the length multiplied by the height, and not the area of the joints. Openings are deducted by the same rules as for plastering. Units: measured in m², paid per m².
(ii) Steel reinforcement. Measured as the length of each bar in position, taken from the bar bending schedule — including hooks, bends, laps and cranks — and converted to weight at the standard rate
weight per metre w = d² / 162 kg/m ( d in mm )Chairs, spacers, binding wire and rolling margin are not measured separately; they are covered by the rate. Units: measured in kg (or quintal / MT), paid per kg.
b) (i) Bill of quantities. A tabulated schedule listing every item of work in a project with its brief description, the estimated quantity, the unit, the rate and the amount. Contractors quote their rates against these quantities, so all tenders become directly comparable; the same document is later used to measure and pay for the work actually done.
(ii) Contingency. A lump sum, normally 3–5% of the estimated cost, added to the estimate to meet small unforeseen expenses and minor omissions that cannot be listed at the time of estimating. It is not meant for a change of scope — that needs a supplementary or revised estimate.
c) Why an approximate estimate is made before the detailed estimate
- At the proposal stage the detailed drawings do not yet exist, so a detailed estimate is impossible; only an overall parameter such as plinth area or number of beds is known.
- It is quick and cheap, whereas a detailed estimate takes considerable time and money. There is no sense in spending that effort on a scheme that may be rejected.
- It lets the competent authority decide whether the scheme is worth pursuing and grant administrative approval, and lets the amount be provided in the budget.
- It allows alternative schemes and sites to be compared on cost before one is chosen.
- It fixes the order of magnitude, so that the detailed estimate prepared later can be checked against it.
ENCE 351 §1.2, §1.4 and Chapter 3.
- a) How are the following items of work measured? What are their units of measurement and payment?
Principle of units of measurement
The unit chosen for an item must reflect the way the item actually consumes material and labour, so that the quantity multiplied by the rate gives a fair cost. The rule follows the shape of the work:
| If the work is… | Measure in | Examples |
|---|---|---|
| Thick and voluminous — all three dimensions matter | cubic metre (m³) | earthwork in excavation, brickwork in walls, PCC, RCC, stone masonry |
| Thin and spread over a surface — thickness is fixed by specification | square metre (m²) | plastering, pointing, DPC, white washing, painting, flooring, formwork |
| Long and thin — only length varies | running metre (m) | cornice, string course, dado, skirting, hand rail, kerb, ridges |
| Piece or job work — counted | number (no.) | W.C. pan, wash basin, taps, fans, switches, tube lights, trees |
| Sold by weight | kilogram / metric tonne | reinforcement bars, M.S. grills, nails, structural steel |
| Liquid | litre | paint, kerosene, turpentine, bitumen emulsion |
Two further principles: measurements are taken to a stated degree of accuracy (generally 0.01 m for linear dimensions), and the unit of payment may be a convenient multiple of the unit of measurement — earthwork is measured in m³ but paid per 100 m³.
Units of measurement and payment
| Item of work | Unit of measurement | Unit of payment |
|---|---|---|
| Earthwork | ||
| Earthwork in excavation in foundation | m³ | per 100 m³ |
| Earthwork in filling | m³ | per 100 m³ |
| Surface excavation / surface dressing | m² | per m² |
| Brick and stone work | ||
| Brickwork in foundation, plinth and superstructure | m³ | per m³ |
| Half-brick thick partition wall | m² | per m² |
| Honey-comb brickwork (one brick thick) | m² | per m² |
| Brickwork in well steining | m³ | per m³ |
| Brick flat soling | m² | per m² |
| Brick on edge soling / edging on road | m | per m |
| Concrete work | ||
| PCC and RCC in foundation, slab, beam, column | m³ | per m³ |
| PCC of specified thickness in floor, DPC | m² | per m² |
| Centering and shuttering (formwork) | m² | per m² |
| Steel reinforcement for RCC | kg or MT | per kg or MT |
| Wood work | ||
| Door and window frame (chaukhat) | m³ | per m³ |
| Thickness-specified shutters of doors and windows | m² | per m² |
| Wooden partition, false ceiling | m² | per m² |
| Finishing | ||
| Cement plaster, pointing | m² | per m² |
| White washing, colour washing, distempering, painting | m² | per m² |
| Cornice, string course, skirting, dado | m | per m |
| Miscellaneous | ||
| Iron grills, M.S. work | kg | per kg |
| Asbestos cement sheet in roofs | m² | per m² |
| RC sunshade of specified width and height | m | per m |
| Lightning conductor | m | per m |
| Rain water pipe, G.I. pipe | m | per m |
| W.C. pan, wash basin, sink, tap, fan, switch | number | per number |
| Hand rail | m | per m |
Watch the three that are regularly mis-answered: an RC sunshade of specified width and height is a running metre item (the section is fixed, only the length varies); a thickness-specified shutter is m² (not m³, because the thickness is already specified); and iron grills are kg, not m².
Dawadi, Estimating ch.1 §1.4–1.5; units cross-checked against IS 1200 and the Nepal DoR / DUDBC norms.
