Specification [6 Hours]

Sections 12.1 – 12.5 ~41 Past Questions

12.1 Purpose of Specifications 20792072

PAST EXAM QUESTIONS:

  1. What are purpose of specification? [Part of 7] (2079 Shrawan)
  2. Write the purposes of specification writing. [Part of 4]
  3. State the purpose of specification. [Part of 5] (2072 Ashwin)
PURPOSE of Specifications 1 Quality Control Define standards 2 Fair Bidding Equal comparison 3 Dispute Prevention Clear expectations 4 Cost Estimation Material & workmanship 5 Contract Compliance Legal basis
Fig 12.2 — Purpose of Specifications in Construction

Specification is the document where the level of intended quality is specified. They are clear concise descriptions of materials and workmanship including the methods of construction and precautions to be taken.

Purpose of Specification 2079 2072

12.2 Types of Specifications 20782077207420712070

PAST EXAM QUESTIONS:

  1. Define specification and explain its types. [4] (2078 Chaitra)
  2. Enunciate different types of specification. [1] (2079 Jestha)
  3. Enunciate different types of specification. [2] (2078 Kartik)
  4. Discuss the types of specification. [Part of 5] (2074 Magh)
  5. What are different types of specification you are aware of? [Part of 6] (2074 Bhadra)
  6. Explain detailed specification. [4] (2071 Magh)
  7. Define and differentiate between general and detailed specification. [2] (2077 Chaitra)
  8. Differentiate between general and detailed specification. [2] (2070 Magh)
SPECIFICATION Types 1 Contract Spec Project-specific 2 Standard Spec IS, BS, ASTM 3 Performance Spec End result oriented 4 Manufacturer's Product datasheet
Fig 12.1 — Types of Specifications in Construction

Depending on the purpose served, specifications can be grouped as follows:

a. Contract Specification 2078 2074

Contract specification is developed for a construction or project to accompany the work. Divided into two types:

Scope What to do Materials Standards Workmanship Method Testing QC tests Measurement Units Payment Rate basis
Fig 12.7 — Structure of a Contract Specification

i. General Specification

ii. Particular/Detailed Specification

b. Standard Specification

Generally prepared and published by organizations which cover specific materials used by a specific trade or segment of the construction industry. Examples: Indian Standard (IS), Nepal Standard (NS).

c. Overall Performance Specification

Details in comprehensive but general terms what the client is looking for.

d. Manufacturer's Specification

Specification prepared by manufacturers for their products.

12.3 Importance of Specifications 20792078207520742073207120702069

PAST EXAM QUESTIONS:

  1. Explain the roles of specifications in any construction project. [3] (2079 Chaitra)
  2. Why specification is important in road construction project? Explain. [2] (2078 Kartik)
  3. Why specification is important in construction contracts? [2] (2075 Bhadra)
  4. Write the importance of specification. [Part of 6] (2074 Bhadra)
  5. What are the importance of specification and discuss different elements used in writing a detailed specification? [Part of 5] (2074 Magh)
  6. Why specification is important in construction contracts? [2] (2073 Bhadra)
  7. Discuss the importance of specification in construction work. [Part of 6] (2073 Magh)
  8. Explain the importance of specification. [3] (2071 Bhadra)
  9. Explain the importance of Specifications in Construction Works. [4] (2070 Bhadra)
  10. Explain the importance of specification in construction work. [4] (2069 Bhadra)
IMPORTANCE of Specification 1 Basis of Contract Legal document 2 Quality Assurance Material + workmanship 3 Avoid Ambiguity Clear instructions 4 Cost Control Prevent extras 5 Standard Reference IS/BS codes
Fig 12.3 — Importance of Specifications

Specification is an important document in contract management. Without specification, the tender/contract document is incomplete, baseless, and invalid.

