← CM Home
Chapter 6

Construction Process [6 Hours]

Complete Chapter ~30+ Past Questions

6.1 Site Surveying and Preparation 20752072

PAST EXAM QUESTIONS:

  1. List down the various components for site preparation. [3] (2075 Bhadra)
  2. Explain the necessity of site surveying and preparation in construction project. List out components of site preparation. [3] (2072 Magh)
SITE Survey 1 Topography Contours, levels 2 Soil/Geology Bearing capacity 3 Access Roads, bridges 4 Utilities Water, power supply 5 Drainage Flood level, rivers 6 Climate Rain, temperature 7 Labor Local availability 8 Legal Land ownership, EIA
Fig 6.5 — Site Survey Checklist for Construction Projects

Construction work involves a huge amount of money, different types of human resources and time. Construction work is different from each other because of construction site, even when design and drawings are the same.

Temporary services are necessary to execute construction work: temporary offices, electricity, telecommunication, roadways (access road), drinking water, sanitation system, etc. Spaces should be allocated for heavy and costly equipment for their safety. Disposal of debris should also be considered.

Site Surveying 2075 2072

An inspection of an area where work is to be done to gather information for initiating construction work. It establishes reference points and marks that will guide the construction of structures. It can determine precise location, size and orientation of obstacles.

Equipment used: Levels, Total Station, Theodolites, Electronic Distance Measurement (EDM), GPS with computerization.

Elements of Construction Survey:

Construction Site Preparation 2075 2073 2072

The preliminary works to be done before starting construction. The site needs to be completed properly before the start of the construction process.

Clearing Vegetation Grubbing Roots/stumps Leveling Cut & fill Drainage Temp system Fencing Boundary Temp Roads Access
Fig 6.10 — Site Preparation Steps

Factors to be considered:

6.2 Job Layout 208120802079207820772075207320712069

PAST EXAM QUESTIONS:

  1. Prepare a job layout plant for a Hospital Building Construction Site with construction site area of 500m by 500m. [4] (2081 Shrawan)
  2. Define Job Layout plan with its example and figures. [3] (2080 Chaitra)
  3. What is job layout plan? Explain with typical schematic diagram for a housing project. [5] (2079 Chaitra)
  4. Prepare a job lay-out plan for constructing 1000 sqm area public building in a rectangular land (190 m × 125 m) with sufficient facilities. [4] (2079 Jestha)
  5. Explain the term Job Layout Plan. [3] (2078 Chaitra)
  6. What are the different factors that need to be consider during construction site planning process? [4] (2078 Kartik)
  7. Prepare a typical job layout for a multi-story building construction project. [3] (2077 Chaitra)
  8. Prepare a typical job layout of a Building Project. [4] (2075 Bhadra)
  9. List down the various components for site preparation, and prepare a typical arrangement facilities of a building construction project in Urban area of Nepal. [4] (2073 Bhadra)
  10. Prepare a typical job layout of a Building Project. [4] (2071 Bhadra)
  11. What is job layout? Discuss various factors to be considered in construction site planning. [2+6] (2069 Bhadra, Old Syllabus)

Facility Layout is simply how a facility is arranged to maximize processes that are not only efficient but effective towards the overall organizational goal. The specific requirements of a construction job — man, material, and machine — must be controlled and placed at a site in such a manner that:

Objectives of Layout Decision 2081 2080 2079 2078 2077 2075 2073 2071 2069

Ensure smooth flow of work, material, people, and information. Effective layouts also:

JOB Layout 1 Access Roads Entry/exit routes 2 Storage Areas Material yards 3 Office/Lab Site office, testing 4 Worker Camp Labor accommodation 5 Equipment Yard Parking, maintenance 6 Utilities Water, power, drainage
Fig 6.1 — Key Components of Construction Site Layout 📝 Asked

Primary Factors Affecting Job Layout

  1. Nature and type of work: Every construction project is unique. Job layout for headworks in hydropower differs from building construction.
  2. Access to the site: Facilitates transportation of construction materials and equipment at minimum cost.
  3. Nature of ground: Solid ground needed for equipment fixing and movement.
  4. Temporary roads: Must be constructed from nearest road head to site before starting construction.
  5. Construction methods: Precast/prefab needs extra casting yard; cast-in-situ does not.
  6. Construction material: If available naturally near site, no need for extensive storage planning.