1.3 Data required for estimation of civil engineering works2081
Past Exam Questions on this Topic
- List out the data required for detail estimate of any construction projects. This syllabus point is almost always examined together with the definition and purpose of estimating. The following questions of Section 1.1 also ask for the data required for estimation and must be studied here as well: Q1, Q5, Q6(a), Q7, Q8, Q11, Q12(a). [3] (2081 Bhadra, Q.1)
Solution
Data required for preparing a detailed estimate
- Drawings — complete and fully dimensioned plans, elevations, sections and detail drawings to scale. Without these no quantity can be taken out.
- Specifications — general specifications stating the class and quality of materials, and detailed specifications stating the proportion of the mix and the method of doing each item.
- Schedule of rates — the current district rate of materials, labour and carriage, and the rates of finished items of work.
- Standard rate-analysis norms — the departmental norms giving the material, labour and plant required per unit of each item.
- Standard method of measurement (IS 1200 or the departmental rules) — so that quantities are taken out and paid in a uniform way.
- Site conditions — nature of soil, water table, availability of materials and water, lead and lift, access and transport, and local labour rates.
- Provision for contingencies, work-charged establishment, and the cost of external services such as water supply, sanitation and electrification.
ENCE 351 §1.3.
Data required for preparing an estimate
Four things are needed before an estimate can be started. The examiners ask for this list very often, usually for 3–5 marks.
- Drawings — complete, fully dimensioned plans, elevations, sections and detail drawings. Without dimensions no quantity can be taken out. For a building this means the site plan, floor plans, at least two sectional elevations and details of foundation, doors, windows, staircase and roof.
- Specifications — these state the nature and class of the work, the quality and proportion of the materials and the workmanship expected. They fix what the rate has to cover.
- General (brief) specification gives only the general idea of the class of work — used for approximate estimates.
- Detailed specification describes each item fully: materials, proportions, method of preparation and execution, and the mode of measurement. It forms part of the legal contract document.
- Rates — the current rates of materials at site, of each category of labour, of hire of tools and plant, and of carriage. These come from the district rate list, and are combined into an item rate by analysis of rates (§6).
- Norms — the government's standard schedule stating how much material, labour and equipment one unit of each item consumes. Norms are uniform across the country; only the district rates differ. They stop estimators from varying an estimate arbitrarily.
To these four the Manual adds the mode of measurement (IS 1200 or the departmental equivalent), because the same wall can give different quantities depending on how deductions are taken.
What makes a rate vary
The same item can carry different rates on two sites. The rate depends on the quantity and quality of materials, their availability and lead to site, the location and accessibility of the site, the availability and category of labour, the nature of the work, the facilities to be provided to labour, the contractor's expected profit and overheads, and the standard of management and supervision.
Dawadi, Estimating ch.1 §1.6; Pandey & Katwal, Complete Manual §1.4.
1.4 Method of measurement of earthwork, plaster work, brick work, concrete work, reinforcement and wood work20802079207620712067
Past Exam Questions on this Topic
- a) (i) What is lead and lift? (ii) Prepare the rate analysis for M20 PCC work in 10 m × 10 m × 1 m raft foundation.
- b) Write the method of deduction work for plastering work as per IS-1200.
- c) Explain in detail how Nepal Government agencies take norms and rates for rate analysis. (Parts a and c of this question also belong to Chapter 6.)
Solution
a) (i) Lead and lift
Lead. The horizontal distance through which excavated earth or a material is carried from the point where it is dug or stacked to the point where it is used or deposited. The first 30 m is normally included in the rate for earthwork; beyond that, extra carriage is paid in stages (30 m, 100 m, 500 m, 1 km, and then per km).
Lift. The vertical height through which the material is raised or lowered above or below the ground level at the point of excavation. The first 1.5 m is included in the rate; each additional 1.5 m of lift is paid extra.
lead → horizontal → free up to 30 m lift → vertical → free up to 1.5 mBoth matter because the same item of work costs different amounts at different places. Two identical foundations, one beside the spoil dump and one 300 m away and 4 m deep, cannot carry the same rate — lead and lift are how the difference is measured and paid.