12.4 Specification Writing: Technique & Standards 207920782075207220702069

PAST EXAM QUESTIONS:

  1. What are the principles of writing specification? [1] (2079 Jestha)
  2. What are the principles of writing the specification? [4] (2078 Kartik)
  3. What are the principles of writing technical specification for construction works? [3] (2079 Chaitra)
  4. Discuss on techniques of writing specification. [4] (2078 Chaitra)
  5. Write the techniques of specification writing. [Part of 5] (2072 Ashwin)
  6. Write down the major techniques that you follow for writing specification. [3] (2075 Bhadra)
  7. Write down the main techniques that you follow for writing specification. [4] (2069 Bhadra)
  8. Write a note on the art and science of writing Specifications covering: (i) Necessity (ii) Procedure of drafting (iii) What to write and avoid. [6] (2070 Bhadra)
  9. Explain with examples why international standards are used in drafting of specification. [2] (2072 Magh)

Principles/Techniques of Specification Writing 2079 2078 2075 2072 2070 2069

  1. Specification language: Simple and clear. Same tense; use of a noun is preferable
  2. Brief as possible: Standard articles specified by references and code numbers
  3. Fairness: Fair to all parties. Proper sharing of risks
  4. Express: Requirement of each and every item
  5. Avoid repetition: Repetition of information is avoided to avoid the possibility of contradiction
  6. Inclusion of proper paragraphs:
    • Specification of materials
    • Combinations of materials
    • Preliminary works prior to construction
    • Installation of materials
    • Test, if any
    • Clearing on completion
    • Mode of measurements
  7. Standard size and patterns: Commercial sizes should be specified; unusual dimensions should be avoided
  8. Cross-references: Should be minimum as possible
  9. Quality: Quality of materials and workmanship should be specified
  10. Nothing impossible: Nothing impossible to achieve or not intended to be enforced should be specified
  11. Brand options: While specifying brand of materials, options and choices should be given
Study Drawings Define Materials Set Standards IS/BS Describe Method Specify Testing Review & Finalize
Fig 12.4 — Specification Writing Process Steps

12.5 Typical Examples of Specifications 208120802079207720732072207120702069

PAST EXAM QUESTIONS:

  1. Write detailed specification of First Class Brick work with (1:6) cement sand mortar. [2+6] (2080 Chaitra)
  2. Write detailed specification for Brick work in 1:4 cement sand mortar. [7] (2079 Shrawan)
  3. Prepare detailed specification for earth work in excavation in sandy soil for isolated footing. [6] (2079 Jestha)
  4. Write a detailed specification of cement plaster of 1:4 in brick wall. [4] (2077 Chaitra)
  5. Write down specification paragraphs for first class brick works in cement mortar of 1:4. [4] (2072 Magh)
  6. Key Points: Brick Work Specification Material Requirements • First class bricks (IS 1077) • Compressive strength ≥ 75 kg/cm² • Water absorption < 20% • Cement: OPC 43 grade Workmanship • Bricks soaked in water 2 hrs • English bond / Flemish bond • Mortar: 1:4 or 1:6 (C:S) • Curing: min 7 days
    Fig 12.5 — Brick Work Specification: Key Points
  7. Write down the specification for Stone masonry work in 1:6 mortar. [4] (2073 Bhadra)
  8. Write down detailed specification for cement sand mortar 1:6. [Part of 6] (2073 Magh)
  9. Write a detailed specification of brick work in cement sand mortar. [5] (2071 Bhadra)
  10. Write detailed specification for brick work in 1:4 cement sand mortar. [7] (2070 Magh)
  11. Write detailed specification of: (i) RCC with M20 concrete in column (ii) Brick work in 1:6. [4+4] (2069 Bhadra)
  12. Write detailed specification of M20 RCC works.

A0) Specification for Earthwork in Excavation 2079

Past Exam (2079 Jestha): Prepare detailed specification for earth work in excavation in sandy soil for isolated footing. [6]

Scope

This specification covers all earthwork in excavation for isolated footings in sandy soil, including pit excavation, trimming, levelling, and disposal of excavated material as directed by the Engineer.