Secondary Factors

  1. Accommodation for administration and residences
  2. Medical facilities
  3. Communication facilities
  4. Availability of services
  5. Opportunity for expansion
  6. Other external factors (political, cultural, socio-economic)

Practical Considerations for Job Layout

  1. Access to site: Separate entrance and exit. Track within site for easy movement.
  2. Storage of material:
    • Cement bags: minimum 15 cm above ground, covered with waterproofing material, 30 cm away from wall, use earliest arrival first
    • Bricks, tiles, concrete blocks: stacked on level ground, height should not exceed 2m
    • Aggregates: stored on hard surface in stacks (dimension ~2m × 2m × 0.5m)
    • Inflammable materials: stacked separately, protected from ignition
    • Explosives: kept in a safe place
    • Re-bars: kept away from moisture to prevent rusting
    • Timbers: stacked in well-ventilated sheds
    • Heavy items: stacked away from trenches
  3. Location of machinery:
    • Equipment should be kept near the material and place of use
    • Temporary shed for weather protection of costly equipment
    • Provision for fuel, lubrication, and maintenance
    • Adequate space for erection, removal, and shifting
    • Adequate parking facility
  4. Office location: Main office near the entrance.
  5. Security checkpoints: Located so materials/equipment cannot leave without proper authorization.
  6. Accommodation: For site manager, technical personnel, guards, and laborers.
  7. Miscellaneous: Drinking water, telephone, fencing, hoarding board.

For preparing a good job layout, the following records should be studied: site plan, working drawings, specifications.

Typical Job Layout Plan — Building Construction SITE BOUNDARY (Fenced) ACCESS ROAD ENTRY EXIT Guard BUILDING Under Construction Site Office + QC Lab Cement Store (Covered shed) Steel Yard (Raised platform) Sand/Aggregate (Open stacking) Equipment Yard Parking + Fuel Batching Plant Labor Camp Accommodation Toilet Water Tank + Generator Timber/ Formwork Debris Disposal First Aid INTERNAL CIRCULATION ROAD INTERNAL ROAD Parking N
Fig 6.11 — Typical Job Layout Plan for Building Construction 📝 Asked

6.3 Material Handling System 207420732072

PAST EXAM QUESTIONS:

  1. What is material handling system and why is it useful in construction work. [4] (2074 Bhadra)
  2. Write short notes on: Material handling system. [4] (2073 Bhadra)
  3. Explain the concept of material handling. [3] (2072 Magh)
  4. Write short notes on: Material handling system. [5] (2072 Ashwin)

Material Handling is concerned with solving the pragmatic problems involving the movement, storage, control and protection of materials, goods and products throughout the processes of cleaning, preparation, manufacturing, distribution, consumption, and disposal.

The focus is on the methods, mechanical equipment, systems and related controls used to achieve these functions.

Key Points of Material Handling 2074 2073 2072

Plan Route & method Receive Inspect & record Store Protect & access Handle Minimize movement Deliver To work point
Fig 6.2 — Material Handling System Flow

6.4 Financial Management & Cash Flow 2079207820772075207420732072207120702069

PAST EXAM QUESTIONS:

  1. Explain about the importance of financial and cash flow management for smooth running of construction project. [4] (2079 Shrawan)
  2. How does mobilization advance affect the cash flow of contractor? [2] (2078 Chaitra)
  3. Explain cash flow forecasting of a contractor depicting contract and contractor’s margin with neat diagram. [3] (2077 Chaitra)
  4. Explain about the cash flow management in construction project. [3] (2075 Bhadra)
  5. Discuss with examples cash-flow management during construction of project. [5] (2074 Bhadra)
  6. Write short notes on: Cash flow management in a construction project. [5] (2074 Magh)
  7. What is cash flow and how do you prepare it? Explain its importance. [6] (2073 Magh)
  8. Explain about the points to be dealt in financial management and cash flow management by a manager in a construction project. [Part of 10] (2072 Ashwin)
  9. What is cash flow management? [3] (2072 Magh)
  10. Define financial management. Show a typical cash flow diagram of a contractor after contract agreement. [1+3] (2071 Magh)
  11. Why cash flow management is necessary for a contractor. Draw a typical cash flow estimate of a contractor showing the most critical stage. [2+3] (2070 Magh)
  12. Write short notes on: Financial management. [4] (2070 Bhadra)
  13. Write short notes on: Balance sheet. [4] (2069 Bhadra, Old Syllabus)
FINANCIAL Management 1 Budgeting Cost estimation 2 Accounting Record keeping 3 Cash Flow In/out monitoring 4 Reporting IPC, Final Bill 5 Auditing Verification
Fig 6.7 — Functions of Financial Management

Financial Management 2072 2070

Financial management in construction involves planning, organizing, controlling, and monitoring financial resources to achieve project objectives within the approved budget.