a) (ii) Rate analysis for M20 PCC in a 10 m × 10 m × 1 m raft foundation
Raft 10 m × 10 m × 1 m · M20 concrete, mix 1 : 1½ : 3
Dry volume factor 1.54 · cement 1440 kg/m³ · 1 bag = 50 kg
Rates assumed (take these from your district rate): cement Rs 850/bag, sand Rs 2,500/m³, coarse aggregate Rs 2,800/m³, mason Rs 1,200/day, unskilled Rs 900/dayVolume of concrete
V = 10 × 10 × 1 = 100 m³Materials for 1 m³ of 1:1½:3 concrete
dry volume = 1.00 × 1.54 = 1.54 m³ sum of proportions = 1 + 1.5 + 3 = 5.5 cement = 1.54 × (1/5.5) = 0.28 m³ = 403.20 kg = 8.064 bags sand = 1.54 × (1.5/5.5) = 0.42 m³ aggregate = 1.54 × (3/5.5) = 0.84 m³ check : 0.28 + 0.42 + 0.84 = 1.54 m³ ✓Rate analysis for 1 m³ of M20 concrete
S.N. Particulars Quantity Unit Rate (Rs) Amount (Rs) A. Materials 1 Cement 8.064 bag 850.00 6,854.40 2 Sand 0.42 m³ 2,500.00 1,050.00 3 Coarse aggregate 0.84 m³ 2,800.00 2,352.00 Sub-total, materials 10,256.40 B. Labour 4 Mason (skilled) 0.35 man-day 1,200.00 420.00 5 Unskilled labour 3.00 man-day 900.00 2,700.00 Sub-total, labour 3,120.00 C. Plant and sundries 6 Mixer and vibrator, hire and fuel 1 job 250.00 250.00 7 Water and sundries @ 1.5% of materials — — — 153.85 Sub-total (A + B + C) 13,780.25 Add overhead and contractor's profit @ 15% 2,067.04 Rate per m³ of M20 concrete 15,847.29 Cost of the raft, and total materials
cost = 100 m³ × Rs 15,847.29 = Rs 15,84,729.00 total materials for the raft : cement = 8.064 × 100 = 806.4 bags ( ≈ 40,320 kg ) sand = 0.42 × 100 = 42.00 m³ aggregate = 0.84 × 100 = 84.00 m³Rate of M20 concrete = Rs 15,847.29 per m³; cost of the 100 m³ raft ≈ Rs 15,84,729, requiring 806.4 bags of cement, 42 m³ of sand and 84 m³ of coarse aggregate.Reinforcement, formwork and excavation are separate items and are not included in this rate. The rates used above are illustrative — in the examination take them from the district rate and say so.
b) Method of deduction for plastering work as per IS 1200
Plastering is measured as the whole face of the wall, and openings are then deducted on a three-band rule based on the area of the opening:
Area of the opening Deduction Jambs, soffits and sills Up to 0.5 m² No deduction Not measured Above 0.5 m² up to 3 m² Deduct for one face only Not measured Above 3 m² Deduct both faces (full area) Measured and added Further: no deduction is made for the ends of beams, posts, rafters and steps; where the two faces of a wall are plastered in different mortars the deduction is worked out separately for each face; and the measurement is taken between the finished faces.
The rule is one of compensation. A small opening costs more labour at its reveals than the plaster it saves, so nothing is deducted; a medium one roughly balances on one face; only a large opening genuinely saves plaster, and then its reveals must be paid for separately.
c) How Nepal Government agencies take norms and rates
How Nepal Government agencies take norms and rates for rate analysis
Two different things are combined, and the distinction is the point of the question.
Norms Rates What it gives The quantity of material, labour and plant needed for one unit of an item The price of one unit of each material and one man-day of each class of labour Who fixes it The Department of Urban Development and Building Construction (DUDBC) for buildings, the Department of Roads (DoR) for roads, and the Department of Water Supply and Sewerage (DWSS) for sanitary works The District Rate Fixation Committee, headed by the Chief District Officer Scope National — the same everywhere in the country Local — different in every district How often revised Rarely — only when technology or practice changes Every fiscal year, and published as the district rate Example 1 m³ of 1:2:4 PCC needs 6.34 bags of cement, 0.44 m³ sand, 0.88 m³ aggregate, 0.35 mason and 3 labourers In that district a bag of cement costs Rs 850 and an unskilled man-day Rs 900 The procedure followed
- The norms are taken from the relevant departmental Norms for Rate Analysis — DUDBC for building works, DoR (Standard Norms for Road Works) for roads, DWSS for water supply and sanitary works.
- The basic rates of materials and labour are taken from the district rate published each year by the District Rate Fixation Committee for that district.
- Carriage is added to each material for the actual lead from its quarry or market to the site, using the rate per unit per km in the district rate, supported by a lead statement.
- Quantity from the norm × rate from the district rate = cost of that component; the components are summed.
- Water and sundries (1–2%), overheads and contractor's profit (together about 15–20%) are added.
- The analysed rate is entered in the abstract of cost; VAT at 13% is added at the summary stage.
- Items not covered by any norm are analysed separately from first principles and got approved as non-scheduled items.
The reason for the split is control. Norms are technical and must not vary from district to district; prices genuinely do vary, so they are fixed locally and annually. Mixing the two up — using another district's rate, or an out-of-date norm — is the commonest audit objection.
ENCE 351 §1.4, §6.2, §6.4 and §6.5.
- What are the necessary points that needs to be considered while measuring earthwork? In what case do you need to prepare revise estimate? Explain with an example. [4+4] (2079 Bhadra, Q.2)The second part of this question also belongs to Chapter 3.
Solution
a) Points to be considered while measuring earthwork
- Classification of the soil — soft/ordinary soil, hard soil, soft rock and hard rock requiring blasting are measured and paid separately, because the effort differs greatly.