Site Preparation

Excavation

Dewatering

In sandy soil, groundwater is likely to seep into excavation pits. Adequate dewatering arrangements (sump pumping, well-point system) shall be made by the contractor at his own cost to keep the excavation dry during construction.

Disposal of Excavated Earth

Backfilling

After completion of foundation work, the sides of the pit shall be backfilled with approved material in layers not exceeding 150 mm, each layer watered and compacted to achieve required density.

Measurement

Earthwork shall be measured in cubic meters based on the actual dimensions of the excavation as per drawings. No extra payment for shoring, dewatering, or removal of surplus earth unless specified in the BOQ.

A1) Specification for Cement Sand Mortar 2073

Past Exam (2073 Magh): Write down detailed specification for cement sand mortar 1:6. [Part of 6]

Materials

Proportioning

Cement and sand shall be proportioned by volume using proper gauge boxes. For 1:6 mortar, one part of cement to six parts of sand by volume. For 1:4 mortar, one part cement to four parts sand.

Mixing

Use

Measurement

Mortar is not measured separately; it is included in the measurement of the item for which it is used (brickwork, plastering, masonry, etc.).

A) Specification for Brick Work in Cement Mortar 2080 2079 2072 2071 2070 2069

Bricks

Shall be chimney burnt hand-cast bricks of first-class quality, approved by the Engineer, free from all impurities such as lime, iron, and other deleterious salts. These shall be well-burnt, sound, and shall give a ringing sound when struck with a mallet. The bricks shall conform to IS 3626 with IS 1077 or NS 01-2035.

Brick samples shall be randomly selected for testing — not less than 5 bricks per one thousand for each lot of construction work.

Cement Mortar

Cement mortar shall be mixed in the specified proportion. Portland Cement shall be used, conforming to IS 1958 or NS 049-2041.

Sand

Sand shall be natural river sand or pit sand conforming to IS 383-1952 or NS 051-2041. Sand shall be clear, sharp-grained, and free from organic matters. It shall be well washed if containing more than 5% clay, dust.

Water

Potable water shall be used for mixing mortar and curing.

Mixing

Cement and sand shall be mixed in the required proportion (e.g., 1 part cement : 4 parts sand) by weight. Mix in a clean, dry platform till bubbles cease to come up.

Laying

Bricks shall be laid in cement mortar with frog upward. Bricks shall be laid flush in cement mortar. The courses shall be truly horizontal. Joints shall be uniform in thickness. All joints shall be well filled with mortar.

Scaffolding

Scaffolding shall be sufficiently strong for all construction and must be approved by the engineer.

Curing

The brickwork shall be continuously kept well watered for at least 14 days after laying. At no time during the curing period shall the mortar be allowed to dry.

Measurements

The measurement shall be computed on the basis of length, height, and thickness. It is measured on the finished work. No deductions shall be made for openings of areas less than 0.1 sq.m and for bearings of lintels, beams, girders, and holdfast blocks.

B) Specification for RCC Works 2069

Materials

Materials shall be of the qualities specified and delivered to works at least 7 days before required for use. Water used in mixing shall be free from injurious acids, alkalis, organic material, or other deleterious substances — as clean as drinking water.

Key Points: RCC Works Specification Materials • OPC 43/53 grade cement • Clean, graded aggregates • TMT bars (Fe 500/500D) • W/C ratio: 0.40-0.50 • Slump: 50-100mm (general) Execution • Mix design as per IS 10262 • Cover: 25-50mm (beams) • Vibration: needle vibrator • Cube test: 3 cubes / 50 m³ • Curing: min 14-28 days
Fig 12.6 — RCC Works Specification: Key Points

Cement

Portland cement complying with IS 1967. Delivered in packages with unbroken seal, marked with brand name and manufacturer. Stored in a dry place. Set cement removed immediately from work at contractor's expense. Tests shall be made as per IS specifications.