Contractor's Cash Flow Diagram Inflow (+) Outflow (−) M1M2 M3M4 M5M6 M7M8 Income (IPC Payments) Expenditure (Materials, Labor)
Fig 6.4 — Contractor’s Monthly Cash Flow: Income vs Expenditure 📝 Asked

Types of Finance:

Financial managers are responsible for acquiring funds needed by a firm and directing those funds into projects that will maximize the value of the firm to its owners. They must determine best sources of financing and allocate resources among competing investment alternatives.

Cash Flow Management 2079 2075 2074 2073 2072 2070

The process of monitoring, analyzing, and adjusting a business's cash flows. It is a key component of a business — planning future cash requirements to avoid a crisis of liquidity.

Cash is the most important current asset for operations of the firm. It is an idle and non-earning asset. Therefore, the firm should keep just sufficient cash, neither more nor less. More cash balances reduce the rate of return on equity and hence reduce efficiency.

Cash Flow Components

Three components in the product lifecycle costing:

CASH FLOW Components 1 Material Cost 40-60% of total 2 Labor Cost 20-30% 3 Equipment 10-15% 4 Overheads 8-12% 5 Profit Margin 5-10%
Fig 6.9 — Components of Contractor’s Cash Flow

1. Initial Investment

The relevant cash outflow or cost of setting up the project.

Initial Investment = Cost of capital assets + Installation costs + Working capital margin + Preliminary & pre-operative expenses - Tax benefit on capital assets

2. Operating Cash Flows

The relevant cash inflows and outflows resulting from the project's life.

Operating cash inflow in a given year = Profit after tax + Depreciation + Other non-cash charges + Interest on long-term debt - Tax rebate

3. Terminal Cash Inflow

The relevant cash inflow occurring at the end of the product lifecycle on account of project liquidation.

Terminal cash inflow = Post-tax proceeds from sale of capital assets + Net recovery of working capital margin + Tax adjustment

Contractor's Construction Budget Breakdown

The project plan in the form of the master budget, which includes the profit and loss statements, balance sheet, and cash flow forecast. Budget shows allocated resources, schedule of work, and capital expenditure.

S-Curve

A graph showing cumulative earned value and cumulative production costs of a project over time. The gross operating profit = revenues - total cost of production. Revenue is the time-related cumulative value of earned production.

Balance Sheet Structure ASSETS Fixed Assets (Land, Building) Current Assets (Cash, Stock) Receivables (Debtors) Bank Balance LIABILITIES Owner's Equity (Capital) Long-term Loans Current Liabilities (Creditors) Reserves & Surplus Assets = Liabilities + Owner’s Equity
Fig 6.6 — Balance Sheet: Assets = Liabilities + Equity
Cumulative % Time Planned Actual Slow Start Peak Progress Finishing 100% 0%
Fig 6.3 — S-Curve: Planned vs Actual Progress

Cash Flow Forecasting of Contractor 2077

Even though regular and interim payments are made as per contract, both client and contractor sometimes face liquidity problems. Shortage of funds affects project progress and can lead to work stoppage.

The project funding pattern is determined by making a cash flow forecast that predicts the monthly net effect of cash inflow and outflow.

Cash Flow Diagram of Contractor 2071 2070

The cash flow diagram defines sources from which contractor receives funds and how they are utilized:

SymbolMeaningDescription
VValue curve (Earned Value)Value of project work done
CCost curve (Production cost)Cost incurred in construction (direct costs)
RRevenue curve (Cash inflow)Amount received from clients on regular intervals per contract agreement
EExpenditure curve (Cash outflow)Expenditures in procurement, payment to vendors, etc.
NNet cash flow curveDifference between R and E
Contractor’s Cash Flow Diagram (5 Curves) Cumulative Amount (Rs) TIME (Months) V (Value) C (Cost) R (Revenue) E (Expenditure) N (Net CF) Capital Lock-up Zone (N < 0) V−C = Margin Completion Key Relationships: V − C = Contract Margin (Profit) N = R − E = Net Cash Flow N < 0 → Capital Lock-up R lags V (payment delay) E leads R (pay suppliers first)
Fig 6.12 — Contractor’s 5-Curve Cash Flow Diagram (V, C, R, E, N) 📝 Asked

Key relationships:

A contractor uses this graph to prepare financial statements periodically. Client cash flow study forecasts the extent of funds required for meeting payment commitments. Contractor's cash flow forecast is more complex, catering to all inflows and outflows including working capital, equipment, material purchase cost, inventory cost, manpower mobilization cost, temporary works, and utility installation.