- Lead — the horizontal distance the excavated earth is carried. The first 30 m is normally included in the rate; beyond that, extra lead is paid in stages.
- Lift — the vertical height through which the earth is lifted. The first 1.5 m is included in the rate; each additional 1.5 m is paid extra.
- Depth of excavation, measured from the existing ground level, and taken in stages where the depth is large.
- Dewatering — excavation below the water table or in slush is measured separately.
- Working space and side slopes — measure the authorised dimensions of the trench as per drawing; extra excavation for the convenience of the contractor is not paid.
- Excavation and filling kept separate, and the volume of filling measured after compaction, not loose.
- Bulking and shrinkage — earth increases in volume when loosened and reduces when compacted, so the state in which the measurement is taken must be stated.
- Unit — measured in m³ and generally paid per 100 m³. Surface dressing up to 30 cm deep is measured in m².
b) When a revised estimate is required
A revised estimate is a fresh detailed estimate prepared for a work already sanctioned. It becomes necessary when:
- the expenditure exceeds, or is likely to exceed, the sanctioned amount by more than 5%;
- the rates adopted in the original estimate have changed materially;
- there is a substantial change in the design, specification or scope;
- site conditions turn out to differ from those assumed; or
- the work has been abandoned and is restarted after a long interval.
Example. A rural road was sanctioned for Rs. 2.00 crore on the assumption of ordinary soil throughout. On excavation, hard rock was met over 600 m of the alignment, raising the excavation cost and requiring additional breast walls. The anticipated cost rose to Rs. 2.35 crore — an excess of 17.5%, far beyond 5% — so a revised estimate was prepared showing the original and revised quantity and cost of each item side by side, with the reason for every variation, and was submitted for fresh sanction.
ENCE 351 §1.4 and §3.3.
- Briefly explain the method of quantity estimate for road construction. Workout the quantities of earthwork in embankment and cutting. [2+10] (2079 Bhadra, Q.8)The second part of this question belongs to Chapter 5; the earthwork data table is given with the original question paper.
Solution
a) Method of quantity estimate for road construction
A road is a long structure of nearly uniform cross-section, so it is estimated chainage by chainage rather than item by item over a plan. The procedure is:
- Carry out a longitudinal survey and plot the ground level and the proposed formation level at every chainage (usually every 20–30 m).
- At each chainage find the depth of cutting or height of filling, D = GL − FL for cutting, FL − GL for filling.
- Work out the cross-sectional area at each chainage from the trapezoidal section.
- Find the volume between successive chainages by the mid-sectional, mean-sectional or prismoidal method, keeping cutting and filling in separate columns.
- Total the two columns separately to get the balance of earthwork, and hence the quantity to be borrowed or wasted.
- Add the pavement layers, cross drainage, protection works and furniture as separate items, and abstract the cost.
A = B·D + s·D² B = formation width, D = depth, s = side slope 1. mid-sectional : dm = (d₁+d₂)/2 ; Amid = B·dm + s·dm² ; Q = Amid × L 2. mean-sectional : Q = ½(A₁ + A₂) × L 3. prismoidal : Q = (L/6)(A₁ + 4Amid + A₂)b) Worked example
Formation width B = 10 m, side slope s = 2:1 in both cutting and filling, cross-sections at 30 m intervals. Depths from the longitudinal section:
Filling (embankment): d₁ = 1.0 m, d₂ = 1.6 m
Cutting: d₁ = 1.2 m, d₂ = 2.0 mEmbankment (filling) — prismoidal method
A₁ = 10(1.0) + 2(1.0)² = 10.00 + 2.00 = 12.00 m² A₂ = 10(1.6) + 2(1.6)² = 16.00 + 5.12 = 21.12 m² dm = (1.0 + 1.6)/2 = 1.30 m Amid = 10(1.30) + 2(1.30)² = 13.00 + 3.38 = 16.38 m² Qfill = (30/6)[12.00 + 4(16.38) + 21.12] = 5 [12.00 + 65.52 + 21.12] = 5 × 98.64 = 493.20 m³Cutting — prismoidal method
A₁ = 10(1.2) + 2(1.2)² = 12.00 + 2.88 = 14.88 m² A₂ = 10(2.0) + 2(2.0)² = 20.00 + 8.00 = 28.00 m² dm = (1.2 + 2.0)/2 = 1.60 m Amid = 10(1.60) + 2(1.60)² = 16.00 + 5.12 = 21.12 m² Qcut = (30/6)[14.88 + 4(21.12) + 28.00] = 5 [14.88 + 84.48 + 28.00] = 5 × 127.36 = 636.80 m³Balance of earthwork
surplus = 636.80 − 493.20 = 143.60 m³ of cut to be disposed ofEarthwork in embankment = 493.20 m³, earthwork in cutting = 636.80 m³; the cut exceeds the fill by 143.60 m³, which must be carried to spoil.Had the mid-sectional method been used the answers would be 5×98.28 = 491.40 and 5×126.72 = 633.60 m³ — slightly less; the mean-sectional method gives 496.80 and 642.60 m³ — slightly more. The prismoidal result lies between the two, as it always does.