Aggregates (IS 383-1970)

General: Aggregates shall consist of naturally occurring sand and crushed stone. They shall be strong, dense, durable, clean, and free from veins. Flaky and elongated pieces should be avoided. Shall not contain harmful materials such as iron pyrites, coal, mica, shale, clay, alkali, glass fragments, seashells, or organic impurities.

Fine Aggregates: Natural sand or sand derived by crushing reliable gravel or stone, free from coagulated lumps. Shall contain no more than 3% silt on total weight by sedimentation test. Clay lumps, shale, soft fragments, and other deleterious substance not more than 5%.

Coarse Aggregates: Crushed stone, angular in shape. Friable, flaky, and laminate particles limited. 24-hour immersion weight gain not more than 10% for plain concrete. Los Angeles Rattler Test wear at 500 revolutions not more than 50%.

Measurement and Proportioning

Aggregate measured by weight or by volume (if approved) in a gauge box of correct and approved size. Cement measured by weight — one or more complete bags of 50 kg per batch. Normal proportions shall comply with specified quantities. Range: 1 part fine aggregate to 1.5 parts coarse aggregate up to 1 part fine to 2.5 parts coarse.

Reinforcement

TMT bars conforming to IS 1786-1966 or IS 1139-1966. MS bars conforming to IS 432-1966. Item includes supplying and fixing with 18 gauge MS binding wire. Reinforcement shall be free from pitting, loose rust, paint, oil, grease, or adhering concrete.

Mixing

Cement and aggregates thoroughly mixed together in proportions in a batch mixer. Mixed till uniform color. Mixing time inversely proportional to speed. Not remixed with addition of cement or water.

Cube Tests

During progress of work, 15 cm cubes made as per IS 1964 and tested per IS 516-1964.

Consistency/Workability

Determined by making trial mixes with dried aggregates. Workability checked at frequent intervals by slump test at commencement of each grade of concrete placing.

Formwork

Supply, erection, and removal of all types of formwork including props, struts, strutting, wedging, form oil, sealing. Measured in square meter.

Placing

Time between adding water and concrete placing operation shall not exceed 30 minutes. Concrete shall not be dropped from a height that may cause separation. Each layer compacted by ramming, tamping, or vibration to form dense surface free from honeycombing. Vibrators at about 450 mm centers.

Cover of Concrete

Curing

Immediately after placing, concrete protected from loss of surface moisture for seven days minimum (Portland cement). Methods:

Measurement

Calculated weight in kg from sizes and lengths of bars. No allowance for cutting waste, rolling margin, or tolerances. No hooks required for ribbed steel.

C) Specification for Gabion Works

Gabions consist of steel wire mesh crates. Steel wire shall comply with IS: 280-1962. All wire galvanized with extra heavy coating by electrolytic process. Wire woven into hexagonal mesh with minimum 3 twists.

Gabion & Stone Masonry Spec: Key Points Gabion Works • GI wire mesh boxes (2×1×1m) • Stones: 150-300mm, hard • Bracing wires at 300mm c/c Stone Masonry • Coursed rubble/ashlar • Mortar 1:4 or 1:6 (C:S) • Header stones every 1m
Fig 12.9 — Gabion & Stone Masonry Specification

Assembly

Crates assembled by binding edges together using binding wire. Interval between laces approximately at regular spacing.

Filling

Crates placed in final position before filling. Vertical corners kept square by inserting 20 mm steel bar. Stones individually placed, bedded and bonded as in dry random rubble masonry. No stones tipped into crate. When filled, lids closed and bound with binding wire.

D) Specification for Stone Masonry Works 2073

Stone shall be clean, hard, unweathered. Length of any stone shall not exceed three times its breadth, and breadth shall not exceed 150 mm or 3/4th the wall thickness. Spalls not exceeding 2% of the wall surface area may be used for filling voids.