Effect of Mobilization Advance on Cash Flow 2078

Past Exam (2078 Chaitra): How does mobilization advance affect the cash flow of contractor? [2]
Mobilization Advance: 10-20% of Contract Amount Given upfront • Recovered by deducting from IPCs (usually 10-20% per bill) ✓ Helps contractor's cash flow ✓ Bank guarantee required
Fig 6.8 — Mobilization Advance: Amount, Recovery & Impact on Cash Flow

Mobilization advance (typically up to 20% of contract price as per PPA/PPR) significantly impacts the contractor’s cash flow:

Balance Sheet 2069

Past Exam (2069 Bhadra): Write short notes on: Balance sheet. [4]

A balance sheet is a financial statement that reports an organization’s assets, liabilities, and shareholders’ equity at a specific point in time. It provides a snapshot of the financial position of a business.

Fundamental equation:

Assets = Liabilities + Owner’s Equity

Assets (What the company owns)Liabilities + Equity (What the company owes)
Current Assets:
• Cash and bank balances
• Accounts receivable (unpaid bills from clients)
• Inventory (materials in stock)
• Advance payments

Fixed Assets:
• Land and buildings
• Equipment and machinery
• Vehicles
• Furniture and fixtures
(Less: Accumulated depreciation)
Current Liabilities:
• Accounts payable (unpaid supplier bills)
• Short-term loans
• Accrued expenses
• Mobilization advance (unrecovered portion)

Long-term Liabilities:
• Long-term loans
• Bonds payable

Owner’s Equity:
• Share capital
• Retained earnings
• Reserves

For a construction contractor, the balance sheet helps assess financial health — whether the company has sufficient assets to cover its liabilities, and whether it has adequate working capital (Current Assets − Current Liabilities) to fund ongoing projects.

Important Things to Consider

Marks Distribution: 3 Marks (Low Weightage)

SectionTopicFrequencyPriority
6.2Job Layout10 timesHighest
6.4Financial Management & Cash Flow10 timesHighest
6.3Material Handling System4 timesHigh
6.1Site Surveying and Preparation2 timesMedium

Key Exam Patterns

  • Despite only 3 marks allocation, Job Layout and Cash Flow are heavily asked (10 times each) — these sections are critical
  • Job Layout: Know definition, purpose, principles, and what to show on a site layout drawing — storage areas, access points, offices, equipment positions
  • Cash Flow: Understand the 5-curve system (V, C, R, E, N) and their relationships; V − C = Contract Margin, N = R − E = Net Cash Flow
  • Short answer likely: Given only 3 marks, expect concise questions on job layout features or cash flow diagram explanation

Must-Know Points

  1. Site survey procedure: Pre-survey Preparation → Survey Activity → Survey Analysis → Design and Solution → Implementation
  2. Setting out: Locating points on ground as per drawings using reference points; assigning locations for materials, equipment, facilities
  3. Job layout elements: Entry/exit points, material storage, offices, equipment positions, guard house, toilets, circulation areas, emergency access
  4. Material handling principles: Planning, systems, material flow, simplification, gravity, space utilization, unit size, mechanization, safety, standardization
  5. Cash flow 5 curves: V (earned value), C (production cost), R (revenue/inflow), E (expenditure/outflow), N (net cash flow)
  6. Key relationships: V − C = Contract margin; N = R − E; Negative net cash flow = Capital lock-up
  7. Mobilization advance: Up to 20% of contract price; reduces capital lock-up; recovered from running bills (IPC); shifts N-curve upward
  8. Balance sheet equation: Assets = Liabilities + Owner’s Equity. Current Assets − Current Liabilities = Working Capital
  9. Contractor cash flow: Working capital, equipment, material purchase, inventory, manpower, temporary works, utilities