ENCE 351 §5.4; formulas after Dawadi, estimating earth work.
- Explain the following:
- a) Multiplying factors adopted of Panelled door and Louver door.
- b) Rules for deductions from plastering for opening brick surfaces.
- c) Bill of quantities and abstract of cost.
Part c of this question also belongs to Chapter 3.Solution
a) Multiplying factors for a panelled door and a louvered door
Painted joinery is measured flat (the overall area of the opening, taken once) and multiplied by a factor that covers both faces and all edges:
Type Factor Reason Panelled door 1.30 Sunk panels, mouldings and rebates give roughly 30% more painted surface than a flat area of the same size Louvered (venetian) door 1.80 Each louver blade presents two faces and four edges, so the painted surface is far greater — the largest factor of all For comparison: flush door 1.20, fully glazed 0.80, partly panelled and partly glazed 1.00.
Rules for deduction from plastering for openings in brick surfaces (IS 1200)
Plastering is measured as the whole face of the wall, and openings are then deducted on a three-band rule that depends on the area of the opening:
Area of the opening Deduction Jambs, soffits and sills Up to 0.5 m² No deduction Not measured Above 0.5 m² and up to 3 m² Deduct for one face only Not measured Above 3 m² Deduct for both faces (full area) Measured and added The logic is compensation. A small opening costs more labour at its edges than the plaster it saves, so nothing is deducted. A medium opening roughly balances on one face. Only a large opening genuinely saves plaster, and then the reveals have to be paid for separately.
Further points: no deduction is made for the ends of beams, posts and rafters; no deduction for openings up to 0.5 m² each even if there are many; and where the two faces of a wall are plastered with different mortars, the deduction is made separately for each face.
c) Bill of quantities and abstract of cost
Bill of quantities (BOQ). A tabulated schedule of every item of work in the project, giving a brief description, the estimated quantity, the unit, the rate and the amount. It is issued with the tender documents so that all contractors price the same quantities and their offers can be compared directly; it later becomes the document against which work is measured and paid.
Abstract of cost. The final summary sheet of the detailed estimate, in which the quantity of each item — brought forward from the measurement sheet — is multiplied by its analysed rate to give the amount, and the amounts are totalled. To that total are added contingencies (3–5%) and work-charged establishment (1.5–2%) to give the estimated cost of the work.
Bill of quantities Abstract of cost Purpose To invite and compare tenders, and to pay for work done To arrive at the total estimated cost for sanction Rates used Quoted by the contractor Obtained from the estimator's rate analysis Stage Tender and execution Preparation of the estimate Contains Item, quantity, unit, rate, amount The same, plus contingencies, establishment and the grand total ENCE 351 §1.4 and §3.7; IS 1200.
- Explain the following:
- a) Multiplying factors adopted in painting of Panelled door, flush door, Louver door and Glazed window.
- b) Rules for deductions from plastering for opening in brick surfaces.
- c) Bill of quantities.
Part c of this question also belongs to Chapter 3.Solution
a) Multiplying factors in painting
Multiplying factors in painting of doors and windows
Painted joinery is measured flat — the overall area of the opening, measured once — and then multiplied by a factor that accounts for the extra or lesser surface actually painted. The factor covers both faces including all edges and rebates.
Type of door / window Multiplying factor Why Panelled door 1.30 Mouldings and sunk panels give more surface than a flat area Flush door 1.20 Plain faces, only the edges add a little Fully glazed door or window 0.80 Most of the area is glass, which is not painted Partly panelled and partly glazed 1.00 The two effects cancel Louvered (venetian) door or window 1.80 Every louver blade has two faces and edges — much the largest area Fully glazed steel door / window 0.50 Partly glazed or panelled steel 0.80 Weather boarding 1.20 Corrugated sheeting 1.14 Order to remember: louvered 1.80 > panelled 1.30 > flush 1.20 > partly glazed 1.00 > fully glazed 0.80. The more broken the surface, the bigger the factor; glass reduces it.
Rules for deduction from plastering for openings in brick surfaces (IS 1200)
Plastering is measured as the whole face of the wall, and openings are then deducted on a three-band rule that depends on the area of the opening:
Area of the opening Deduction Jambs, soffits and sills Up to 0.5 m² No deduction Not measured Above 0.5 m² and up to 3 m² Deduct for one face only Not measured Above 3 m² Deduct for both faces (full area) Measured and added The logic is compensation. A small opening costs more labour at its edges than the plaster it saves, so nothing is deducted. A medium opening roughly balances on one face. Only a large opening genuinely saves plaster, and then the reveals have to be paid for separately.