Bondstones: Minimum 10% by volume. Shall measure minimum 150×150 mm on exposed face and 450 mm into the wall. At least one bondstone in every 0.8 m².

Stones shall be hammer/chisel dressed. Natural bed shall be at right angles to the direction of load. Cement, sand, water as per brickwork requirements. No unbroken boulder used in masonry. Stone samples submitted to engineer for approval.

E) Specification for Plaster Work 2077

Materials

Cement and sand as specified. For example, cement mortar 1:4 (1 cement : 4 sand) or 1:3 by volume. Mixing in mechanical mixer unless hand mixing approved.

Plaster Work Specification: Key Points • Surface cleaned, joints raked 12mm deep, wetted before plastering • Two coats: Base coat (12mm, 1:4) + Finishing coat (6mm, 1:3) • Thickness: Internal 12mm, External 20mm, Ceiling 6mm • Curing: minimum 7 days continuous moist curing
Fig 12.8 — Plaster Work Specification Highlights

Workability

Mixing and Using Period

All mortar and grout shall be used within 2.5 hours of initial mixing. No mortar or grout used after it has begun to set. If mortar stiffens from evaporation, it may be re-tempered by adding water and remixing.

Plaster Work

Curing

By keeping plastered surface damp on all exposed faces. Curing starts during application and continues for not less than 7 days. In hot weather, all finished work shall be covered or wetted.

Measurement

Measured in square meter. No deductions made for openings up to 0.5 m².

F) Specification for Painting Work

Preparation

Painting Work Specification • Surface: Clean, dry, smooth, free from dust and oil • Apply: 1 primer + 2 coats of approved paint (min 24hr gap) • Coverage: as per manufacturer recommendation • Types: Distemper (internal), Enamel (wood/metal), Emulsion (walls)
Fig 12.10 — Painting Work Specification Highlights

Application

After preparing the surface, priming coat shall be applied as per manufacturer's printed instructions.

Measurement

Measured in square meter (flat). Include for two or more coats inclusive of all labor and materials complete.

Important Things to Consider

Marks Distribution: 6 Marks

SectionTopicFrequencyPriority
12.5Typical Specification Examples (Brick, RCC, Plaster)11 timesHighest
12.3Importance of Specifications10 timesVery High
12.4Specification Writing Techniques & Standards9 timesVery High
12.2Types of Specifications8 timesVery High
12.1Purpose of Specifications3 timesMedium

Key Exam Patterns

  • Writing detailed specification: Asked 11 times — practice writing specifications for Brick Work (1:4 and 1:6), RCC M20, Cement Plaster, Stone Masonry, Earthwork
  • 6-7 mark practical question: "Write detailed specification for Brick Work in cement sand mortar 1:4" — most common exam question
  • Importance + techniques combo: Often asked together as 5-6 mark question
  • Differentiation: General vs Detailed specification — asked multiple times

Must-Know Points

  1. Types: General Specification (brief, for common works) vs Detailed/Particular Specification (specific to each item, with materials, proportions, workmanship)
  2. Purpose: Define quality, quantity, materials, workmanship standards; avoid disputes; basis for measurement and payment; legal document
  3. Writing techniques: Use imperative mood, be specific, refer to standards (NS/IS/BS), avoid ambiguity, specify tolerances, include measurement method
  4. Brick Work specification structure: Materials (brick type, mortar ratio) → Preparation → Laying (English/Flemish bond) → Joints → Curing → Measurement
  5. RCC specification structure: Materials (cement, aggregates, water, steel) → Mix design → Formwork → Placing → Compaction → Curing → Measurement
  6. Mortar usage: Must be used within 2.5 hours of mixing; no mortar after it begins to set; re-tempering allowed if stiffened from evaporation
  7. Measurement: Brick work in cubic meter; plaster in square meter; earth work in cubic meter