Further points: no deduction is made for the ends of beams, posts and rafters; no deduction for openings up to 0.5 m² each even if there are many; and where the two faces of a wall are plastered with different mortars, the deduction is made separately for each face.
c) Bill of quantities
A bill of quantities is a tabulated schedule of all the items of work in a project, each with a brief description, the estimated quantity, the unit, the rate and the amount. Its importance is that:
- all tenderers price the same quantities, so their offers are directly comparable;
- the contractor need not take out quantities himself, which saves time and avoids disputes;
- it becomes the basis for measuring and paying the work actually executed, and for valuing variations; and
- it gives the owner an item-wise picture of where the money goes.
Typical format:
S.N. Description of item Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation in ordinary soil 120.00 m³ 350.00 42,000.00 2 PCC 1:3:6 in foundation 18.50 m³ 9,000.00 1,66,500.00 Total 2,08,500.00 ENCE 351 §1.4 and §3.7; IS 1200.
- a) Explain with neat sketches to workout quantity of semi-circular arch (span, thickness and rise of arch given).
- b) Prepare tables of quantity sheet and abstract cost for a residential building.
- c) What is Bill of quantities? State its importance. (Parts b and c of this question also belong to Chapter 3.)
Solution
a) Quantity of a semi-circular arch
A semi-circular arch over a span L has its centre at mid-span, so the rise r = L/2 and the intrados (soffit) is a semicircle of radius L/2. If the arch ring is of thickness t measured radially and the wall is of breadth b, the arch is the volume of a half hollow cylinder.
internal radius R₁ = L / 2 ( = the rise of a semi-circular arch ) external radius R₂ = R₁ + t = L/2 + t area of the arch ring (half annulus) A = ½ × π ( R₂² − R₁² ) volume of arch V = A × b = ½π( R₂² − R₁² ) × b equivalently, using the MEAN radius Rm = R₁ + t/2 : length of centre line of the ring = π Rm V = π Rm × t × b ← the quicker formNumerical illustration. Span L = 2.0 m, ring thickness t = 0.30 m, wall breadth b = 0.30 m:
R₁ = 2.0/2 = 1.00 m rise = 1.00 m R₂ = 1.00 + 0.30 = 1.30 m A = ½ × π (1.30² − 1.00²) = ½ × π (1.69 − 1.00) = ½ × π × 0.69 = 1.0838 m² V = 1.0838 × 0.30 = 0.325 m³ check by the mean-radius form: Rm = 1.00 + 0.15 = 1.15 m V = π × 1.15 × 0.30 × 0.30 = 0.325 m³ ✓Volume of the semi-circular arch = 0.325 m³Note the two checks that the examiner looks for: for a semi-circular arch the rise always equals half the span, and the mean-radius formula V = πRmtb must agree with the annulus formula.
b) Quantity sheet and abstract of cost for a residential building
Measurement (quantity) sheet — quantities are taken out here:
S.N. Description of item No. Length (m) Breadth (m) Height / Depth (m) Quantity Unit 1 Earthwork in excavation in foundation 1 18.00 0.90 1.00 16.20 m³ 2 PCC 1:3:6 in foundation 1 18.00 0.90 0.15 2.43 m³ 3 Brickwork in foundation and plinth 1 18.00 0.50 0.90 8.10 m³ 4 Brickwork in superstructure 1 18.00 0.23 3.00 12.42 m³ Abstract of cost — quantities are brought forward and priced here:
S.N. Description of item Quantity Unit Rate (Rs) Amount (Rs) 1 Earthwork in excavation 16.20 m³ 350.00 5,670.00 2 PCC 1:3:6 in foundation 2.43 m³ 9,000.00 21,870.00 3 Brickwork in foundation and plinth 8.10 m³ 11,000.00 89,100.00 4 Brickwork in superstructure 12.42 m³ 12,500.00 1,55,250.00 Total cost of works 2,71,890.00 Add contingencies @ 3% 8,156.70 Add work-charged establishment @ 2% 5,437.80 Estimated cost 2,85,484.50 Rates shown are illustrative — in the examination take them from the district rate or from your own rate analysis, and say so.
c) Bill of quantities and its importance
Bill of quantities (BOQ). A tabulated schedule of every item of work in the project, giving a brief description, the estimated quantity, the unit, the rate and the amount. It is issued with the tender documents so that all contractors price the same quantities and their offers can be compared directly; it later becomes the document against which work is measured and paid.
Abstract of cost. The final summary sheet of the detailed estimate, in which the quantity of each item — brought forward from the measurement sheet — is multiplied by its analysed rate to give the amount, and the amounts are totalled. To that total are added contingencies (3–5%) and work-charged establishment (1.5–2%) to give the estimated cost of the work.
Bill of quantities Abstract of cost Purpose To invite and compare tenders, and to pay for work done To arrive at the total estimated cost for sanction Rates used Quoted by the contractor Obtained from the estimator's rate analysis Stage Tender and execution Preparation of the estimate Contains Item, quantity, unit, rate, amount The same, plus contingencies, establishment and the grand total ENCE 351 §1.4, §3.6 and §3.7.
- How are the following items of work measured?
- i) Plaster work
- ii) Cornice work
Solution
(i) Plaster work. Plastering is measured as the area of the finished surface, length × height, taken separately for each thickness and each mix. Measurement is taken between the finished faces; no deduction is made for the ends of beams, posts and rafters. Openings are deducted on the three-band rule:
Rules for deduction from plastering for openings in brick surfaces (IS 1200)
Plastering is measured as the whole face of the wall, and openings are then deducted on a three-band rule that depends on the area of the opening:
Area of the opening Deduction Jambs, soffits and sills Up to 0.5 m² No deduction Not measured Above 0.5 m² and up to 3 m² Deduct for one face only Not measured Above 3 m² Deduct for both faces (full area) Measured and added The logic is compensation. A small opening costs more labour at its edges than the plaster it saves, so nothing is deducted. A medium opening roughly balances on one face. Only a large opening genuinely saves plaster, and then the reveals have to be paid for separately.
Further points: no deduction is made for the ends of beams, posts and rafters; no deduction for openings up to 0.5 m² each even if there are many; and where the two faces of a wall are plastered with different mortars, the deduction is made separately for each face.
Unit: measured in m², paid per m².
(ii) Cornice work. A cornice is the projecting moulded band at the junction of the wall and the ceiling or at the eaves. Because its section is fixed by the drawing and only its length varies, it is measured in running metre along the centre line of the moulding, taken separately for each pattern and each girth. Mitres and returns at corners are included in the running length; no extra is paid for them.
Unit: measured in running metre (m), paid per m. Where the cornice is very large and its section varies, it may instead be measured in m² of girth or m³ of solid volume, but this must be stated in the specification.
ENCE 351 §1.2 and §1.4; IS 1200.
- a) Describe how will you prepare a preliminary estimate of a government office building for administrative approval of government including external services. The external services should be specified.
- b) How are the following items measured?
- i) Plaster work
- ii) Cornice work
Part a of this question also belongs to Chapter 3.Solution
a) Preliminary estimate of a government office building for administrative approval
At this stage no detailed drawings exist, so the cost is worked out from a single overall parameter using the plinth area method. The procedure is:
- Fix the requirement — the number of officers and staff to be accommodated, and hence the floor area needed, from the departmental space standards.
- Work out the plinth area of each floor, measured to the outer face of the walls, and total it for all floors.
- Obtain the plinth area rate (Rs per m²) from a recently completed building of similar type, specification and locality, and update it to current rates.
- Cost of the building = total plinth area × plinth area rate.
- Add the external services and other charges as percentages of the building cost.
- Prepare a brief report with a site plan, line drawings and the justification for the work, and submit it for administrative approval.
The external services and additional provisions to be specified are:
Item Usual provision Water supply and sanitary installation 8–10% of building cost Internal electrical installation 8–10% of building cost Architectural treatment / elevation work 1–2% Approach road and paving 1–2% Compound wall, gate and fencing lump sum or 1–2% Lawns, landscaping and tree planting 1–2% External water supply, sewer and electric line connections lump sum, as per site Furniture and fixtures 2–5% Contingencies 3–5% Work-charged establishment 1.5–2% Example — plinth area 3 floors × 400 m² = 1200 m² plinth area rate = Rs 25,000 per m² cost of building = 1200 × 25,000 = Rs 3,00,00,000 water supply & sanitary @ 8% = Rs 24,00,000 electrification @ 8% = Rs 24,00,000 approach road, compound @ 3% = Rs 9,00,000 ---------------- Rs 3,57,00,000 contingencies @ 3% = Rs 10,71,000 work-charged estt. @ 2% = Rs 7,14,000 ---------------- approximate estimated cost = Rs 3,74,85,000b) How the items are measured
(i) Plaster work — measured as the area of the finished surface in m², separately for each thickness and mix, with openings deducted on the three-band rule (no deduction up to 0.5 m²; one face for 0.5–3 m²; both faces plus jambs, soffits and sills above 3 m²). Paid per m².
(ii) Cornice work — measured in running metre along the centre line of the moulding, separately for each pattern and girth, mitres and returns included. Paid per m.
ENCE 351 §1.4, §3.1 and §3.6.
The rules below are the Indian Standard IS 1200 rules, which Nepalese departmental practice follows. They matter because they decide what is deducted and what is ignored — and that is what the marks are for.
General rules
- Linear dimensions are measured to the nearest 0.01 m, areas to the nearest 0.01 m² and volumes to the nearest 0.01 m³.
- Work of each description, and work executed in different situations (in foundation, in plinth, in superstructure, under water, in foul position, in liquid mud) is measured separately, because each carries a different rate.
- Different mortar proportions and different mixes are kept separate.
- Measurements are taken of the finished work in place; no allowance is made for wastage, which is already inside the rate.
Earthwork
Measured in m³ as length × breadth × depth of the trench, each dimension to 0.01 m. Excavation in different classes of soil (ordinary soil, hard soil, soft rock, hard rock) is measured separately, and so is excavation below water table. Surface excavation and surface dressing up to 15–30 cm depth are measured in m².
Concrete work
Measured in m³. No deduction is made for:
- the volume of reinforcement;
- openings up to 0.1 m² in area;
- the volume occupied by pipes, conduits and sheathing not exceeding 100 cm² in cross-section;
- small voids and the ends of embedded members of similar size.
No extra labour is allowed for forming those voids or openings either. Some texts quote 25 cm² rather than 100 cm² for embedded conduits; quote the figure your prescribed code gives and state it.
Brick work
Measured in m³ to 0.01 m³. No deduction is made for:
- openings each up to 0.1 m² (1000 cm²) in area;
- the ends of beams, posts, rafters, purlins and lintels up to 500 cm² (0.05 m²) in section;
- bed plates, wall plates and the bearing of chajjas and the like up to 10 cm in depth;
- drainage holes, iron fixtures, pipes and hold-fasts.
The bearings of floor and roof slabs are not deducted from the wall masonry. Rectangular openings are deducted in full. For a door or window carrying a small segmental arch, deduct only the rectangular portion up to the springing line — the segmental part is treated as solid, to allow for the extra labour of building the arch.
Half-brick and thinner walls are measured in m².
Plastering and pointing — the deduction rule
Measured in m² to 0.01 m²; ceilings, walls and different mixes separately. Deductions for openings follow a three-band rule, and no addition is made for jambs, sills and soffits except in the largest band:
| Area of one opening | Deduction | Jambs, sills, soffits |
|---|---|---|
| Up to 0.5 m² | No deduction | Not added |
| Over 0.5 m² and up to 3 m² | Deduct for one face only when both faces are plastered. If one face is plastered and the other pointed, deduct from the face with the lesser width of reveal; for equal reveals deduct 50% from each side. | Not added |
| Over 3 m² | Deduct from both faces | Measured and added |
Plaster on honeycomb brickwork is measured flat in m² without deducting the openings. White washing, colour washing, distempering and painting follow the same deduction rules as plastering.
Painting — multiplying factors for doors and windows
A panelled door is not a flat surface, so its painted area is obtained by multiplying the measured area of the opening by a factor. The area is measured flat, and the factor covers both faces unless stated otherwise.
| Description | Multiplying factor |
|---|---|
| Panelled shutter | 1.30 (each side) |
| Flush shutter | 1.20 |
| Fully glazed shutter | 0.80 |
| Partly panelled and partly glazed | 1.00 |
| Fully glazed steel door and window | 0.50 |
| Partly glazed and partly panelled steel door | 0.80 |
| Louvered / venetian shutter | 1.80 |
| Weather-boarding | 1.20 |
| Corrugated sheet (steel or A.C.) | 1.14 |
The pattern is worth remembering rather than the numbers alone: the more timber surface the shutter has, the higher the factor (louvered 1.80 > panelled 1.30 > flush 1.20); the more glass, the lower (fully glazed 0.80, and only 0.50 for a steel frame, because there is very little metal to paint).
Wood work
Areas to 0.01 m² and volumes to 0.001 m³. Frames (chaukhat) are measured in m³; shutters of specified thickness in m². Shoring and strutting timber is measured in m³; skirting, cornices, picture rails and similar mouldings in running metre.
Reinforcement
Measured in kg (or MT) of the finished bar in place. The length of each bar, including hooks, bends and laps, is measured and converted to weight using
No allowance is made for rolling margin or wastage, and binding wire is not measured separately — both are inside the rate. Bars of different diameters are kept separate.
Other finishing items
- Flooring: m² to 0.01 m²; types measured separately; dividing strips in running metre.
- Roof covering: m²; ridges, hips and valleys in running metre.
- Painting of pipes and poles: running metre, not m².
- Demolition and dismantling: areas in m² and volumes in m³, each class of work separately.
IS 1200 as summarised in Dawadi, Estimating ch.2 §2.1; multiplying factors from the same source, extended with the standard louvered, weather-boarding and corrugated-sheet values.
Sources consulted for this chapter
These are the references actually used in writing this chapter. Where a worked example is taken from one of them, the figure or the sheet is recomputed here from the stated dimensions rather than transcribed.
- IOE syllabus, ENCE 351 Estimating and Costing (Year III, Part II) — course code, hours and marks
- Er. Narayan Prasad Dawadi, Estimating and Costing lecture notes (IOE, Pashchimanchal Campus) — definitions, purpose and the data required for an estimate
- M. Chakraborti, Estimating, Costing and Specification in Civil Engineering — ch. I–II — principle of units, and the unit / mode of measurement table reproduced from IS 1200
- B. N. Dutta, Estimating and Costing in Civil Engineering — ch. 1 §1.7 — deduction for openings and bearings in masonry, and the rule that slab bearings are not deducted
- IS 1200 — Method of Measurement of Building and Civil Engineering Works — deduction rules for concrete, brickwork, plastering and painting
- Pandey & Katwal, Complete Manual of Estimating and Costing (T.U., B.E. Civil) — unit of measurement and unit of payment for the items asked in the papers
- Asst. Prof. Roshan Karki, Estimating and Costing slides, chapters 1–3 — introduction and purposes of estimating